(Baonghean.vn) - On May 21, Ban Ve Hydropower Company organized a disaster prevention and control drill and a dam protection drill at Ban Ve Hydropower Plant in 2024.

bna_9. ảnh pv.jpg
Ban Ve Hydropower Plant. Photo: Nguyen Dao

After 1 day of practicing scenarios such as: Operation of flood discharge spillway; Ensuring safety when people and vehicles temporarily pass through the dam and the factory operation road; Heavy rain causes landslides on the upstream traffic road; The flood discharge valve is stuck during flood discharge operation; When the flood discharge operation is in progress, the entire factory loses power due to a grid collapse; Situation of losing communication; When Ban Ve reservoir is releasing flood, a group of people obstruct the operation of the flood discharge spillway; Violations of the dam safety protection corridor; Dam sabotage; Subjects carrying weapons and dangerous materials mixed with visitors entering the construction site and factory.

bna_1. ảnh pv.jpg
One of the drill plans at Ban Ve Hydropower Plant. Photo: Nguyen Dao

With a high sense of responsibility and smooth coordination between departments, the members have excellently performed their tasks according to the proposed plan. The disaster prevention and control drill and dam protection drill at Ban Ve Hydropower Plant are annual activities of the company before the rainy and stormy season, aiming to raise awareness and sense of responsibility, enhance proactiveness in disaster prevention and search and rescue work, and minimize damage caused by rain and floods.

bna_09. ảnh pv.jpg
With smooth coordination between departments, members have excellently performed their tasks according to the proposed plan. Photo: Nguyen Dao

The drill also aims to improve the command and management capacity of the Steering Committee for Natural Disaster Prevention and Search and Rescue; improve response skills, promptly resolve emergency situations, ensure the safety of lakes and dams, and at the same time, follow the "4 on-site" motto: On-site command, on-site human resources, on-site materials and equipment, and on-site logistics when rain and floods occur to ensure safe and continuous power generation.

bna_0. ảnh pv.jpg
Meeting to evaluate and learn from the drill. Photo: Nguyen Dao

At the end of the drill, the company's leaders and related departments and workshops met with the company's Disaster Prevention and Search and Rescue Command to evaluate and comment on the issues that were successful and not successful, thereby drawing experience to be proactive in work to carry out assigned tasks.