(Baonghean.vn) - Nghi Thiet grinding station is an important part of Song Lam cement factory when it brings Clinker from Song Lam cement factory in Do Luong here and produces products.The Vissai Group is currently investing heavily in the Vissai grinding station and port, aiming to soon serve the production and consumption of the group's products by the end of 2016.
 |
Road D4 is the road serving the transportation of cement from Do Luong to Nghi Thiet port. Nghe An is currently interested in investing in construction and site clearance. In the photo: Contractors are actively constructing road D4 to the port. |
 |
Despite lack of capital and harsh weather, the construction unit still mobilized machinery to continuously build roads to meet the progress of Song Lam Cement Factory. |
 |
There is a section of this road being cleared so it is very difficult for people to travel. |
 |
The Vissai Group is speeding up construction of Nghi Thiet crushing station items at Nghi Thiet beach. |
 |
There are always thousands of workers at the crushing station construction site at Nghi Thiet port. |
 |
Construction of water tank for grinding station. Grinding station project and international specialized seaport are 2 items associated with Song Lam Cement factory project (Bai Son commune, Do Luong district). |
 |
From a sand and rock field in Nghi Thiet, The Vissai has leveled the ground and actively constructed. In the photo: Contractor Cienco 4 is constructing the port for The Vissai Group |
 |
Piles are being driven into the offshore wharf to welcome ships to shore when completed. |
 |
New resettlement areas have sprung up on both sides of D4 road to make way for the road construction project. |
PV Group