On the construction site of the embankment to prevent landslides along the Nam Mo River.

July 14, 2015 16:52

(Baonghean) - After a period of suspension due to funding difficulties, construction has resumed on the embankment project to prevent erosion along the Nam Mo River, from Tam Bridge to Cung Bridge in Block 4, Muong Xen town, Ky Son district, with a length of 1,963m.

The Nam Mo River embankment project, with a total investment of 140 billion VND from government bonds, commenced in 2013. To date, 921 meters out of the total 1,963 meters of the project have been completed. This is a key project for Ky Son district; upon completion, it will address the long-standing problem of riverbank erosion, contributing to minimizing damage to people and property during the rainy season and floods.

Toàn cảnh công trường thi công kè chống sạt lỡ bờ sông Nậm Mộ
Overview of the construction site for the embankment to prevent erosion along the Nam Mo River.
Làm mặt băn
But the landslide site is gradually being filled in.
Công nhân trải vải địa kỹ thuật chống thấm
Workers lay geotextile waterproofing fabric.
Làm mặt bằng để lát bê tông
Prepare the ground for concrete paving.
Những tấm bê tông
Precast concrete is poured right at the construction site.
khuân bê tông

Workers laboriously carried each concrete slab to the installation site under the scorching sun, with temperatures exceeding 40 degrees Celsius.

lắp
đặt
một đoạn hoàn thành
With the rapid pace of construction, the embankment project to prevent erosion along the Nam Mo River has now been completed by nearly 50%.
Tiếp tục mặt bằng
The project is being constructed by Phu Nguyen Hai Co., Ltd. and is expected to be completed in two years.

Quang An - Tuong Anh