With the road under construction, residents are worried about landslides.
(Baonghean.vn) - National Highway 7A sectionfrom km 147 to km 148The border between Mac village and Cay Me village in Thach Giam commune (Tuong Duong district) frequently experiences landslides, posing a safety risk to road users.
This project aims to address subsidence caused by the water damming of the Khe Bo Hydropower Plant. The project's investor is the Khe Bo Hydropower Project Management Board. Despite four years of construction, the less than 1km stretch of road remains unfinished.
![]() |
| The new road, which is currently unfinished, is on the right. Photo: Trang Trang |
The fact that the road construction has been unfinished for many years has significantly affected people and vehicles passing through, as it is dusty in sunny weather and muddy and slippery in rainy weather, with landslides and fallen trees.
A bus driver on the Vinh - Ky Son route said that landslides occur not only on rainy days, but also in sunny weather, due to groundwater leaks and weak soil. Therefore, the road is often cut off and blocked.
![]() |
| Landslides are occurring even on sunny days along the unfinished road construction section. Photo: Trang Trang |
Given the above situation, the authorities need to take measures to urge the construction unit to expedite the completion of the project, so as not to affect people and vehicles passing by.
Trang Trang