Vinh - Cua Lo Avenue Phase 2 will open to traffic before August 15

Quang An - Xuan Hoang DNUM_AGZAIZCACE 12:31

According to Nghe An Department of Transport, by early August 2024, the construction output of Vinh - Cua Lo Boulevard phase 2 reached over 90% and is expected to open to traffic before August 15.

cao 6
Vinh - Cua Lo Boulevard Phase 2 was approved by the Provincial People's Committee in Decision No. 4686/QD-UBND dated December 2, 2021. With a total length of 10.8km passing through 3 localities including Vinh City (3.4km), Nghi Loc District (4.8km) and Cua Lo Town (2.6km), this is the main artery of Nghe An connecting Vinh City with Cua Lo Town, and is also the largest road in Nghe An today. Photo: Xuan Hoang
cao 1
The starting point of the project is at Km0 intersection with Truong Van Linh Street - Vinh city and the ending point is at Km10+800 intersection with Binh Minh Street, Cua Lo town. The total investment of the project is 1,415 billion VND. In the photo: The section Km9+680 - Km10+832 has a main road 16m wide on each side, including 4 lanes; The median strip is 22m wide; The sidewalk on each side is 9m wide. Photo: Xuan Hoang
cao 5
The end point of the project intersects with Binh Minh Street, Cua Lo Town, facing the sea, and is now basically completed. Photo: Xuan Hoang
máy móc
In early August, the joint venture of contractors mobilized all human resources and machinery to carry out construction to meet the schedule. According to the Nghe An Department of Transport, by early August 2024, the construction output of this project reached over 90%. Photo: Quang An
công nhân 3
Currently, the contractor is focusing on completing the asphalt concrete pavement, finishing the sidewalk, paving stones, planting trees... Photo: Quang An
đèn điện
In addition, the lighting system and traffic safety items on the route are also in the final stages of construction. Photo: Quang An
công nhân
Despite the extremely hot weather in recent days, workers have overcome difficulties and stayed at the construction site to complete the project on schedule. Photo: Quang An
đèn giao thông
The traffic light system at the starting point of the project, the intersection with Truong Van Linh Street, has been installed. Photo: Quang An
bna_1.jpg
After Vinh - Cua Lo Boulevard Phase 1 is completed, people will travel from Vinh City to Cua Lo on the two-way access road, each side is 9 meters wide, with 2 lanes. According to the Department of Transport, Vinh - Cua Lo Boulevard Phase 2 is expected to be opened to traffic before August 15 with the main road on each side being 16 meters wide, with 4 lanes, minimizing traffic congestion as well as creating a highlight for the future face of Vinh city. Photo: Quang An

Quang An - Xuan Hoang