Request Vinh City to continue to speed up the progress of Vinh - Cua Lo road
(Baonghean.vn) - That was the direction of Vice Chairman of the Provincial People's Committee Huynh Thanh Dien at the inspection to speed up the progress of the Vinh - Cua Lo road project on the morning of February 18. Attending the inspection were representatives of departments, branches, leaders of Vinh city, Cua Lo town, and Nghi Loc district.
![]() |
Vice Chairman of the Provincial People's Committee Huynh Thanh Dien inspected the field to remove difficulties and speed up the construction progress of the Vinh - Cua Lo route. Photo: Thu Huyen |
Slow progress compared to the requirements assigned by the Provincial People's Committee
Project overview and progress: Total length 10.83km; starting point Km0+00 intersects with Truong Van Linh Street, Nghi Phu Commune, Vinh City, ending point Km10+830 intersects with Binh Minh Street, Cua Lo Town. Total project investment is 1,411 billion VND, of which: Government bond source 1,100 billion VND and local budget 311 billion VND.
Up to now, the allocated capital is 981,564 billion VND, disbursed 981,564 billion VND. Currently, the Department of Transport is directing contractors to focus on implementing the construction of sections with available land (8.6 km), coordinating with localities to clear the remaining sections for early handover, ensuring the construction of layer 1 asphalt concrete as required.
The 9m strip has been cleared for 8.6 km, the remaining 2.2 km (0.7 km of agricultural land, 1.4 km of residential land, 0.1 km of cemetery land) is concentrated in Vinh city; Nghi Loc and Cua Lo have been handed over.
Construction progress is basically guaranteed according to the plan for the sections with handed over site, ensuring quality.
![]() |
Vinh city leaders report on the site clearance situation of the project section through Nghi Phu and Nghi Duc communes. Photo: Thu Huyen |
In the past time, the departments and branches have promptly advised the Provincial People's Committee to remove and so far have basically handled the problems. However, compared to Notice No. 12/TB-UBND dated January 7, 2019 of the Provincial People's Committee, the progress has not been ensured as required by the Provincial People's Committee, especially the section through Vinh city.
Reasons for delay: The slow review of households and resettlement lots affects the adjustment of subdivision planning, approval of land prices and allocation of resettlement land to households; Confirmation of land origin, area balance, population determination, and recovery rate by Nghi Phu Commune People's Committee is still slow.
Regarding the inventory of agricultural land through Nghi Phu commune, due to the lack of cooperation of the people, forced inventory had to be carried out, leading to a prolonged implementation time.
The progress of handling problems under the authority of Vinh City People's Committee is still slow (guiding people to divide inheritance, adjusting cadastral map excerpts, supplementing plots with missing land prices...). The construction of resettlement areas is still slow, not ensuring compliance with the set progress requirements, especially the resettlement areas of Xuan Trung and Xuan Dong hamlets - Nghi Duc commune.
![]() |
Construction unit of asphalt pavement section through Nghi Loc district. Photo: Thu Huyen |
Vinh City needs to take more drastic action.
Speaking at the scene, Vice Chairman of the Provincial People's Committee Huynh Thanh Dien acknowledged the efforts of departments, branches, local authorities and contractors. To speed up the progress of the project, ensure safety and aesthetics, he requested relevant units to complete the paving, plant trees and markers and hand them over to the Department of Transport for management. For the section through Nghi Phong commune, Nghi Loc district, it is necessary to drive stakes and plant trees to avoid re-encroachment.
The Vice Chairman of the Provincial People's Committee emphasized: In the past time, the Vinh City People's Committee has made efforts and made changes, however, there are still many difficulties ahead. Therefore, it is recommended that the Vinh City People's Committee resolutely direct departments, offices, People's Committees of communes and related individuals to seriously implement the plan on December 28, 2018 of the Chairman of the Vinh City People's Committee. Organize propaganda and mobilize households to receive compensation to hand over the site for the project. For households affected within a radius of 9m, it is recommended to apply the plan to support funding for building temporary houses to hand over the site as soon as Nghi Loc district has done.
Vinh City continues to direct the People's Committees of Nghi Phu and Nghi Duc communes to speed up the work of land use ownership, determine the recovery percentage, determine the population, etc. for agricultural land on the main route and resettlement areas No. 5 and No. 21. Propaganda and mobilization for people to receive money to hand over the land to clear the 9m line for Nghi Duc commune before April 30, 2019; Nghi Phu commune before June 30, 2019.