Thanh Chuong irrigation dam damaged after 10 years of construction and not yet handed over

Tien Dong DNUM_AIZABZCACC 06:50

(Baonghean.vn) - The project to repair and upgrade the Hong Vang reservoir in Thanh Khe commune (Thanh Chuong) began in 2011. Although it has not been handed over yet, the project has been damaged and seriously degraded...

The project to repair and upgrade the Hong Vang reservoir was approved by the Provincial People's Committee for its technical economic report under Decision No. 4126/QD.UBND-NN dated September 16, 2010. This is a level V project, assigned to the Thanh Chuong District People's Committee as the investor, and Duy Hung Construction and Supervision Consulting Joint Stock Company, located in Vinh City, to carry out the construction. In June 2011, this project began construction. Photo: Tien Dong
Initially, the total investment of this project was 6,954 billion VND, then on June 9, 2016, it was adjusted down to more than 6,440 billion VND, and at the same time, the normal water level was lowered from 27.10m to 24.30m. This project was implemented to ensure irrigation for about 50 hectares of agricultural land in Thanh Khe commune. Photo: Tien Dong
It has been 10 years since the construction of the repair and upgrade of the Hong Vang reservoir began, but the project has yet to be handed over. In particular, the project has seriously degraded, the dam body is leaking water but has not been completely repaired. Photo: Tien Dong
Thân đập đã bị rò rỉ nhiều điểm. Ảnh: Tiến Đông
The dam body has leaked in many places. When you get close to the dam body, you can clearly hear the sound of strong water flow and the alum marks are boldly imprinted on the dam roof. Photo: Tien Dong
Nước chảy ào ào ra từ thân đập. Ảnh: Tiến Đông
Mr. Tran Quoc Hung - Chairman of Thanh Khe Commune People's Committee said that this project is invested by the district, the commune is only the beneficiary. Up to now, it has not been handed over to the locality for management and operation. In the photo, water flows out of the dam body. Photo: Tien Dong
Theo lãnh đạo địa phương, việc rò rỉ nước đã xẩy ra từ lâu thế nhưng nhà thầu vẫn không lên khắc phục, sửa chữa. Ảnh: Tiến Đông
According to local leaders, the water leak has been happening for a long time and is larger than the allowable level. Photo: Tien Dong
Đoạn dưới cửa xả tràn của đập đã bị xói lở. Vào mùa mưa lũ năm 2020 và năm 2021 nước tràn từ thân đập đã làm xói lở đất đá xuống một diện tích ruộng phía dưới đập, buộc chính quyền địa phương phải tự khắc phục. Ảnh: Tiến Đông
The section below the spillway of the dam has been eroded. During the 2020 flood season, water overflowing from the dam body eroded rocks and soil into an area of ​​rice fields below the dam, forcing the local authorities to fix it themselves. According to the report of the Thanh Chuong District Construction Investment Project Management Board, up to now, the Hong Vang dam project has basically completed all items; has been granted more than 4.2 billion VND, of which the construction unit paid more than 3.9 billion VND and 370 million VND for other costs. However, because the leakage exceeded the allowable level, the project has not been accepted and handed over for use. Photo: Tien Dong
Ông Hùng cũng cho biết, hiện nay nhiều diện tích lúa phía dưới đập đã bị đất đá bồi lấp không còn sản xuất được. Ảnh: Tiến Đông
Currently, many rice fields below the dam have been filled with rocks and soil and are no longer productive. With the project not yet handed over but already damaged for a long time, the local authorities and people are concerned that in the long term, it will affect water storage, and even pose a risk of the dam breaking when the rainy season comes. Photo: Tien Dong

Tien Dong