Many localities of Nghe An propose solutions to speed up disbursement of capital for national target programs.

Hoai Thu DNUM_ABZBCZCACE 11:14

Identifying the causes leading to difficulties and obstacles in the implementation of the medium-term public investment plan for the period 2021 - 2025, many localities have made specific recommendations and proposals to increase the disbursement rate, especially sources of national target programs.

The medium-term public investment plan for the 2021-2025 period is implemented on the basis of inheriting the achieved results and learning from the shortcomings and limitations of the previous period. Sectors and levels have high consensus and unity on the guiding ideology of concentrated public investment with focus and key points, overcoming the situation of dispersion.

However, the implementation of the Medium-Term Public Investment Plan for the 2021-2025 period still faces many difficulties and challenges, such as: the Covid-19 pandemic has had a severe impact; the world situation has many rapid, complex and unpredictable changes. Domestically, inflationary pressure is high, prices of gasoline, oil, raw materials and input materials fluctuate strongly. Natural disasters and floods with complicated developments have greatly affected public investment activities, including national target programs.

Mô hình trồng khôi nhung tía dưới tán rừng ở bản Coọc, xã Yên Hòa (Tương Dương) từ nguồn vốn Chương trình Mục tiêu quốc gia. Ảnh: Hoài Thu
People in Cooc village, Yen Hoa commune (Tuong Duong) grow medicinal herbs under the forest canopy using funds from the national target program. Photo: Hoai Thu

In order to speed up the progress and disbursement rate of public investment in national target programs, localities in Nghe An have made recommendations and proposals to higher-level departments and branches to remove difficulties and obstacles encountered in the process of disbursement and implementation of projects. Mr. Lo Thanh Nhat - Vice Chairman of Tuong Duong District People's Committee said that the implementation of the medium-term public investment plan for the period 2021-2025 in Tuong Duong district ensures progress, disbursement by December 31, 2023 reaches 100% of the capital plan.

However, there are still problems and difficulties. For example, the total investment estimate for projects is still limited, the total budget has not been accurately estimated, many projects have had to adjust the total investment due to price fluctuations, changes in standards... There are still problems with the provisions of the law, for example, problems with the content of environmental impact assessment, lack of land for filling, conversion of forest land takes a long time...

Therefore, to build an accurate medium-term investment plan and ensure sufficient capital for implementation, it is necessary to clearly identify the needs, anticipate future price increases, and increase the reserve limit. To resolve the problems of the law, it is necessary to propose law adjustments and related regulations in the direction of increasing decentralization to localities and establishments, especially small-scale projects in a district.

bản Văng Môn Nga My7
Many poor and near-poor households have the opportunity to develop their economy from capital support from the National Target Program for Socio-Economic Development of Ethnic Minority and Mountainous Areas. Photo: Hoai Thu

The leaders of Tuong Duong district also proposed that the central level increase investment support for the districts of Western Nghe An, border districts, especially districts with many hydropower projects, with the aim of improving the quality of people's lives, contributing to socio-economic development, ensuring security and national defense. Consider proposing to adjust related regulations, such as in the laws: Law on Environmental Protection, Law on Minerals in the direction of increasing decentralization to localities, establishments, specific regulations for each type of project, corresponding to the appropriate total project investment.

Regarding Thanh Chuong district, regarding the limitations that need to be overcome to accelerate the disbursement of capital for national target programs, the leader of the district People's Committee said that the disbursement of public investment capital for national target programs from the central budget in new rural construction and socio-economic development in ethnic minority and mountainous areas is still facing "difficulties" when the situation of investors not proactively implementing has not been completely resolved.

The reason is that the capital source for supporting district budget and commune budget for investment in construction of works is from the source of land use rights, but because the land use rights auction market has slowed down in both quantity and land price, investors do not have capital. In addition, when proposing investment policies for construction of works, investors have not carefully reviewed the ability to ensure counterpart capital, especially for works that are mainly local budget counterpart.

HĐND tỉnh giám sát hiệu quả thực hiện giải ngân đầu tư công tại huyện Thanh Chương. Ảnh tư liệu MInh Quân
The Provincial People's Council supervises the effectiveness of public investment disbursement in Thanh Chuong district. Photo courtesy of Minh Quan

Therefore, Thanh Chuong district proposed solutions, such as: Urging investors to review their ability to secure capital to implement the remaining projects. For projects under the National Target Program on New Rural Development and the National Target Program on Socio-Economic Development in Ethnic Minority and Mountainous Areas for the 2021-2025 period that have not been implemented, the Provincial People's Committee is requested to consider and decide to submit to the Provincial People's Council the allocation of the remaining public investment capital for the 2021-2025 period for investors to pay for completed volumes, and implement projects whose technical and economic reports have not been approved.

For projects invested by the District People's Committee from the provincial budget with counterpart funds from the district budget: Because the district budget counterpart funds for investment in construction of projects mainly come from land use rights, but because the land use rights auction market has stagnated in both quantity and land price, it is not possible to ensure counterpart funds for investment in construction of works. Therefore, it is proposed to include it in the medium-term public investment plan for the period 2026-2030.

Đoàn giám sát HĐND tỉnh khảo sát Dự án Nâng cấp tuyến đường du lịch từ Quốc lộ 7 đến khu du lịch thác Khe Kèm. Ảnh: Mai Hoa
The Provincial People's Council's monitoring delegation surveyed public investment projects in Con Cuong district. Photo: Mai Hoa

The difficulty in finding counterpart funds to implement public investment projects is not only encountered by Tuong Duong and Thanh Chuong localities, but is a common situation in localities in the province, especially in highland and mountainous districts. And the main reason is that the district has difficulty in finding counterpart funds when the revenue from granting land use rights and land auctions is limited and ineffective.

Regarding the local feedback, the Provincial People's Council and the Provincial People's Committee of Nghe An have conducted monitoring, reception and synthesis to submit to the levels and sectors, and included in the work content according to their authority to gradually resolve. In the coming time, the National Assembly is expected to pass the amendment to the 2019 Law on Public Investment, so the Provincial People's Council and the Provincial People's Committee also recommend that the Provincial National Assembly Delegation pay attention to and synthesize the difficulties in the practical implementation of the Law on Public Investment to make recommendations to the National Assembly during the process of discussing and passing the draft Law.

Hoai Thu