Resolving the issue of stalled projects in Nghe An province.
(Baonghean) - In recent times, Nghe An has attracted many investment projects, creating a breakthrough and bringing a new look to the province's socio-economic development. However, there are still projects that have been implemented but are behind schedule or not implemented at all, affecting the province's investment environment; violating regulations and commitments in investment, causing public dissatisfaction.
(Baonghean) - In recent times, Nghe An has attracted many investment projects, creating a breakthrough and bringing a new look to the province's socio-economic development. However, there are still projects that have been implemented but are behind schedule or not implemented at all, affecting the province's investment environment; violating regulations and commitments in investment, causing public dissatisfaction.
"Voters in Cua Lo town request the revocation of the stalled project."
Vinh City: Projects stalled on prime land
Projects that have been put on hold.
As the economic center of the province, Vinh City has attracted hundreds of investment projects in recent years. Many of these projects play a crucial role in the city's construction and development. However, Vinh City is currently facing many difficulties, as a significant number of projects remain stalled.
Hung Hoa commune (Vinh City) is one of the localities with many projects whose detailed planning has been approved for many years, but have yet to be implemented by investors. For example, the Commercial and Service Center Project in Hung Hoa commune, invested by Nam Binh Trading and Service Co., Ltd., has a land area of 41,960m2 and was expected to be implemented from 2012. However, after 4 years, the project is still "stuck" in place.
Similarly, the project of the Vietnam-Laos Economic Cooperation Corporation, launched in 2010 with the aim of building an urban area and social housing on an area of 200 hectares, has only completed the surrounding fence. The project of Ha Thanh Company (Thanh Hoa), with an area of 80 hectares, had its detailed plan approved in 2010 but has remained an empty plot of land. Notably, the investor has not paid compensation to the residents for the past six years. Or, the project of Vinaconex Company, whose detailed plan was approved 10 years ago, is also stalled after only completing the land leveling work.
Mr. Tran Cao Cuong, Vice Chairman of the People's Committee of Hung Hoa commune, said: "Many projects have had their detailed planning adjusted and certificates changed repeatedly over the past decades, but now they have become extremely wasteful livestock grazing areas. At every meeting with constituents, the people raise this issue, and the commune also expresses its concerns, but nothing changes..."
![]() |
| Lam Hong Company Limited in Hung Hoa commune (Vinh City) has become a cattle grazing area. |
This situation is also occurring in many central wards of Vinh City, with numerous projects in lucrative locations failing to meet deadlines, such as: the Commercial Center, Office Building, High-Rise Apartment and Townhouse Project in Hung Dung Ward; the Commercial House and Automobile Assembly Workshop Project in Ha Huy Tap Ward; the Automobile Service Center Project in Nghi Phu Commune by Nam Kinh Investment and Construction Joint Stock Company; the Central Region ENT Hospital Project (Le-nin Street)...
Similarly, Cua Lo town has over 10 projects for the construction of guesthouses, fishing ports, resorts, and real estate... covering hundreds of thousands of square meters, which are behind schedule or have not even started construction after many years since the investment certificates were issued.
Located in the heart of Cua Lo town, the BMC Cua Lo Plaza project received detailed planning approval from the Provincial People's Committee in 2008 with a total investment of 933 billion VND, but to date, no construction has been carried out. The 5,274 m2 of land along Nguyen Sinh Cung street (Nghi Huong ward, Cua Lo town) designated for the project's 21-story twin towers (supermarket and luxury hotel) remains an empty plot of land overgrown with weeds.
For example, the Song Hong Resort project in Nghi Hoa ward, with a land area of 9,890 m2, was approved in 2008 with the aim of building a hotel, restaurant, and villas, but to date, the investor has only completed the walls and left the site unfinished. Similarly, the Hanoi Tourism Joint Stock Company's hotel and resort project in Nghi Hoa ward, whose detailed planning was approved in 2006, has only completed the surrounding walls, main gate, planting trees, and installing a lighting system.
The port and fishing harbor project, invested by Ha Dung Co., Ltd. with a total capital of over 94 billion VND and a planned area of nearly 30,000 m2 across both locations, received an investment certificate from the Provincial People's Committee in 2009. To date, construction has not begun at location 1, and only a few minor items have been implemented at location 2…
![]() |
| The hotel and guesthouse project of Hanoi Tourism Joint Stock Company in Cua Lo is experiencing delays in implementation. |
In Cua Lo town, there are also investment projects by several defense and security agencies that were allocated land and granted land use rights certificates since 2007 but have not yet been implemented. This situation is also occurring in many central wards of Vinh City, with many projects in lucrative locations not progressing as planned, such as: the Commercial Center, Office for Rent, High-Rise Apartment Building and Townhouses project in Hung Dung ward; the Commercial House and Automobile Assembly Workshop project in Ha Huy Tap ward; the Automobile Service Center project in Nghi Phu commune by Nam Kinh Investment and Construction Joint Stock Company; the Central Region ENT Hospital project (Lenin Street)...
The reality of many projects being behind schedule, failing to fulfill tax obligations as required, and not adhering to extended deadlines is not only occurring in central areas such as Vinh City and Cua Lo Town, but also in many localities throughout the province. In 2016, the Provincial People's Committee directed the establishment of three inter-agency inspection teams to check the progress of investment projects in the province. Team No. 1, led by the Department of Planning and Investment, was assigned to inspect 20 projects of 20 organizations/enterprises in the province from April 10th to May 10th, 2016.
Following the inspection, the delegation recommended that the Provincial People's Committee issue a decision to cancel the planning of 3 projects; terminate operations and revoke the investment certificates of 3 projects (Duc Hong Minh General Hospital Project of Duc Hong Minh Co., Ltd.; Hieu Market Complex Project - Thai Hoa Town of Nghe An Petroleum Construction Corporation; Alloy Production Plant Project of Thai An Mineral Investment Joint Stock Company); and one project was recommended to be removed from the list of investment projects in the province: Golden Land Non-fired Brick Factory Project of Golden Land Construction Investment Consulting Joint Stock Company.
Subsequently, the inter-agency inspection team 2 (led by the Department of Construction) inspected the progress of 21 projects from May 16th to May 27th, 2016, and recommended that the Provincial People's Committee issue a document notifying the cancellation of the Decision approving the detailed construction plan and related legal documents for 6 projects.
The third inter-agency inspection team (led by the Department of Natural Resources and Environment) inspected 26 projects of 26 businesses/investors in the province from June 10 to July 10, 2016. As a result, they recommended the revocation of 7 projects, including the waste treatment plant for energy production in Thai Hoa town and surrounding areas (Costructa Srl Co., Ltd. was approved by the Provincial People's Committee for investment, but currently has no activities to continue the project, violating the Investment Law); and the Quy Hop market and commercial street project, invested by Thang Long Urban Infrastructure Investment Joint Stock Company (the Provincial People's Committee had granted an extension in Document No. 6804/UBND-ĐTXD dated September 27, 2013, which required the project to commence in the second quarter of 2014, but the investor did not continue implementation).
Waste of land resources
Project delays have negatively impacted the province's socio-economic development. Besides wasting land resources, increasing costs, reducing investment efficiency, and affecting the business performance of enterprises, they also negatively impact social development, people's livelihoods, and the environment.
It is noteworthy that most of these projects are located in prime locations. The land allocated to these projects has been left fallow for decades, while the people have no land for production. “As a purely agricultural locality with no government agencies or units located within its boundaries, both the government and the people are very excited when investment projects come in. However, many projects have remained ‘stalled’ for decades, existing only on paper, while the people have no land for production…”
![]() |
| The project for a Central Vietnam ENT hospital along Le Nin Boulevard has not yet been implemented. (Photo: CL) |
This situation has been raised by voters through numerous meetings with National Assembly and People's Council representatives at all levels. "Local officials and people want the projects to start operating; if the investors cannot implement them, the land should be reclaimed and returned to the people for production," reflected Mr. Tran Cao Cuong, Vice Chairman of the People's Committee of Hung Hoa commune.
Revoking projects, withdrawing investment licenses, and transferring projects to more capable investors are the demands of the majority when discussing unfeasible projects. Mr. Vo Van Hung, Vice Chairman of the People's Committee of Cua Lo town, suggested: "While the town no longer has land available for auction to attract capable investors, and lacks land to recoup investment for some projects already implemented in the area, we propose that the province issue a document requiring project owners to implement their projects. If the project owner fails to implement it within the specified timeframe, procedures should be initiated to revoke the project."
Discussing this issue, Comrade Vo Viet Thanh - Member of the Standing Committee of the Provincial Party Committee, Secretary of the Vinh City Party Committee, said: “The arrival of projects in the area is necessary to build the city to be worthy of a Class 1 urban area. However, the difficulty is that many projects involve businesses holding hundreds of hectares of land without compensating the people. In particular, there are projects that have been licensed for over a decade but have still not been implemented, causing a waste of land resources.”
Regarding Vinh City, initial checks have been conducted on 34 projects that are currently under consideration by the province. The city will continue its inspections to advise the province on appropriate action. For investors lacking capacity and goodwill, who are merely waiting to sell or transfer their projects, the province is requested to revoke their licenses to ensure efficient land use. For example, the area surrounding the regulating lake (in Hung Loc, Hung Dung, and Hung Hoa communes and wards) is one of the city's largest potential land areas, yet some investors have acquired hundreds of hectares of land almost entirely on paper without compensation or any concrete action. The province is requested to revoke these licenses, re-plan the area, and allocate this land to attract potential investors.”
Several local leaders in the province also stated that the situation of many "stalled" or delayed projects has created difficulties for local authorities in implementing new projects. For example, persuading people to hand over land is not simple in practice; in some projects, authorities have to resort to forced eviction, but after the land is handed over to the investor, it is left unused, while people lack land for production, causing resentment. In addition, there are unfinished land clearance projects where investors lack the financial capacity to compensate people as required, leading to complaints and accusations.
Many abandoned projects have become dumping grounds for scrap metal and waste, causing environmental pollution and drug dens… violating land use regulations, resulting in budget losses, and negatively impacting the investment environment of the province and localities.
(To be continued...)