The Vinh - Cua Lo road project, phase 2, has a total length of 10.8km. The project plays an important role in creating momentum for economic development, connecting the administrative center of Vinh City and the Cua Lo coastal tourist town. After completing phase 1, the project will start construction of phase 2 from July 2022. In 2022, the project will be allocated 490 billion VND, in 2023, 253 billion VND. Photo: Tran Chau |
 |
Although the capital for 2023 is allocated 253 billion VND, only 50 billion VND has been decided to be allocated. Overcoming difficulties, in the first days of the year, the consortium of 3 contractors, Hoa Hiep Company Limited, Tan Hung Company Limited, Tan Nam Construction Joint Stock Company, mobilized human resources and machinery to carry out construction. Photo: QA |
 |
The construction area in the middle of the road in phase 2 has been covered by construction units, separated from the 2 lanes on both sides to ensure the safety of continuous traffic participants. Photo: QA |
 |
Checking the construction of bridge components on the route. Photo: Tran Chau |
 |
"Despite facing many difficulties due to continuous rain, fog, and lack of workers, thanks to the close direction of the Department of Transport and the sense of responsibility of the contractors, since after Tet until now, the contractors have arranged one team to install centrifugal culverts, one team to construct the roadbed, one team to complete the top of the roadbed, and another team to construct the roadbed. The units are mobilizing one tire excavator, one crawler excavator, 11 rollers, one self-propelled crane, and tank trucks," said Mr. Pham Dinh Hanh - Director of Hoa Hiep Company Limited. Photo: Quang An |
 |
At the beginning of the year, due to focusing on different projects, there were times when some construction sites were quite empty. Photo: QA |
 |
Since the completion of Vinh - Cua Lo Boulevard Phase 1, traffic density on both sides of the road has been very crowded and bustling. Photo: QA |
 |
Chief Engineer Bui Ha Thanh - Hoa Hiep Company Limited said: The company is currently mobilizing 30 motorbikes to carry out the unit's work. Photo: Tran Chau |
The Vinh - Cua Lo traffic route project, phase 2, was approved by the People's Committee of Nghe An province in Decision No. 4686/QD-UBND dated December 2, 2021, with a total investment of VND 1,415 billion. The project is invested by the Nghe An Department of Transport, with a length of 10.8km passing through 3 localities, including Vinh city, Nghi Loc district and Cua Lo town; constructed by 3 contractors: Hoa Hiep Company Limited, Tan Hung Company Limited, Tan Nam Construction Joint Stock Company and started construction at the end of July 2022. This is the main artery of Nghe An connecting Vinh city with Cua Lo, currently the largest road in Nghe An. Currently, the Traffic Project Management Board of the Department of Transport requires the supervision consultants of contractors to regularly be present at the site to coordinate with the Board to grasp the techniques, promptly detect and handle errors, and strengthen the management of construction quality because this is a key project.