Speed up the progress of the different level intersection between National Highway 1 - National Highway 48B - Lach Quen Port
(Baonghean.vn) - On the morning of March 1, under the chairmanship of Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee, the Provincial People's Committee held a working session on the progress of site clearance for the investment project to build a grade-separated intersection between National Highway 1 and National Highway 48B and the section of National Highway 48B connecting from the intersection to Lach Quen.
Also attending were representatives of the departments: Natural Resources and Environment, Finance, Construction, Provincial People's Committee Office, Quynh Luu district, Joint Venture of CTGT Construction Corporation 4 and Corporation 319.
![]() |
Vice Chairman of the Provincial People's Committee Huynh Thanh Dien chaired the meeting. |
Investment project to supplement the construction item of the grade-separated intersection between National Highway 1 and National Highway 48B and the section of National Highway 48B connecting from the intersection to Lach Quen port under the National Highway 1 expansion project, section Km 368+400 (Nghi Son) - Km 402+330 (Cau Giat), Thanh Hoa and Nghe An provinces under the form of BOT contract approved by the Ministry of Transport in Decision No. 4195/QD-BGTVT dated November 25, 2015, with QL1A BOT 2TV Company Limited Cienco4 - TCT319 as the investor.
![]() |
BOT representative reports on project progress. |
The project has a total investment of 371.11 billion VND. The total length of the entire route is about 12.4 km, of which the starting point is at Km0+00 (QL48B, Lach Quen port) in Quynh Thuan commune, the end point is at Km12+500, QL48B intersecting with the turnoff to Cau Giat station in Cau Giat town. Overpass location: Km11+526.66 on QL48 intersecting with QL1 at Km404+309 in Cau Giat town.
After the groundbreaking day (December 25, 2015), the work of installing GPMB stakes and road boundary markers at the project has been completed and handed over to the GPMB Council of Quynh Luu district. The BOT Company and Design Consultant have handed over to the GPMB Compensation Council of Quynh Luu district the entire set of completed drawings for installing GPMB stakes and road boundary markers of the project. The investor has directed the Contractor to proactively negotiate with households to rent construction sites. Currently, the Contractor has finished renting the sites of Binh Son I and Binh Son II bridges, the section from Km8+700 to Km9+300 has been counted and is preparing to pay to get the construction site. The Contractor has mobilized machinery and equipment to implement the above sections before March 5, 2016...
![]() |
The construction unit concentrates equipment and motorbikes to implement the project. |
After listening to the opinions of the investor and the departments, Vice Chairman of the Provincial People's Committee Huynh Thanh Dien emphasized that this is an important project, requiring fast construction progress. Therefore, in order to complete the project in 2016 in accordance with the direction of the Ministry of Transport, he requested the BOT side, the People's Committee of Quynh Luu district, and related departments to focus on clearing households according to plan; complete the plan to relocate power lines and water lines, prioritize undergrounding power lines across the 10KV line and the 0.4KV line at the intersection. At the same time, coordinate with the construction unit to promptly clear the sections where the ground is available.
The Vice Chairman of the Provincial People's Committee also requested the Compensation and Site Clearance Council of Quynh Luu district to notify the management unit of Viettel cable, Quynh Luu telecommunication cable, Cable TV... with underground and above-ground works within the construction area to have a plan to relocate and coordinate with the construction unit to relocate the sections that have been cleared. During the construction process, it is necessary to ensure traffic safety, technical safety and labor safety...
Thu Huyen