The flood control dike upgrade project is still unfinished.

• August 18, 2016 05:55

(Baonghean.vn) - To prevent floods and natural disasters, many critical dike sections in the province have been upgraded. However, some projects have dragged on… delays in construction have caused concern among local people. The dike section in Luong, Yen, and Khai communes of Thanh Chuong district is a typical example.

Hơn 3 năm nay, việc nâng cấp tuyến đê qua các xã Lương - Yên - Khai của huyện Thanh Chương bị ngưng trệ.
For over three years, the upgrading of the dike system through Luong, Yen, and Khai communes in Thanh Chuong district has been stalled.

Four years ago, the people of the three communes of Thanh Luong, Thanh Yen, and Thanh Khai in Thanh Chuong district were overjoyed when the local government announced that the "Upgrading the Luong - Yen - Khai dike in Thanh Chuong district" project had been approved. Immediately afterwards, they saw a flurry of construction vehicles arriving to begin work.

But the joy was short-lived; after only a short period of construction, the vehicles quietly left the site, leaving it unfinished. This not only worried the people but also hindered their lives and production. Mr. Nguyen Kim Nam, Secretary of the Party branch of Yen Hong village, Thanh Yen commune, expressed his frustration: “We hadn’t even had time to celebrate the dike upgrade project before it was left unfinished. The area has become a mess of rocks and soil, making it very difficult for people to travel and carry out their production…”

Người dân thôn Yên Hồng, xã Thanh Yên (Thanh Chương)
Residents of Yen Hong village, Thanh Yen commune (Thanh Chuong district) are "sitting on pins and needles" as the dike construction is progressing slowly.

The project to upgrade the Luong - Yen - Khai dike in Thanh Chuong district, section from K3+262 to K6+133, is part of Component 4 of the "WB Disaster Management Project 5," with the Department of Agriculture and Rural Development as the investor. According to the tender notice dated November 23, 2012, issued by the Department of Planning and Investment, the project comprises three packages with a total value of nearly 68 billion VND. Of this, the construction portion accounts for approximately 46.6 billion VND.

This project was designed with a base width of 30m, a top width of 5m, and a height of 2-2.85m higher than the old dike, sufficient to prevent flooding up to alert level 3. Since its commencement, only a section from Thanh Khai commune to Yen Thang village has been completed, with the rest unfinished. The section from Yen Hong village through Yen Long to Thanh Luong commune has not been completed, and sections through Yen Hong and Yen Binh villages are partially completed. Particularly concerning is one point in the residential area of ​​Yen Hong village where the entire dike has collapsed, posing a direct threat to the lives and property of residents not only during the rainy season but also on ordinary days.

Nhiều hộ dân lo lắng chuẩn bị thuyền chống lũ lụt
Many households are worried and preparing boats to cope with the flooding.

For the past three years, every time the weather forecast predicts a storm or heavy rain, the authorities and people of Thanh Yen commune are always worried. Mr. Le Hong Long, Chairman of the People's Committee of the commune, shared: “Every time it rains and storms, we feel like we're sitting on a powder keg, worried and uneasy because the dike in our area is deteriorating, while the dike upgrade project remains unfinished. We have repeatedly reported this to the district and province and have been told that funding is being allocated…” Waiting anxiously, people in the communes behind the dike have to repair their basket boats, prepare bamboo rafts, and even rafts made of banana trees to prepare for unforeseen circumstances when floods occur.

Interview clip with Mr. Le Hong Long - Chairman of the People's Committee of Thanh Yen Commune

Thanh Dinh - KT Huu Quan