Law

Openly set up a truck staging area under the 500kV power line

Tien Dong November 19, 2024 19:30

Although the land is located under the 500kV power grid corridor, a family in Nghia Trung commune (Nghia Dan) still brazenly built a truck parking lot.

Operation of the truck yard right under the 500kV power line. Video: Tien Dong

Nghe An Newspaper reporters received information from local residents that in Trung Thanh hamlet, Nghia Trung commune, Nghia Dan district, there is a plot of land located under the 500kV power line corridor. Although it is under the management of the commune People's Committee, it has been built into a truck staging area. This plot of land is located near National Highway 36, passing through Nghia Trung commune.

bna_1.jpg
The land is located under the 500kV power line. Photo: Tien Dong

Present in this area, we noticed that under the 500kV power grid corridor, there is a large land area surrounded by a solid fence. This area is often visited by many trucks, especially heavy trucks such as container trucks and tractors.

bna_xe.jpg
A tractor trailer leaves the staging area. Photo: Tien Dong

According to local residents, a makeshift oil pumping station was even built to pump oil for trucks when they gathered here. Every day, a large number of trucks came in and out, especially at night, causing damage to the concrete road in the hamlet.

xe dầu
Tanker trucks supply fuel to the gas station, "field" fuel in this yard. Photo: Tien Dong

According to our research, this land was previously residential land and garden land of some households (all brothers in the same family). After the 500kV line 1 was built in 1992, because it was located under the line, this land was reclaimed, cleared and handed over to the locality for management.

Looking up the land plot diagram shows that this land plot has an area of ​​5,996.4m2.2, currently agricultural land, mostly other perennial crop land and some freshwater aquaculture land.

sơ đổ
The plot diagram shows agricultural land, including perennial crop land and freshwater aquaculture land. Photo: Tien Dong

Answering our question about the appearance of this truck yard under the 500kV power line, Mr. Nguyen Long An - Chairman of the People's Committee of Nghia Trung commune said: In the locality, after the construction of the 500kV line circuit 1 in 1992, some households moved to other places after the land was cleared, some households asked to stay but built houses to avoid the power line. The households moved but still cultivated on the old land.

bơm dầu
A tanker truck is delivering oil. Photo cut from video.

Mr. An also informed that the above land is currently being used by Mr. Nguyen Huu Thang (a relative of the former landowner). "The commune also received information that Mr. Thang had let another unit build a truck storage area, even though he had previously applied for a chicken and pig farm. We will conduct a specific inspection," said Mr. An.

Clause 3, Article 51 of the 2024 Electricity Law, regulating the safety protection of overhead power lines, clearly states: It is not allowed to exist houses and buildings where people regularly live and work in the safety protection corridor of overhead power lines with voltage of 500kV or higher, except for specialized buildings serving the operation of that power grid.

It can be seen that setting up a truck staging area under the 500kV power line not only seriously violates legal regulations, specifically violating Decree 14/2014/ND-CP, dated February 26, 2014, detailing the implementation of the Electricity Law, and affecting the country's electricity transmission activities andpotentially threatening electrical safety and people's lives.

Tien Dong