Finalize the plan for compulsory land acquisition to implement the VSIP industrial park project

Tien Dong DNUM_AEZAIZCACD 12:18

(Baonghean.vn) - The People's Committee of Hung Nguyen district has just issued a Plan to organize the enforcement of the Decision on land recovery to implement the Project of construction and business of infrastructure of VSIP Nghe An industrial, urban and service park in Phuc Long hamlet, Hung Tay commune.

Before that, doProject of Construction and Business of Infrastructure of VSIP Nghe An Industrial, Urban and Service Park(Industrial Park, Phase 1B), in Hung Tay Commune, Hung Nguyen District People's Committee has assigned the VSIP Project Compensation and Site Clearance Council to measure, count, develop a compensation plan, and support site clearance for affected households.

Based on the approval decisions of the People's Committee of Hung Nguyen district, the Compensation and Site Clearance Council of VSIP project has made payments to households and individuals in accordance with regulations. Basically, all households have received compensation and support funds and handed over the site to the investor. Of which, 73/90 households have received money, only 17 households and individuals in Phuc Long hamlet, Hung Tay commune, have not yet received compensation funds and handed over the site to the investor.

BNA_khu vực dự kiến sẽ thực hiện cưỡng chế.jpg
The land is expected to be subject to forced eviction. Photo: Tien Dong

Despite the fact that the People's Committee of Hung Nguyen district as well as relevant agencies, departments and branches have repeatedly communicated, mobilized, dialogued and explained, 17 households and individuals still do not comply with the Land Reclamation Decision, and at the same time make unfounded requests. Specifically, the request to increase the compensation price for agricultural land and support for career conversion 5 times. This is extremely unreasonable, affecting the progress of site handover, affecting the investment environment and the strictness of the law.

Therefore, on April 6, 2023, the People's Committee of Hung Nguyen district issued a Decision to establish a Board to enforce land recovery for households and individuals in Phuc Long hamlet, Hung Tay commune. On July 31, 2023, the People's Committee of Hung Nguyen district officially issued Plan No. 37/KH-UBND to organize the enforcement of the land recovery decision.

According to this plan, the area of ​​enforcement organization is 21,105.2m2.2is agricultural land within the clearance area. The enforcement is expected to be held on August 8, 2023.

BNA_khu đất thực hiện cưỡng chế.jpg
This land has an area of ​​21,105.2 square meters, is agricultural land under the use of households and individuals within the clearance area. Photo: Tien Dong

The land acquisition and site clearance to hand over to the investor to implement the VSIP Nghe An Industrial, Urban and Service Park Infrastructure Construction and Business Project in Hung Tay Commune, Hung Nguyen District is a correct policy, consistent with the development of the province. In addition to properly implementing the province's investment attraction policy, it also creates conditions for enterprises to soon deploy factory construction and start production and business according to the set plan.

If the handover of the site is delayed, it will lead to missed opportunities to attract investment resources, which will greatly affect the investment environment that the province has worked so hard to build for so long.