Nghe An: Requires 4 chairmen of district and town People's Committees to hand over the site of the expressway project before March 25, 2022

PV DNUM_BEZADZCACC 09:26

(Baonghean.vn) - Four localities are slow to hand over the land for the North-South expressway project in the East phase 2017-2020, the section passing through Nghe An province including: Dien Chau, Yen Thanh, Hung Nguyen and Hoang Mai town.

Accordingly, in Document No. 1517/UBND-CN signed by the Standing Vice Chairman of Nghe An Provincial People's Committee Le Hong Vinh, it stated: "Recently, the Provincial People's Committee has directly directed the Departments, branches and localities where the route passes through to focus on resolving difficulties and obstacles, speeding up site clearance work to hand over according to the required schedule.

However, up to now, localities have not focused on solving difficulties and problems, have not made detailed plans as required, affecting the progress of the project, especially Dien Chau, Yen Thanh, Hung Nguyen districts and Hoang Mai town have not yet completed and are behind schedule for the North-South expressway project in the East phase 2017-2020, the section through Nghe An province.

Lãnh đạo tỉnh kiểm tra tiến độ thi công cao tốc Bắc Nam đoạn qua huyện Hưng Nguyên. Ảnh: Quang An
Provincial leaders inspect the construction progress of the North-South Expressway section through Hung Nguyen district. Photo: Quang An

Therefore, the Provincial People's Committee criticizedChairman of District People's CommitteeDien Chau, Yen Thanh, Hung Nguyen and Hoang Mai town have not strictly followed the direction of the Provincial People's Committee on site clearance for this project in the past, causing the progress to be slower than required.

The Provincial People's Committee requests the Chairmen of the People's Committees of districts and towns where the route passes through to urgently: Direct departments and offices to make detailed progress plans for the remaining volumes of each unfinished item. Complete the report to the Provincial People's Committee before 5:00 p.m. on March 11, 2022.

Directly direct to complete site clearance work, hand over the entire site to Project Management Board 6 - Ministry of Transport before March 25, 2022.

Nghe An Provincial People's Committee requests the Chairmen of the People's Committees of districts and towns where the route passes through to urgently: Direct departments and offices to make detailed progress plans for the remaining volumes of each unfinished item. Complete the report to the Provincial People's Committee before 5:00 p.m. on March 11, 2022. At the same time, resolutely direct to complete the site clearance work, hand over the entire site to Project Management Board 6 - Ministry of Transport before March 25, 2022.

After the above time, if any locality fails to complete, the Chairman of the People's Committee of the district and town shall take full responsibility before the Provincial People's Committee and the Chairman of the Provincial People's Committee, stated in Document No. 1517/UBND-CN.

Thi công cao tốc Bắc Nam trên địa bàn T.X Hoàng Mai. Ảnh: Tiến Đông
Construction of the North-South Expressway. Photo: Tien Dong

It is known that,North-South Expressway Construction Investment ProjectThe Eastern phase 2017 - 2020 passes through Nghe An province, nearly 90km long, belonging to 2 component projects: Nghi Son - Dien Chau section, 50km long, passes through Thanh Hoa and Nghe An provinces.

The project has a total investment of about 7,293 billion VND, using State budget capital, the project construction time is about 2 years; Dien Chau - Bai Vot: About 50km long, passing through the territory of 2 provinces Nghe An (44.4km) and Ha Tinh (4.9km). The project has a total investment of about 11,157 billion VND.