Appraisal, approval of investment policies and decisions on public investment programs and projects

DNUM_BFZAGZCABF 18:29

(Baonghean.vn) - Nghe An Provincial People's Committee has just issued Official Letter No. 3766/UBND-XD on appraisal, approval of policies and investment decisions for public investment programs and projects. The content of the Official Letter clearly states.

Dear:

- Departments and agencies;

- People's Committees of districts, cities and towns

- Project management boards with construction investment of the Province

Pursuant to Official Dispatch No. 3482/BXD-HDXD dated December 30, 2014 of the Ministry of Construction on the implementation of the Construction Law, the Provincial People's Committee issued Official Dispatch No. 846/UBND-XD dated February 6, 2015 on a number of regulations in the construction field implementing the Construction Law No. 50/2014/QH13.

On March 2, 2015, the Ministry of Planning and Investment issued Official Dispatch No. 1101/BKHDT-TH guiding the approval of investment policies and decisions for public investment programs and projects. Considering the request of the Department of Planning and Investment in Official Dispatch No. 940/SKHDT-TH dated June 1, 2015 on a number of contents related to the implementation of the Law on Public Investment, the Law on Construction and guiding documents of the Central Ministries and branches, the Provincial People's Committee has the following opinions:

While waiting for the Government to issue detailed Decrees implementing the Law on Public Investment and the Law on Construction, the Provincial People's Committee requests the Departments, Branches, People's Committees of districts, cities, towns and related entities to implement construction investment, to strictly implement the guidance of the Ministry of Construction in Official Dispatch No. 3482/BXD-HDXD dated December 30, 2014; Official Dispatch No. 1101/BKHDT-TH dated March 2, 2015 of the Ministry of Planning and Investment guiding the approval of policies and investment decisions for public investment programs and projects.

Regarding the order of preparation, appraisal and decision on investment in programs and projects: implement according to the provisions in Section 2, Chapter II of the Law on Public Investment and according to the instructions in Point 2, Section III of Official Dispatch No. 1101/BKHĐT-TH dated March 2, 2015 of the Ministry of Planning and Investment, with specific assignments as follows:

- For public investment programs decided on investment policy by the Provincial People's Council and public investment projects without construction components approved by the provincial level for investment decisions and other projects assigned by the Provincial People's Committee, the Department of Planning and Investment is the agency in charge of advising the Provincial People's Committee to appraise the Feasibility Study Report and approve the investment decision.

- For public investment projects with construction components approved by the provincial level for investment decisions, the Department of Construction shall appraise the technical part of the project Feasibility Study Report or the Technical Economic Report for small-scale projects; the Department of Planning and Investment shall appraise mainly the effectiveness of the public investment project, capital sources and the ability to balance capital for implementation, as a basis for consideration of arrangement in the public investment plan.

During the implementation process, if there are any difficulties or problems, they must be promptly reported to the Provincial People's Committee for consideration and specific guidance, or reported to the Government and Central Ministries for implementation opinions./.

TM.UBND

Chairperson

Nguyen Xuan Duong