Nghe An proposes to recover public investment capital for 60 projects and works
(Baonghean.vn) - Based on legal regulations, the Provincial People's Committee is submitting to the Provincial People's Council a policy on handling the remaining undisbursed capital for 68 projects; of which 60 projects request capital recovery and 8 projects are allowed to extend the implementation period to 2022.
Disbursement rate reached 95.9%
According to the report of the Provincial People's Committee, the total public investment plan focusing on local budget sources in 2021 is more than 1,587 billion VND; of which the capital plan of previous years extended to 2021 is more than 106 billion VND; the capital plan in 2021 is more than 1,480 billion VND.
The disbursement result of the public investment plan focusing on local budget sources in 2021 is more than 1,522 billion VND, reaching 95.9%. Of which, the disbursement result of the investment capital plan in previous years extended to 2021 is more than 96.5 billion VND, reaching 90.63%; the disbursement result of the capital plan in 2021 is nearly 1,426 billion VND, reaching 96.28%.
![]() |
Disbursement rate in 2021 reached 95.9%. Illustration photo: Mai Hoa |
Proposal to recover capital from 60 projects
Pursuant to Clause 5, Article 101 of the 2019 Law on Public Investment, the 2020 public investment capital plan is allowed to be implemented and disbursed in accordance with the provisions of the Law.Invest2014 public investment plan in Clause 1, Article 76: The time for implementation and disbursement of capital for the medium-term public investment plan of the previous period is until December 31 of the first year of the medium-term investment plan of the next period; the time for disbursement of the annual public investment plan is extended to the following year. In special cases permitted by competent authorities, the disbursement time may be extended but not beyond the medium-term public investment plan.
Thus, the implementation time and disbursement of capital planpublic investment2020 must not be extended beyond December 31, 2021. Therefore, the Provincial People's Committee proposes that the Provincial People's Council approve the policy of recovering the remaining undisbursed capital for works and projects to allocate capital to projects that need to speed up progress.
Specifically, there are 19 projects in the 2020 plan that have extended the implementation and disbursement period to 2021, but have not fully disbursed the target, and it is proposed to recover the remaining undisbursed capital with a total capital of nearly 10 billion VND.
![]() |
An irrigation project under construction. Illustration photo: Mai Hoa |
Regarding the 2021 public investment plan, Clause 2, Article 68 of the 2019 Law on Public Investment stipulates: The implementation and disbursement period for the annual public investment plan is until January 31 of the following year. In case of force majeure, the Prime Minister decides on the central budget capital, and the Provincial People's Council decides on the local budget capital to allow an extension of the implementation period, but not beyond December 31 of the following year.
The scope of projects allowed to be extended are important national projects; compensation, resettlement support, and site clearance projects; projects with capital plans arranged to be completed and put into use in the planning year but with capital planned for the following year; projects with investment plans supplemented from sources of increased revenue, expenditure savings, state budget surplus, and annual state budget reserves but not yet permitted by competent authorities to disburse in the following year; projects whose progress is affected by natural disasters, catastrophes, epidemics, or objective causes that cannot be foreseen and cannot be overcome despite the application of all necessary and permissible measures; projects of representative agencies and other agencies of Vietnam abroad; Ministries, central and local agencies that have only one project in the planning year or do not make plan adjustments.
![]() |
Thi công dự án hạ tầng giao thông. Ảnh minh họa: Mai Hoa |
Trên cơ sở quy định các dự án được cho phép kéo dài nêu trên, UBND tỉnh đề xuất HĐND tỉnh cho phép kéo dài thời gian thực hiện và giải ngân sang năm 2022 đối với 8 dự án với số vốn còn lại hơn 55 tỷ đồng.
Có 2 dự án với số vốn còn lại chưa giải ngân hơn 8,1 tỷ đồng, trong đó đề xuất cho phép kéo dài số vốn gần 2,3 tỷ đồng và số còn lại đề nghị thu hồi.
Có 39 dự án với số vốn gần 34 tỷ đồng không thuộc các trường hợp cho phép kéo dài bị đề nghị thu hồi số vốn chưa được giải ngân còn lại.
Như vậy, đối với kế hoạch đầu tư công năm 2021, có tổng 49 dự án chưa giải ngân hết chỉ tiêu với số vốn còn lại chưa giải ngân là hơn 55 tỷ đồng; trong đó được đề xuất kéo dài hơn 15,3 tỷ đồng và thu hồi hơn 39,7 tỷ đồng.
Tính chung kế hoạch đầu tư năm 2020 kéo dài sang 2021 và kế hoạch đầu tư công năm 2021 có tổng 68 dự án; trong đó có 8 dự án cho phép kéo dài thời gian thực hiện và 60 dự án đề nghị thu hồi số vốn còn lại là gần 50 tỷ đồng. Từ nguồn vốn thu hồi, UBND tỉnh đề xuất phương án bố trí vốn đầu tư cho 7 công trình, dự án.
![]() |
Ban Kinh tế - Ngân sách HĐND tỉnh iến hành thẩm tra dự thảo nghị quyết về việc xử lý số vốn còn lại chưa giải ngân thuộc kế hoạch đầu tư công nguồn ngân sách địa phương năm 2021 và năm 2020 kéo dài sang năm 2022 vào chiều ngày 18/3/2022. Ảnh: Mai Hoa |
Đề xuất phương án xử lý số vốn còn lại chưa giải ngân đối với 68 công trình, dự án nêu trên đã được UBND tỉnh xây dựng dự thảo nghị quyết về việc xử lý số vốn còn lại chưa giải ngân thuộc kế hoạch đầu tư công nguồn ngân sách địa phương năm 2021 và năm 2020 kéo dài sang năm 2022 để trình HĐND tỉnh xem xét, quyết định.
Trên cơ sở các nội dung trình của UBND tỉnh, Ban Kinh tế - Ngân sách HĐND tỉnh đã tiến hành thẩm tra dự thảo nghị quyết với sự thống nhất cao để báo cáo với Thường trực HĐND tỉnh đưa vào chương trình nghị sự kỳ họp thứ 5, HĐND tỉnh khóa XVIII, nhiệm kỳ 2021 - 2026 dự kiến tổ chức vào ngày 25/3/2022./.