Quarter I of 2017 must complete land acquisition and clearance for Vinh urban development project

January 19, 2017 20:33

(Baonghean.vn) - Afternoon of January 19,The World Bank, led by Ms. Phan Thi Phuong Huyen - Urban expert, head of the working group, had a working session with the Provincial People's Committee on the Vinh urban development project. The province hasComrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee, together with departments and branches: Finance, Construction, Natural Resources - Environment, Planning - Investment, Provincial People's Committee Office and local authorities: Vinh City, Hung Nguyen District.

Các thành viên dự buổi họp
Members attending the meeting. Photo: Xuan Hoang

The Vinh Urban Development Project, funded by the World Bank, includes four components: Improving services and upgrading basic infrastructure; improving environmental sanitation; building bridges and urban roads; and enhancing technical infrastructure capacity. The total investment of the project is 152.922 million USD, equivalent to 3,180 billion VND, of which the World Bank loan is 98 million USD, and Vietnam's counterpart fund is 54.922 million USD.

The project is expected to be completed on December 30, 2017. Up to now, the total capital disbursed from the World Bank loan is 47 million USD, reaching 55% of the total project capital; the project implementation time is 80%; the counterpart capital has been provided 970 billion VND.

Đồng chí Huỳnh Thành Điền - Phó Chủ tịch UBND tỉnh giao cho TP Vinh và huyện Hưng Nguyên hoàn thành GPMB cho dự án phát triển đô thị Vinh trong quý I năm 2017.
Comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee assigned Vinh City and Hung Nguyen District to complete site clearance for the Vinh urban development project in the first quarter of 2017. Photo: Xuan Hoang

Currently, the project has completed a number of packages such as: Improving school sanitation; Building resettlement areas in Hamlet 5, Nghi Phu Commune; Upgrading and renovating the North Canal, Phase 1 and 2; Upgrading and renovating canal No. 3; Upgrading the main wastewater pumping station, building a new wastewater pumping station and a self-flowing canal to the main pumping station and is implementing the construction of 11 construction packages. Of which, some packages are facing difficulties and obstacles in site clearance, so the construction progress is slower than the assigned plan.

Bà Phan Thị Phương Huyền phát biểu ý kiến
Ms. Phan Thi Phuong Huyen speaks. Photo: Xuan Hoang

World Bank representative, Ms. Phan Thi Phuong Huyen said that although the Vinh urban land acquisition project has made many steps forward, the progress is still slow. In particular, in Hung Nguyen district, there are still many areas that have not been cleared. In order for the Vinh urban development project to be completed in June 2018, the locality must completely complete the land acquisition work in the first quarter of 2017.

Thi công đường hào thành cổ Vinh
Construction of Vinh ancient citadel moat. Photo: Document

Discussing with the working group, Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee agreed with the opinions and recommendations of the expert group. At the same time, he committed to completing the site clearance work in the first quarter of 2017. After the Lunar New Year holiday, Vinh City and Hung Nguyen District immediately started the site clearance work. The biggest problem is on the 35m road section through Nghi Duc commune, the compensation area for site clearance has been measured.