Settlement village lies abandoned in the middle of the forest.

December 15, 2015 09:06

(Baonghean.vn) - The project to build a resettlement village for 54 ethnic minority households in the Thung Chanh area (Tho Son - Anh Son) has been underway for many years but remains unfinished. The only completed item, the 3km road leading to the village, is also severely damaged and degraded.

Đường vào dự án định canh, định cư vùng Thung Chanh
The project was implemented according to Decision 33/2007/QD-TTg of the Prime Minister. Finding the Thung Chanh resettlement project area is not easy; many local residents, when asked, were unaware of the project despite it being approved by the competent authorities in 2009 and implemented in 2011. (In the photo: The inter-village road of Tho Son commune leading to the Thung Chanh resettlement project area.)
Đường rộng hơn 2m, cây cối rậm rạp
This is a gravel road, a single component of the project, which received a total investment of over 2.7 billion VND and is nearly 3km long. According to the design, the road surface should be 3.5m wide, but many sections are now obscured by bushes, leaving it only slightly wider than 2m.
Một trong những cầu tràn đã bị nước lũ cuốn trôi.
Along the project route, there are 5 overflow bridges, 2 of which have collapsed and been swept away by floodwaters.
Điều tréo nghoe là cầu tràn này lại được xây dựng song song với dòng suối.
Speaking about the overflow bridge on the project route, officials and residents in the area humorously parodied the song "Boat and Sea," saying: "The bridge is in one place, and... the ravine is in another."
14.jpg
In reality, due to the poor structure and construction quality of the bridge, just one flood can wash it away, leaving behind exposed concrete slabs.
b
The bridge was damaged, so people had to wade through the stream to get to their production areas.
3.jpg
This small culvert has also eroded and could collapse at any time if there is heavy rain and flooding.
Tuyến đường giao thông vào khu tái định cư được đầu tư hơn 2 tỷ đồng để đổ cấp phối nhưng đến nay không khác gì lối mòn.
The surface of the road leading to the resettlement area is damaged in many sections, appearing only as worn-out patches.
Có đoạn đường nay đã bị sạt lở và chỉ còn bụi rậm.
Some sections of the road have even been damaged by landslides and are now just overgrown with bushes.
Do khu tái định cư chưa được xây dựng nên nhiều hộ phải làm lán trại ngay trong rừng để thuận tiện cho việc sản xuất.
Some residents of Tho Son commune, especially the Thai ethnic minority in Khe Trang Ha and Khe Trang Thuong villages, due to a lack of arable land, have built makeshift shelters in the Thung Chanh area even though the resettlement area has not yet been planned.
Gia đình anh Lộc Văn Công (xóm 1, xã Thọ Sơn) là một trong 54 hộ đăng ký xin được tái định cư nhưng chờ 6 năm nay vẫn không thấy dự án triển khai.
The family of Mr. Loc Van Cong (Khe Trang Ha hamlet, Tho Son commune) is one example. Mr. Cong is one of 54 households that registered to be resettled but "have been waiting for six years and still haven't seen any progress."
Hiện gia đình anh đang ở nhờ nhà của bố mẹ, cách lán trại gần 10km. Do đường đi lại xa nên ảnh hưởng đến hoạt động sản xuất của gia đình anh.
Every day, Mr. Cong's family has to travel about 10km from their home to their family's makeshift camp for production.
16.JPG
When asked about the project and the quality of construction of the road and bridge in Khe Trang Ha hamlet, Mr. Loc Van Hai replied that the people were too tired of waiting for the project; and the construction quality was extremely poor.

Nhat Lan - Pham Bang