Hung Nguyen: Relocating high voltage power poles to construct the North-South expressway
(Baonghean.vn) - After Nghe An Newspaper published an article "Hung Nguyen has many problems in clearing the land for the North-South Expressway", Hung Nguyen district and the electricity industry relocated high-voltage power poles to hand over the land to investors.
On April 6, 2023, Nghe An Newspaper published an article "Hung Nguyen has many problems in site clearance for the North-South Expressway" in which it stated the current situation that some electric poles in Hung Tay commune have not been relocated.
![]() |
A high-voltage power pole in Hung Tay commune has been dismantled by the electricity industry. Photo: PV |
On April 6, 2023, Hung Nguyen district sent a document to Project Management Board 6 and the construction enterprises of the North-South Expressway section through Hung Nguyen: To complete the project of relocating the 220kV line and dismantling column 117 of the 220kV Ban La - Vinh line under the project of relocating the 110kV and 220kV lines to serve the site clearance of the North-South Expressway project in the East, handing over the site to the construction unit, Hung Nguyen district coordinated with the Northern Dispatch Center, Power Transmission 1 to approve the power outage schedule from 5:00 a.m. on April 8, 2023 to 5:00 p.m. on April 11, 2023 (on lines 271, 272 T220 Do Luong-272-273T220 Hung Dong). After the power outage, power construction units proceeded to erect poles from April 9 to April 11 to deploy laying and pulling wires.
Hung Nguyen District requests contractors to direct construction teams not to circulate through the service road section intersecting with the 220kV power line at Km460+060 (highway route) from April 9, 2023 to 5:00 p.m. on April 11, 2023 so that the power line construction units can complete their tasks.
![]() |
Two high voltage power poles have been moved to a new location. Photo: PV |
Currently at the scene, one electric pole (No. 117) of the 220kV Ban La - Vinh line has been dismantled, two 220kV electric poles have been relocated to a new location.