Dien Chau - Bai Vot Expressway opens to traffic as scheduled
PV Group - April 27, 2024 12:54
(Baonghean.vn) - After nearly 2 years of construction, the Dien Chau - Bai Vot expressway will open to traffic during the April 30 - May 1 holiday as scheduled. The travel time from Vinh City to Hanoi is just over 3 hours. This is a remarkable result from the efforts of the entire political system and the project's contractors.
The Dien Chau - Bai Vot expressway project (North - South expressway) with a total investment of more than 11,000 billion VND, has a length of 49.3 km, passing through 2 provinces: Nghe An (44.4 km), Ha Tinh (4.9 km). After more than 2 years of construction, the project has now been opened to traffic in Nghe An. Photo: PV Accordingly, the project will open about 30 km from the National Highway 7 intersection (Dien Cat commune, Dien Chau district) to the National Highway 46B intersection (Hung Tay commune, Hung Nguyen district) in Nghe An. As of this morning (April 27), the construction unit is checking the final items. Photo: PVAfter the highway is opened to traffic, the travel time from Vinh City to Hanoi will be just over 3 hours, much faster than traveling on National Highway 1A before. Photo: PVMr. Truong Duc Lien - Deputy General Director of Phuc Thanh Hung Investment Joint Stock Company, the construction company of Dien Chau - Bai Vot Expressway Project, said: The opening ceremony will be held tomorrow afternoon (April 28). After the opening ceremony, vehicles can travel on the expressway from April 29. Photo: PVAt the intersections with the highway, there are signs to guide vehicles in the right direction. Photo: PVConstruction units are urgently completing the final items such as road markings, corrugated iron, anti-glare nets, traffic signs and fences. Photo: PVAt highway overpasses, vehicles can travel normally. Photo: PVIt is known that in order to open the Dien Chau - Bai Vot route on schedule, hundreds of machines and workers were mobilized by the construction unit to work day and night, divided into many shifts, to meet the peak demand of people during the holiday. Photo: PV
On April 26, some people brought trees to block the road on the Dien Chau - Bai Vot highway, through Dien Phu commune, Dien Chau district, demanding compensation due to the impact of blasting during the highway construction on people's houses.
Sharing with Nghe An Newspaper about this issue, Mr. Tang Van Luyen - Chairman of Dien Chau District People's Committee, said: The incident of blasting at the Dien Chau - Bai Vot expressway construction section through Dien Phu commune by the contractor Cienco 4 Group Joint Stock Company affected 6 households, of which 5 households have not yet received compensation. Regarding this incident, the District People's Committee, the project enterprise, the contractor Cienco 4 Group Joint Stock Company and the insurance appraisal agency have worked to determine the extent of loss for compensation. On April 26, the District People's Committee and related units worked directly with the households and agreed to make full payment on May 2, 2024. The households agreed to this plan and returned home, and the planned traffic opening was not affected.
Share your opinion
Your comment has been submitted and will be displayed after being approved by the editorial team. The editorial board reserves the right to edit comments to comply with the Newspaper's content regulations.