Agree on a solution to handle cases of houses damaged by road construction in Vinh City
After Nghe An Newspaper reported, on the afternoon of December 20, 2024, the local authorities and the construction unit signed a commitment to take responsibility if damage occurs to Ms. Nguyen Thi Tinh's house (Trung My block, Hung Dong ward) during the construction of lane 56 Nguyen Su Hoi.
Nghe An Electronic Newspaper issue dated December 19, 2024 had an article"It is necessary to thoroughly handle the road construction that damaged houses in Vinh City.", reflecting the indignation of Ms. Nguyen Thi Tinh, residing at house number 1, lane 56, Nguyen Su Hoi street, Trung My block, Hung Dong ward (Vinh city), about the fact that while she was away, the construction unit of this lane road, Nam Truong Thanh Construction Joint Stock Company (headquartered on Truong Chinh street, Le Loi ward, Vinh city), damaged her house.
.jpg)
Ms. Tinh requested the local authorities to intervene to protect her rights. On November 8, 2024, representatives of the local authorities and the construction unit went to Ms. Tinh's house to inspect the scene to make a record to resolve the issues that Ms. Tinh requested.
Then, on November 19, 2024, Hung Dong Ward People's Committee organized a meeting between representatives of Vinh City Land Fund Development Center (investor); the construction unit is Nam Truong Thanh Construction Joint Stock Company; local authorities, the block executive committee and Ms. Tinh, to resolve Ms. Tinh's urgent request for intervention on November 8, 2024.
.jpg)
At this meeting, the People's Committee of Hung Dong Ward also requested the construction unit and the investor, the Vinh City Land Fund Development Center, to ensure safety during construction, and to calculate damaged assets as a basis for compensation... In addition, a commitment must be made that if Ms. Tinh's house is damaged during construction and 3 months after the project is completed, compensation must be paid according to regulations. However, up to this point, the investor and the construction unit have not yet resolved the matter.
.jpg)
After Nghe An Newspaper published an article reflecting on the situation, on the afternoon of December 20, 2024, under the witness of representatives of the local government and the Central American bloc executive committee, Nam Truong Thanh Construction Joint Stock Company measured the current status of the house and made a commitment to perform the construction safely and not damage Ms. Tinh's house.
If during the construction process and after 3 months from the date of completion of the project, Ms. Tinh's house is damaged, Nam Truong Thanh Construction Joint Stock Company and the Central American Executive Committee will be responsible for coordinating to resolve the issue...