Đường thi công dang dở, người dân thấp thỏm lo sạt lở
(Baonghean.vn) - National Highway 7A sectionfrom km 147 to km 148The border between Mac village and Cay Me village in Thach Giam commune (Tuong Duong district) frequently experiences landslides, posing a safety risk to road users.
This project aims to address subsidence caused by the water damming of the Khe Bo Hydropower Plant. The project's investor is the Khe Bo Hydropower Project Management Board. Despite four years of construction, the less than 1km stretch of road remains unfinished.
![]() |
| The new road, which is currently unfinished, is on the right. Photo: Trang Trang |
The fact that the road construction has been unfinished for many years has significantly affected people and vehicles passing through, as it is dusty in sunny weather and muddy and slippery in rainy weather, with landslides and fallen trees.
A bus driver on the Vinh - Ky Son route said that landslides occur not only on rainy days, but also in sunny weather, due to groundwater leaks and weak soil. Therefore, the road is often cut off and blocked.
![]() |
| Tình trạng sạt lở diễn ra ngay trong cả những ngày nắng ở đoạn đường thi công dang dở. Ảnh: Tràng Tràng |
Với thực tế nêu trên, cơ quan chức năng cần có biện pháp đề nghị đơn vị thi công để đẩy nhanh tiến độ hoàn thành công trình, không để ảnh hưởng đến người, phương tiện qua lại./.
Tràng Tràng