Nghe An Provincial People's Council surveys a number of key public investment projects and works

Plum Blossom DNUM_AJZBAZCACE 12:10

On the morning of October 9, the Provincial People's Council's monitoring delegation surveyed a number of key public investment projects and works for the 2021-2025 period in the province.

Comrade Nguyen Nam Dinh - Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Council led the survey team. Also participating in the survey were leaders of the Provincial People's Council Committees; Office of the National Assembly Delegation and the Provincial People's Council, together with representatives of the Department of Agriculture and Rural Development, the Department of Transport and the Southeast Economic Zone Management Board.

 Ven biển
Coastal route survey team. Photo: Mai Hoa

The monitoring delegation of the Provincial People's Council directly surveyed the construction progress of the Anti-erosion Embankment Project to protect the Lam River embankment, Yen Xuan area, Hung Nguyen district, invested by the Department of Agriculture and Rural Development.

The embankment is over 1.7 km long (including 16 residential steps and 8 drainage culverts on the route), with a total investment of 200 billion VND. Currently, this project has been completed and disbursed 98%, and is being submitted to the construction authority for approval of the acceptance results.

 Kè
The Provincial People's Council's monitoring delegation surveyed the construction progress of the Anti-erosion Embankment Project to protect the Lam left dyke, Yen Xuan area, Hung Nguyen district. Photo: Mai Hoa

The project has been completed and put into use, and has had a positive effect, overcoming the situation of riverbank erosion, protecting the downstream area of ​​the Ca River, with a total protected area of ​​about 90.4 thousand hectares and about 780,000 people in Nam Dan, Hung Nguyen, Nghi Loc districts and Vinh city, along with a number of important projects, such as the North-South railway, National Highway 1A... Currently, this project has been completed and disbursed 98%, and is being submitted to the specialized construction agency for approval of the acceptance results.

 Dự án Kè
The project of Anti-erosion Embankment to protect the Lam left dike, Yen Xuan area, Hung Nguyen district has been completed and put into use, overcoming the situation of riverbank erosion. Photo: Mai Hoa

The monitoring delegation also surveyed a number of projects in the Southeast Economic Zone; including the N2 level crossing project and the railway overpass on the N2-Southeast Economic Zone route.

The N2 level crossing project has a total length of over 6.9 km and a total investment of over 405 billion VND. The project has been completed and put into use; currently the project settlement documents are being prepared.

For the railway overpass project at N2 road, the total investment is 150 billion VND; the accumulated capital allocated is 137 billion VND and the accumulated capital disbursed is more than 135.5 billion VND; the remaining capital requirement is 2 billion VND. Currently, the project has been basically completed and is carrying out procedures for handover and putting into use.

 3, Đoàn giám sát HĐND tỉnh khảo sát dự án tuyến đường N2 và cầu vượt trên tuyến N2. Ảnh Mai Hoa
The Provincial People's Council's supervision delegation surveyed the N2 route project and the overpass on N2 route. Photo: Mai Hoa

However, to effectively promote the capital invested in 2 projects, the N2 crossroad project and the railway overpass at N2 road; to ensure the interconnection and synchronization of the functional subdivisions in the North of the economic zone with the North-South expressway, National Highway 1A, the coastal road to Cua Lo port area..., through N2 road; the investor is the Management Board of the Southeast Economic Zone, proposing that the Provincial People's Council and the Provincial People's Committee prioritize the allocation of capital sources to invest in the intersection between N2 road and the North-South expressway and the railway overpass at N2 road (phase 2).

 Đoàn N2
N2 route and bridge project on N2 route. Photo: Mai Hoa

Survey of the coastal road project from Nghi Son (Thanh Hoa) to Cua Lo (Nghe An) with a total length of more than 64 km; the starting point is in Quynh Loc commune, Hoang Mai town, connecting with National Highway 48D and the ending point is in Khanh Hop commune, Nghi Loc district, intersecting with National Highway 46. The total investment of the project is 4,651 billion VND; the capital structure includes the central budget and local budget.

 Dự án đường ven biển, đoạn qua huyện Diễn Châu. Ảnh Mai Hoa
Coastal road project, section through Dien Chau district. Photo: Mai Hoa

The project has been under construction since February 2022, with the construction and installation value so far reaching 85% of the contract. The total capital allocated to date is more than VND 3,625 billion; of which, in 2024, the medium-term public investment capital is VND 682 billion. The cumulative disbursement to date is more than VND 3,232 billion, reaching 89.18%; of which, the disbursement of medium-term public investment capital in 2024 is more than VND 382 billion, reaching 56.1%.

Currently, the project is stuck in site clearance at some local points in Nghi Loc, Dien Chau, Quynh Luu districts and Hoang Mai town. The investor is coordinating with localities to propagate and mobilize people to support the project, in order to soon complete and put the entire route into use.

Plum Blossom