Nearly 60% of customers in Nghe An have had power restored.

Tien Hung October 1, 2025 15:58

According to statistics from Nghe An Electricity Company, as of the afternoon of October 1, nearly 630,000 out of 1.1 million customers had their power restored. In the old Vinh City area alone, about 90% of customers had their power restored.

bna_dien1.jpg
Power workers are fixing problems in rural areas. Photo: Phan Thuy

The leader of Nghe An Electricity Company said that as of early afternoon on October 1, the unit had fixed the problem and restored power to nearly 630,000 customers out of nearly 1.1 million customers in Nghe An province. 3 days after storm No. 10, for the 110kV power grid, Nghe An Electricity Company had restored 16/16 transformer stations and 41/41 damaged power lines. For the medium voltage power grid, 4,961 transformer stations and 155 damaged power lines were also restored.

"In the old Vinh City area alone, about 90% of customers have had their power restored," said Mr. Pham Van Nga - Deputy Director of Nghe An Electricity Company, adding that storm No. 10, which landed in Nghe An, caused heavy damage to people's property and severely damaged the power grid. Hundreds of electric poles were broken, many kilometers of power lines were broken and many transformer stations were damaged.

bna_dien2.jpg
As of the afternoon of October 1, about 57% of customers in Nghe An had their power restored. Photo: Phan Thuy

Currently, the entire electricity industry is mobilizing all its strength together with Nghe An Electricity Company to make efforts to restore the power grid system in the entire Nghe An province after storm No. 10. The leaders of the Northern Power Corporation and Nghe An Electricity Company are divided into many working groups to directly stay at the scene, closely monitor, urge and motivate officers and workers to restore the power grid, to restore power as quickly as possible to serve the people.

"More than 1,000 officials and employees of the electricity sector have divided into groups to go to each locality to fix the problem, including many reinforcements from the northern provinces. However, the recovery work is facing many difficulties, because many areas in Nghe An province are still deeply flooded. We expect that by October 6 at the earliest, we can basically fix the problem and restore power to all customers," Mr. Pham Van Nga added.

Some images of Nghe An Electricity Company workers trying to repair the power grid system in the whole province:

z7070211302281_c5674230083adb63bbb169ffc8f01b53.jpg
The entire electricity industry mobilized all its resources together with Nghe An Electricity Company to make efforts to restore the power grid system in the entire province. Photo: Phan Thuy
công nhân điện lực làm việc xuyên đêm để cố gắng cấp điện trở lại phục vụ sản xuất, sinh hoạt. Ảnh PV
Electricity workers work day and night to try to restore power to serve production and people's lives. Photo: Phan Thuy
z7070211284881_c3d197723ede68a30a0f8ad6ccf1322c.jpg
z7070210817635_530aeef8a6226c7c41f2120e79b83d1a.jpg
z7070210794585_c7a817a28f14755f2d0fafd6b015b3bc.jpg
With the utmost efforts of the electricity industry, it is expected that by October 6 at the earliest, the problem can be basically resolved and power can be restored to all customers. Photo: Phan Thuy