Dien Ngoc Housing and Commercial Service Area Project speeds up phase II progress
(Baonghean.vn) - The Dien Ngoc residential and commercial service project, located in Dien Ngoc commune, Dien Chau district, invested by Hai Van Company Limited, has completed phase I and is proving effective. Currently, the investor is actively speeding up the progress of phase II, striving to complete it by the end of 2020.
![]() |
Dien Ngoc Residential and Commercial Service Area Project (Dien Chau) is under construction in phase II. Photo: Hai An |
Currently, phase 1 of the project is in operation, initially creating a highlight for the coastal urban area of Dien Chau district. With a total area of 31 hectares, a scale of 800 households, the investor has implemented more than 15 hectares, investing over 200 billion VND in construction, including main traffic routes connecting from National Highway 1 along the Bung River to the project, side roads, along with a green tree system, underground lighting; planning of a people's market.
![]() |
Machinery and equipment are leveling the ground. Photo: Hai An |
Along with the residential area, the investor has built a 2-storey kindergarten worth 17 billion VND, a water park. During the project construction, Hai Van Company Limited has completed all procedures and tax obligations of the State according to regulations, paid land use fees, land rent, registration fees, land compensation fees, etc.
Mr. Nguyen Hai Van - Director of Hai Van Company Limited said: Since March 2020, Hai Van Company Limited has focused on implementing the construction of phase 2 of Dien Ngoc residential and commercial service area.
In this phase 2, the project will level nearly 7 hectares of land, investing in infrastructure worth hundreds of billions of VND.
![]() |
The project's entertainment area has been put into operation. Photo: Hai An |
Specifically, the construction of internal traffic routes of the project is nearly 8 km, the widest road is 24 m, the narrowest road is 15 m, all paved with asphalt. Construction of lighting items, drainage system, trees on both sides of the traffic roads. In particular, the land lots of phase II are designed diversely, the smallest is 150 - 250 m2 to build villas.
Dien Ngoc residential and commercial service project strives to ensure that customers enjoy the open space along the Bung River close to nature, while also benefiting from welfare facilities right at the project area.
Up to this point, the Dien Ngoc residential and commercial service project phase II has achieved over 60% progress and is expected to be completed and put into use by the end of 2020.
![]() |
The children's water park has a regulated depth. Photo: Hai An |
This project meets the entertainment needs of the project's residential area and the people of the coastal communes of Dien Chau. Currently, the project is strictly implementing the technical requirements.
Mr. Nguyen Hai Van - Director of Hai Van Company Limited shared: To ensure safety while playing in the water park during the hot season, the company has reminded parents to keep an eye on their children; Comply with the management board's regulations... In case children do not know how to swim, parents must supervise them when playing in the water park...
![]() |
Water park for adults. Photo: Hai An |

Vinh City will withdraw capital from 11 projects and enforce some urban projects.
(Baonghean.vn) - The information was stated at the opening session of the 6th meeting of the Vinh City People's Council, term XXI, 2016 - 2021, on the morning of July 9.

World Bank commits to continue supporting Vinh Urban Subproject
(Baonghean.vn) - As part of the visit and working program in Nghe An, on July 20, the World Bank delegation in Vietnam had a meeting with provincial leaders about a number of programs and projects funded by the WB that are being implemented in the area.