Con Cuong: 10.5 km of road "missed" for more than 2 years

DNUM_BJZBAZCABF 10:03

(Baonghean) - More than 2 years have passed since the expected completion date, but the road from Mau Duc commune to Thach Ngan commune, Con Cuong district, over 10 km long, is still unfinished, much to the anticipation of local people.

This route is designed according to the standards of grade VI mountainous roads (TCVN 4054-2005), the roadbed is 6m wide, the road surface is 3.5m wide, the total length of the route is 10.5km. The total investment of this project is nearly 53 billion VND. The approved construction progress is 18 months, starting on November 14, 2011 and ending on May 14, 2013.

Up to now, the construction unit has only completed 2.1 km of the Thach Ngan commune section and handed it over for use. In Mau Duc commune, only 11/17 culvert locations have been completed; the remaining volume is 6 culvert locations, roadbed, road surface foundation and traffic safety have not been implemented.

Con đường còn rất hoang sơ
The inter-commune road Mau Duc - Thach Ngan passes through many mountainous areas, so it plays a vital role in the lives of local people.
Nhiều nơi nền đường đất cũ đã xuống cấp, đi lại rất khó khăn trong khi nền đường mới lại  thi công chậm tiến độ
In many places, the old dirt road has deteriorated, making travel very difficult, while the construction of the new road is behind schedule. Photo taken at Ke Me village, Mau Duc commune, Con Cuong on the morning of October 16, 2015.

Meanwhile, the old dirt road has deteriorated, making travel and trade for people in Mau Duc and Thach Ngan communes very difficult, especially during the rainy season. Many locations on the road are muddy and seriously slippery.

Mr. Lang Van Nam's family in Ke Me village, Mau Duc commune has 2 hectares of acacia and more than 1 hectare of cassava, but every harvest season, they struggle with the problem of transportation due to degraded roads. "Transporting agricultural and forestry products is difficult, so the investment cost increases, significantly affecting income. In addition to affecting business, students in these villages also face many difficulties when going to school," said Mr. Nam.

Mr. Lo Van That, Chairman of Mau Duc Commune People's Committee, said: "Voters have proposed to speed up the construction progress many times, but the commune's only solution is to mobilize internal resources and ask for support from the district to temporarily fix the degraded sections. Every year, the commune has to repair the road on average 2-3 times."

Trước tình hình đó, các xã phải huy động người dân thu gom cát, sạn để gia cố những đoạn xuống cấp để phục vụ đi lại mùa mưa lũ
Faced with this situation, communes had to mobilize people to collect sand and gravel to reinforce degraded sections to serve people's travel during the rainy season. Photo taken at Ke Trang village, Mau Duc commune on the morning of October 16, 2015.

Mr. Ngan Xuan Dung, Chairman of the People's Committee of Thach Ngan Commune, said: "Every time commune officials go to the center of Con Cuong district for a meeting, they have to go back to Anh Son and then follow National Highway 7 to Con Cuong town. Besides, the selling price of agricultural products is also being squeezed by traders. Hopefully, this route will soon be restarted and completed to create more convenient conditions for people to travel."

Currently, the biggest difficulty is that the investment capital demand for the project is too large, but the annual investment budget capital is too low, and there is no allocation of land clearance capital, leading to slow implementation progress. Up to now, the total capital allocated and paid for the project is only over 14.8 billion VND out of the total investment of nearly 53 billion VND.

Người dân xã Mậu Đức, Con Cuông cùng nhau gia cố nền đường
People of Mau Duc commune, Con Cuong focus on reinforcing the roadbed
Nhân dân xã Mậu Đức khơi thông cống thoát nước để tránh úng ngập cho tuyến đường vào mùa mưa
People of Mau Duc commune clear the drainage to avoid flooding on the road during the rainy season.
Nhân dân xã Mậu Đức cũng khơi thông các tuyến mương thoát nước 2 bên đường
People of Mau Duc commune also cleared drainage ditches on both sides of the road.

Mr. Tran Anh Tuan, Head of the Management Board of Construction Investment Projects of Con Cuong District, said: The project was implemented on the basis of the province's excess revenue. In recent years, the excess revenue has disappeared, so the project has not been allocated capital since 2012. The project has not been included in the annual concentrated capital allocation of the provincial budget by the Provincial People's Committee.

“Given the above situation, Con Cuong district proposes that the Provincial People's Committee include this project in the priority list of the 2015-2020 medium-term public investment plan according to the provincial budget for basic construction, which is concentrated and allocated annually to have a basis for continuing to implement the project,” said Mr. Tuan.

Nhat Le