Vinh City determined to open phase 2 of Ly Thuong Kiet street in September
Nguyen Hai•DNUM_CHZAIZCACD 09:04
(Baonghean.vn) - According to information from Vinh City People's Committee, the city is currently concentrating resources and efforts to open phase 2 of Ly Thuong Kiet Street, starting from the intersection with Le Loi Street to Nguyen Van Cu Street in September.
Phase 2 projectLy Thuong Kiet Street1.06 km long, 24 m wide, located in Hung Binh ward (Vinh city), starting from Ly Thuong Kiet street currently intersecting with Le Loi street (National Highway 1A) running on the east side of Trung Duc building, crossing Ngo Tuan street and Nguyen Duc Canh street to Nguyen Van Cu street. Although the length is not much, due to land issues, the planning has to "wait" for nearly 30 years before construction can begin. From 2021, to celebrate the 60th anniversary of Vinh city andurban beautification, traffic congestion reduction,Vinh City People's Committee has just focused resources and resolutely implemented this project.
Below are some images that Nghe An Newspaper reporters recorded at the scene:
The end point of phase 2, Ly Thuong Kiet Street, which has many houses, has been a bottleneck that has been difficult to clear for many years, and is now about to open to Nguyen Van Cu Street. In the photo: Immediately after the residents agreed to hand over the site, the construction unit used machinery to dismantle and clear the road to prepare for the construction of the route. Photo: Nguyen HaiThe intersection of Nguyen Van Cu Street and Ly Thuong Kiet Street seen from Thanh Thai Street (Hung Phuc Ward), if opened, will help reduce traffic congestion on Doc Thiet Street and Nguyen Thi Minh Khai and Kim Dong Streets. Photo: Nguyen HaiA 300m section of Ly Thuong Kiet Street through Military Unit 682 in Yen Phuc block has been completed due to early site handover, waiting for carpeting and sidewalk paving. Photo: Nguyen Hai The construction unit is taking advantage of the opportunity to level the ground to clear the route from the intersection with Nguyen Duc Canh Street through the intersection with Ngo Tuan Street to the west of Ly Thuong Kiet Street, near Trung Duc Company Building. Photo: Nguyen HaiDue to the progress being much slower than planned, when the site was available, the contractors quickly started construction to make up for the delay. In the photo: The construction unit is maintaining the manhole to collect water to the drainage ditch on Ly Thuong Kiet Street at the intersection with Nguyen Duc Canh Street, Hung Binh Ward. Photo: Nguyen HaiMr. Nguyen Ngoc Phong - Director of Vinh City Investment Project Management Board said: According to the original design, Ly Thuong Kiet Street has a total length of about 3 km, width of 24 m; phase 1 from Truong Chinh Street to Le Loi Street and phase 2, from Le Loi Street (Hung Binh) to the intersection of Hermann Gmeiner Street (Hung Phuc) including the current Thanh Thai Street. In the photo: Contractors leveling, clearing and weathering, constructing ditches and culverts running through Hung Binh Ward Primary School. Photo: Nguyen HaiLy Thuong Kiet Street, phase 1, was expanded in 1995, intersecting with Le Loi Street (National Highway 1A). Now, phase 2 investment will help reduce traffic congestion and limit flooding on this road. Photo: Nguyen HaiMr. Nguyen Sy Dieu - Vice Chairman of Vinh City People's Committee said: The City People's Committee has considered and applied to ensure the rights of households, agencies and units affected by the Ly Thuong Kiet Road Project Phase 2. The city is renovating Nguyen Van Cu Street, so if the route is opened at this time, it will be very good and convenient. The city will also develop a plan to enforce and protect the construction, striving to connect Ly Thuong Kiet Street to Nguyen Van Cu Street. In the photo: At the intersection of Nguyen Xuan On Street and Ly Thuong Kiet Street, households agreed to receive compensation and hand over the site to the construction unit. Photo: Nguyen HaiOf the 1.06 km length of the second phase of Ly Thuong Kiet Street, there are only 2 remaining locations, of which, location 1, about 100m from Ngo Tuan Street to the West, connecting to the first phase of Ly Thuong Kiet Street, currently has a few temporary houses, people who have received compensation are stuck with houses and architectural structures that have not been cleared and the route has not been opened, of which, 80m and about 20m of Mr. Pham Van Ky's household adjacent to Nguyen Van Cu Street have not agreed to hand over. In the photo: Another construction site after the households handed over the site, has been leveling from the West of Ly Thuong Kiet Street (from Trung Duc building) back. Photo: Nguyen HaiMr. Phan Thanh Son - Chairman of Hung Binh Ward People's Committee said: To implement the Ly Thuong Kiet Street Project Phase 2, the city had to adjust the budget many times and this time with an amount of nearly 360 billion VND, of which, the majority is for site clearance. Currently, basically households, agencies and units have agreed to hand over the site, only 1 household is stuck, after the City People's Committee has a decision to resolve the complaint, the forced construction will be organized. In the photo: The land plot next to Mr. Pham Van Ky's land, the construction unit has stripped the weathering and is waiting for the site to connect to Nguyen Van Cu Street. Photo: Nguyen HaiLy Thuong Kiet Street Phase 2 has been constructed to the second lane, right after Nguyen Van Cu Street, but had to stop to wait for a household because the land had not been handed over. To ensure traffic safety, the construction unit had to barricade the road. Photo: Nguyen HaiMr. Nguyen Viet Duc - Head of the Urban Management Department of Vinh City People's Committee said: The completed Ly Thuong Kiet Street Phase 2 project (red connecting line) will connect the current Ly Thuong Kiet Street, from the intersection with Vinh Central Bus Station (old) to Nguyen Van Cu Street to Thanh Thai Street and Duy Tan Street, connecting the city's traffic in the West - East direction and vice versa. If operated well, it will contribute to reducing congestion on Doc Thiet Street and Nguyen Thi Minh Khai Street during rush hour. Photo: Diagram of Phase 2 of Ly Thuong Kiet Street. Photo: NH
Centerwas hired by Vinh City People's Committee to advise on compensation and site clearance for the project. Although the number of households and organizations affected is large, with the determined participation of the center and functional departments of Vinh City, up to this point, almost all of the site has been handed over, only 1 household has not agreed and complained, so the City People's Committee is considering and resolving it. However, basically, the rights have been guaranteed and if this household agrees to hand over the site, the clearance construction will be smooth and in September, Ly Thuong Kiet Street can be connected to the intersection with Nguyen Van Cu Street to go to Thanh Thai Street.
Mr. Cao Quang Trung - Director of Provincial Land Fund Development Center