Expedite the progress of the Song Lam cement project.

November 19, 2015 14:29

(Baonghean.vn) - Due to favorable weather conditions, at the Song Lam Cement Plant construction site (Do Luong district), the construction units are concentrating 1,200 experts, technicians, workers, and modern equipment and machinery to accelerate the construction progress.

Công trường thi công Nhà máy xi măng Đô Lương
Construction site of Do Luong Cement Plant
lll
Construction of heat exchanger tower system

This is one of the key projects in Nghe An. Hoang Phat Vissai Group (the investor) always ensures all requirements for construction are met, such as: internal roads; electricity and water systems for construction; arrangement of excavation and leveling equipment, and storage yard leveling; ensuring concrete supply; and has completed over 1800/1830 concrete bored piles (18/20 main items completed). Construction is currently underway on the clay storage facility and AQC boiler for Line B (waste heat and exhaust gas power generation).

Thi công khu nhà làm việc tại nhà máy
Construction of pillars at the project.


The Song Lam Cement Plant project has a capacity of 18,000 tons/day, with Phase 1 (from 2015 - 2017) consisting of two production lines with a total capacity of 12,000 tons of clinker/day (equivalent to 4 million tons of cement/year). Currently, the investor and contractor are actively working to ensure the project stays on schedule.

Hoang Vinh