Khe Da Bridge is unfinished, Tien Dong residents are worried about the flood season

Nhat Lan - Vo Hai DNUM_BAZAIZCACF 14:20

Khe Da Bridge was started in November 2022 with the goal of ensuring convenient and safe travel for people, contributing to promoting socio-economic development for the difficult mountainous area of ​​Tan Ky district (old), however, up to now, the bridge project is still under construction.

Below are images of the unfinished Khe Da bridge construction, causing great difficulty for people and vehicles, reported by PV. Nghe An Newspaper, Radio and Television recorded on August 8, 2025.

gen-n-z6889928992277_7f093f123ebba924665b98c6c8afaebd.jpg
Khe Da Bridge is a bridge project on Route 534D, on the section passing through Dong Van commune of Tan Ky district (old), now in Tien Dong commune. The bridge started construction in November 2022, and is scheduled to be completed by the end of 2024. Photo: Nhat Lan
gen-n-z6889928931872_3fcf00e3fa612e61c85c337a3c635bfb.jpg
However, despite being more than 8 months behind schedule, the Khe Da bridge project has reached about 90% of its volume, only completing the construction of the lower structure, installing 16/16 T-beams and the railing system, and the bridge deck is still under construction. Vehicles participating in traffic on the section passing through Khe Da bridge are limited to a load of no more than 3.5 tons. Photo: Nhat Lan
gen-n-z6889928996205_16d28aa5cf43358a930bd5052b3fb40c.jpg
During the construction of Khe Da bridge, a temporary bridge was built on route 534D through Khe Da, which was precarious and did not ensure traffic safety. Photo: Vo Hai
gen-n-z6889928986627_79a4bf1f4010bd4b2d1cf346cf317884.jpg
Because Khe Da bridge is under construction, traffic is very difficult, causing environmental pollution for the residential area around this area. Photo: Nhat Lan
gen-n-z6889928940811_a3ca5ec52a2bc6c3f9247e5c3d692706.jpg
Current status of Khe Da bridge surface under construction. Photo: Vo Hai
gen-n-z6889928939573_4876c99eaa54c330e77c43629539709b.jpg
Road 534D seen from Khe Da Bridge. Photo: Nhat Lan
gen-n-z6889928937513_293ad70288a5a014599ff72601de59ba.jpg
Steel materials left by the construction unit on the surface of Khe Da bridge. Photo: Vo Hai
gen-h-z6889928933270_d066612750068860beed7e8f5057bd1a.jpg
The steel waiting at Khe Da bridge project is currently rusted. According to the management unit, the construction unit has been working slowly in recent months, and has stopped since storm number 3. Photo: Nhat Lan
gen-h-z6889928983424_89e8e9a5fa7c77bc59001a9c1453ba67-2729704f70152990a3793c0af27ee036.jpg
According to the representative of Tien Dong Commune People's Committee, the Khe Da bridge project aims to replace Khe Da spillway which is often deeply flooded, causing traffic disruption during the rainy season, affecting storm and flood response in Dong Van Commune, Tan Ky District (old); ensure convenient and safe travel for people and students going to school; serve the needs of trade and production, contribute to socio-economic development, and improve the lives of people in the benefiting area. However, due to the slow progress of the project, during storm No. 3 on July 22, Tien Dong Commune had to mobilize forces to be on duty here to ensure the safety of vehicles and passersby. The representative of Tien Dong Commune People's Committee also informed that, from the voters' petition, at the recent 31st session of the Provincial People's Council, the delay in the progress of Tien Dong bridge project was reported and recommended by the commune's leaders so that the competent authorities could pay attention and direct the construction unit to urgently complete it to meet the investment target. Photo: Nhat Lan

Nhat Lan - Vo Hai