'The Vinh dike needs to be rebuilt to alleviate concerns.'
(Baonghean.vn) - After 3 days of dike reinforcement in Vinh, the forces have excavated and filled nearly 1000m of embankment.3 The earth and rocks have been largely reinforced at the weak points.
"Small traders at Vinh market will suffer less damage if they have property insurance."
"We will not leave small traders at Vinh Market alone in times of hardship."
"Times when small traders at Vinh market lost everything"
"Vinh Market flooded again, traders rush to move goods."
This morning, October 15th, nearly 200 soldiers are still dropping boulders into the Vinh River to reinforce the embankment. According to a report from the Vinh Tan Ward People's Committee, during three days of intensive embankment work, the forces have excavated and built 200 meters of embankment.3Sand and 200 cubic meters of soil were used to reinforce 30 meters of the eroded riverbank and to lay 250 meters of concrete.3Rocks were thrown into the river, totaling nearly 1000 meters.3 Soil, rocks, and sand have been mobilized.
![]() |
| The embankment on the Hung Nguyen side has been reinforced with sandbags and bamboo stakes. Photo: Tran Chau |
Today, we are scheduled to complete the lowering of the 300m section of the river.3Rocks. The water level of the Vinh River has now dropped by more than 1 meter due to effective drainage efforts, and dike reinforcement work is expected to be completed today.
Mr. Nguyen Hoang Manh, Chairman of the People's Committee of Vinh Tan Ward, Vinh City, said: "The Vinh River dike has been weak and degraded for a long time, not upgraded for decades. The dike banks are weak, the soil is soft, and the dike body is low. Vinh Tan Ward has repeatedly petitioned the city and province regarding the need to rebuild, reinforce, and raise the entire Vinh River dike body, as leaving it as it is still unsafe due to the current situation where several vulnerable points require reinforcement."
Discussing flood and storm prevention plans for the beginning of the year, the Chairman of Vinh Tan ward stated: Upgrading the dike is the responsibility of the province; the locality only mobilizes the people in case of an emergency and disseminates information about evacuation and protecting lives.
![]() |
| The Vinh dike embankment is now more stable after three days of reinforcement by the soldiers. Photo: Tran Chau |
The recent incidents at the Vinh dike show that the weather is becoming increasingly unpredictable, the consequences of natural disasters are growing, and in Vinh, draining floodwaters on the Vinh River is difficult, especially when the water level of the Vinh River is level with the Lam River, thus increasing the risk of dike breaches.
If the local authorities had made thorough preparations based on the "four on-the-spot" principle and had contingency plans for various incidents, the dike repair work wouldn't have been so rushed.
The current embankment reinforcement and protection measures are only temporary and stopgap. In the long term, the Vinh River embankment needs to be upgraded and renovated like other embankments throughout the province.
![]() |
| Today, soldiers from the Provincial Military Command continued to drop 300 cubic meters of rocks into the riverbed to divert the flow. Photo: Tran Chau |
| According to meteorological and hydrological data, rainfall from October 9th to 12th in Nghe An province peaked in many areas. Con Cuong recorded 166.0mm; Nghia Dan 230.5mm; Nam Dan 354.0mm; Vinh 401.0mm; Quy Hop 177.0mm; Thanh Chuong 392.0mm; Quynh Luu 400.0mm; and Cua Hoi 278.0mm. Vinh's rainfall reached its highest level in over 10 years. The heavy rains and flooding have caused severe inundation in many areas, and the Vinh river dike is at risk of breaching. |