Power outage schedule in Hanoi on December 6, 2024
According to Hanoi Electricity, there is a scheduled power outage in districts in Hanoi on December 6, 2024.
The latest information on power outage schedule in Hanoi areas on Friday, December 6, 2024 is updated from the Hanoi Electricity portal.
There can be many reasons for power outages in Hanoi. Factors that can cause power outages include natural disasters, floods, storms, or the management unit carrying out repairs and maintenance of power grid lines.

This is the power outage schedule in the plan of the power companies. Depending on the weather situation, the plan of the power units... the power outage schedule can be adjusted and postponed in some places.
Hanoi power outage schedule on December 6, 2024
Electricity | Time | Area | Reason | Status |
Dong Anh Electricity Company | From 05:00 to 06:15 | Part of Nam Hong commune, Bac Hong commune, Van Noi commune. | Serving the renovation and upgrading of the power grid | Approved |
Dong Anh Electricity Company | From 06:15 to 14:30 | Part of Nam Hong commune, Bac Hong commune, Van Noi commune. | Serving the renovation and upgrading of the power grid | Approved |
Dong Anh Electricity Company | From 14:30 to 16:00 | Part of Nam Hong commune, Bac Hong commune, Van Noi commune. | Serving the renovation and upgrading of the power grid | Approved |
Gia Lam Power Company | From 07:00 to 12:00 | Part of Phu Thi commune | Serving the renovation and upgrading of the power grid | Approved |
Gia Lam Power Company | From 07:00 to 12:00 | Part of Yen Thuong commune | Serving the renovation and upgrading of the power grid | Approved |
Gia Lam Power Company | From 08:00 to 12:00 | Part of Trau Quy Center | Serving the renovation and upgrading of the power grid | Approved |
Gia Lam Power Company | From 09:30 to 11:30 | Vietnam Railway Corporation Branch - Ha Thai Hai Railway Exploitation | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Power Company | From 07:00 to 11:00 | 01 KH New Hope | Serving the renovation and upgrading of the power grid | Approved |
Gia Lam Power Company | From 10:30 to 12:00 | Bat Trang Ceramics Company Limited | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Power Company | From 08:00 to 10:00 | 01 customer HAPROSIMEX-moca | Serving the renovation and upgrading of the power grid | Approved |
Gia Lam Power Company | From 09:00 to 10:00 | Hanoi Irrigation Development Investment One Member Co., Ltd. | Serving the renovation and upgrading of the power grid | Approved |
Gia Lam Power Company | From 14:00 to 16:00 | Giang Anh Trading Company Limited | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Power Company | From 13:30 to 16:30 | Part of Village Eight | Serving the renovation and upgrading of the power grid | Approved |
Thanh Tri Power Company | From 07:00 to 15:30 | Water Well Station H10, H11, H12 Phap Van, Lighting Highway 1B | Serving the renovation and upgrading of the power grid | Postpone |
Thanh Tri Power Company | From 05:00 to 07:00 | Nam Dai Phong Station - Tu Hiep Urban Area | Serving the renovation and upgrading of the power grid | Postpone |
Hoang Mai Power Company | From 07:30 to 11:30 | MBA1, MBA2 Den Lu 2 | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Power Company | From 12:00 to 17:00 | Part of Linh Nam ward | Serving the renovation and upgrading of the power grid | Approved |
Hoan Kiem Electricity Company | From 08:00 to 11:00 | From number 1 to number 39, from number 2 to 64 Hang Hom street, number 17C2 Hang Quat street, Hang Chi alley, from number 84 to number 116 Hang Gai street. | Serving the renovation and upgrading of the power grid | Approved |
Hoan Kiem Electricity Company | From 13:00 to 16:00 | Hang Ngang Street. From house number 2 to house number 34 Hang Can Street | Serving the renovation and upgrading of the power grid | Approved |
Hoan Kiem Electricity Company | From 05:00 to 08:00 | House numbers 40 to 42 Lo Su street; house numbers 38, 32; house number 20 Lo Su street. | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Power Company | From 08:00 to 16:00 | From house number 44 to house number 48, from house number 77 to house number 91, lane 69A Hoang Van Thai. - From house number 72 to house number 112, from house number 141 to house number 223, lane 69A Hoang Van Thai. - The entire alley 69A/72, alley 69A/177 - The entire alley 162/25, alley 162/29 Le Trong Tan street - From house number 107 to house number 131, from house number 48 to house number 70, lane 69A Hoang Van Thai. - All alleys 69A/48, alley 69A/117, alley 69A/131 Hoang Van Thai street From house number 66 to house number 78, from house number 51 to house number 71 lane 192 Le Trong Tan - All alley 192/66, alley 192/72 Le Trong Tan street. | Serving the renovation and upgrading of the power grid | Approved |
Hai Ba Trung Power Company | From 08:30 to 10:00 | No - Low voltage load switched to generator | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Power Company | From 05:00 to 12:00 | Part of Mai Dong ward | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Power Company | From 07:00 to 11:00 | MBA1, MBA2 But Both | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Power Company | From 08:00 to 12:00 | MBA General Warehouse 15BQP | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Power Company | From 08:00 to 12:00 | MBA1, MBA2 Den Lu 3 | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Power Company | From 13:00 to 16:00 | Part of Lu Temple 10 | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity Company | From 14:00 to 17:00 | Part of residential group 6.5, Dong Mai ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity Company | From 06:30 to 08:00 | Institute of Science and Technology - Ministry of Public Security. | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity Company | From 08:00 to 12:00 | Part of residential group 4, 5, Dong Mai ward | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power Company | From 07:00 to 15:00 | Part of Xuan Khanh ward | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power Company | From 07:15 to 09:00 | Part of Hospital 105 | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power Company | From 13:30 to 15:15 | Part of Z151 factory | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power Company | From 15:00 to 16:45 | Part of Z151 factory | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power Company | From 09:00 to 11:00 | Part of the Reconnaissance School | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 07:00 to 07:45 | Customers of Huong hamlet, Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 07:00 to 12:00 | Customers of Xoan TBA, Van Hoa commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 08:00 to 08:45 | Tan Phong customer belongs to Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 08:00 to 09:00 | Customers of TBA TTDVCG TECHNOLOGY commune Minh Quang | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 09:00 to 09:45 | Customer Tan Phong 3 belongs to Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 10:00 to 10:45 | Customers of Giau hamlet, Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 11:00 to 12:00 | Phong Van TBA customers in Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 13:30 to 14:15 | Van Hoi customer belongs to Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 13:30 to 14:30 | Customers belong to Minh Quang People's Committee Sub-district, Minh Quang Commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 14:30 to 15:30 | Customers of TBA Thon Noi, Minh Quang commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 14:30 to 15:15 | Cau Vung customer in Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 15:30 to 16:15 | Dong Thinh customer in Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 15:30 to 16:30 | Customers belong to Minh Hong 2 Substation, Minh Quang Commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 16:30 to 17:15 | Phong Van 2 customer belongs to Phong Van commune | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Power Company | From 09:00 to 10:00 | Customers belong to Minh Quang 1 Substation, Minh Quang Commune | Serving the renovation and upgrading of the power grid | Approved |
Dan Phuong Power Company | From 07:00 to 13:30 | Part of Tho Xuan commune | Serving the renovation and upgrading of the power grid | Approved |
Dan Phuong Power Company | From 08:00 to 11:00 | Part of Dong Thap commune; Song Phuong | Serving the renovation and upgrading of the power grid | Approved |
Thach That Power Company | From 07:00 to 15:00 | Can Kiem Commune | Serving the renovation and upgrading of the power grid | Approved |
Quoc Oai Power Company | From 07:00 to 10:00 | Part of Can Huu Commune | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Power Company | From 09:00 to 10:00 | Khuc Tan Textile Company Limited | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Power Company | From 10:00 to 12:00 | Thu Do Sports Equipment Manufacturing and Trading Company Limited | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Power Company | From 08:00 to 09:00 | Dai Viet Textile Co., Ltd. | Serving the renovation and upgrading of the power grid | Approved |
Phu Xuyen Power Company | From 07:00 to 15:00 | Part of Dai Xuyen commune | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Power Company | From 06:00 to 14:00 | Van Phu Commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 07:30 to 14:30 | Part of Dong Tam commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 10:20 to 11:20 | Huy Toan Construction Materials Production Company Limited, Dong Tam Commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 15:20 to 17:00 | Thong Nhat Company Limited Mieu Mon area | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 08:40 to 09:40 | Hong Son 4 Brick Production Facility, Hong Son Commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 13:30 to 14:30 | Hai Hung Construction and Trading One Member Co., Ltd., Mieu Mon area | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 07:00 to 15:00 | Part of Huong Son commune (TBA Tuyet Son Pagoda) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 07:00 to 15:00 | Hoa Lac village, An Tien commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Power Company | From 07:00 to 08:00 | An Tien Company Limited An Tien Commune | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power Company | From 06:45 to 17:15 | Part of Lien Mac commune | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power Company | From 07:15 to 15:45 | Part of Lien Mac commune | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power Company | From 08:00 to 15:00 | Part of Lien Mac commune | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power Company | From 08:30 to 13:30 | Part of Lien Mac commune | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity Company | From 08:00 to 12:00 | Part of Dong Mai service land, Dong Mai ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity Company | From 08:00 to 12:00 | Part of residential group 6,8 Dong Mai ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity Company | From 14:00 to 17:00 | Part of residential group 1,2 Dong Mai ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity Company | From 06:30 to 08:00 | Phu Thai Group Corporation. | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Power Company | From 08:00 to 12:00 | Click to download Building A, Golden Palace, Me Tri Ward, Nam Tu Liem District, Hanoi City | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 07:00 to 09:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 09:00 to 11:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 11:00 to 13:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 14:00 to 15:30 | Group 7, Group 8 Phuc Dien Ward | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 16:00 to 17:30 | Group 7, Group 8 Phuc Dien Ward | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 00:00 to 06:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 08:00 to 10:00 | Phuc Hung Mechanical | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 06:00 to 12:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Bac Tu Liem Power Company | From 13:30 to 16:00 | No information yet | Serving the renovation and upgrading of the power grid | Postpone |
Above is the power outage schedule for areas in Hanoi on December 6, 2024. Currently, there is no information about power outages in some other locations. Nghe An Newspaper will regularly update the latest and most accurate information about the power outage schedule in Hanoi for readers to follow.