How will the two largest hydroelectric plants in Nghe An operate if the reservoir reaches dead water level?

Xuan Hoang - June 14, 2023 10:27
(Baonghean.vn) - It is possible that the reservoirs of Ban Ve and Hua Na Hydropower Plants in Nghe An will reach dead water levels if the hot weather continues as it is now. If that happens, how will the power plants' power plants operate?
Clip: Xuan Hoang

Ban Ve Hydropower Plantwas built on the Nam Non River. The main dam blocking the river is located in Ban Ve, Yen Na commune, Tuong Duong district. The capacity of Ban Ve reservoir is more than 1.8 billion m3,in which the useful capacity from elevation 155m - 200m is 1.3 billion m3water.

However, due to prolonged drought and the need to regulate water production, the water levellakeBan Ve Hydropower Plant has reached an alarming level. At this time (June 14), the water level in the Ban Ve Hydropower Reservoir has dropped very low, only 1 meter higher than the designed dead water level of the Ban Ve Hydropower Plant.

Reporters' observations on June 13 showed that the Ban Ve Hydropower Reservoir is dropping to a deep level. People living in the Ban Ve Reservoir area said that the water level in the reservoir has never been as low as this year. Photo: Xuan Hoang

Currently, the lake water level is only 156.6m, nearly 20m lower than the same period, and the remaining useful capacity is only over 80 million m3.3.

Mr. Hoang Van Ngoc - Deputy Director of Ban Ve Hydropower Company said: When the reservoir reaches the dead water level of 155m, Ban Ve Hydropower Plant can only generate electricity with the discharge flow equal to the return flow. Accordingly,water flowabout the lake now reaches more than 100 m3/second.

According to regulations, only in special cases to meet energy security or provide irrigation water for downstream areas can the reservoir below the dead water level be exploited, but with low power capacity. However, at this time, only one unit is operating, the other unit must be stopped, because if both units are operating at the time of dead water level, it will affect the equipment.

Therefore, in the second half of June and the end of the dry season, if the weather continues to be extremely hot, there will be a shortage of water supply downstream and a risk of not being able to supply enough electricity to the system.

“Early this June, there was a time when the water flow into the lake only reached 35m3/second, the lowest since the plant began operating. However, it has been raining in the upstream area these past few days, so the water supply has improved. However, the weather is unpredictable, if the heat continues, the operation of the power plants will be difficult," Mr. Ngoc worried.

According to Ban Ve Hydropower Company, the current water level of the reservoir is only 1 meter higher than the dead water level, so the operation of generators is affected, reducing capacity.In the picture:Workers of Ban Ve Hydropower Company at the Central Control Room. Photo: Xuan Hoang

At the FactoryHua Na Hydropower Plant(Que Phong) Although the water level in the lake has improved compared to half a month ago, operations are still difficult.

Mr. Doan Van Truong - Deputy Director of Hua Na Hydropower Company said: At the end of May, the water in the reservoir had dropped to the dead water level. At that time, both generators were still operating, but the capacity only reached a minimum of 70/90 MW/generator.

Panoramic view of the downstream area of ​​Ban Ve Hydropower Dam taken from above on June 13. Photo: Xuan Hoang

"These days the water flow on the Chu River flowing into the lake has improved by more than 150 m3/second, so as of this morning, June 14, the water in the lake is 2.9m higher than the dead water level, but much lower than the same period last year. However, the plant still has to operate at minimum capacity at the dead water level to supply power to the grid. However, the generators operating at the dead water level will affect the equipment," said Mr. Truong.

According to the forecast of the North Central Hydrometeorological Station, the severe heat in the North Central region may last for many days to come, affecting the operations of hydropower plants./.

Share your opinion
POWERED BYONECMS- A PRODUCT OFNEKO