Urgent action needed to address landslides during the construction of National Highway 7C.

Van Truong October 28, 2024 13:21

Currently, the construction unit is making efforts to overcome landslides on National Highway 7C (Do Luong) connecting to Ho Chi Minh Highway (Tan Ky), striving to complete and put it into use before November.

Khẩn trương khắc phục sạt lở núi, kè rọ đá bàn giao quốc lộ 7C Trước thực trạng trên, ngay từ đầu tháng 10, ngành chức năng đã chỉ đạo đơn vị thi công, triển khai huy động máy móc và nhân lực tập trung xử lýDự án đường quốc lộ 7C (Đô Lương) nối liền với đường Hồ Chí Minh (Tân Kỳ) đến nay cơ bản đã hoàn thành, tuy nhiên vào các ngày 20/9 xảy ra mưa lớn kéo dài khiến đoạn đường qua xã Kỳ Tân, huyện Tân Kỳ bị sạt lở nghiêm trọng, bùn đất từ 2 bên sườn núi đổ xuống vùi lấp cả lòng đường với khối lư
Urgent measures are being taken to repair landslides and reinforce the embankment with gabion cages for the handover of National Highway 7C section through Ky Tan commune (Tan Ky district). Photo: Van Truong

The National Highway 7C (Do Luong) project, connecting to the Ho Chi Minh Highway (Tan Ky), has been largely completed; however, On September 20th, heavy and prolonged rainfall caused serious landslides on the road through Ky Tan commune, Tan Ky district. Mud and soil from both sides of the mountain slopes poured down, burying the entire road in large quantities. Some landslides also brought down trees and rocks onto the road.

van truong 2
Sections of National Highway 7C are at risk of landslides. Photo: Van Truong

In response to this situation, since the beginning of October, the authorities have directed the construction unit to mobilize machinery and personnel to focus on clearing the landslide. To date, the construction unit has used excavators to remove over 50,000 cubic meters of soil and rocks that had buried the road section through Ky Tan commune, Tan Ky district.3mud and soil. At the same time, measures are being taken to address the "hanging" rock and soil areas on the mountain slopes that are at risk of collapsing.

van truong 3
Urgent measures are being taken to repair landslides along the route. Photo: Van Truong

In the section affected by the landslide in Ky Tan commune, Tan Ky district, the construction unit is also implementing a gabion retaining wall with a length of over 300 meters to prevent soil and rocks from falling from the mountain, and the work has now reached over 70% completion.

A representative from the Nghe An Department of Transport said: The Department has directed the construction unit to urgently accelerate the progress of repairing the landslide, so that this road can be handed over and put into use before November 2024.

van truong 4
The section of road passing through Ky Tan commune, Tan Ky district, has been reinforced with gabion retaining walls over a length of more than 300 meters to prevent soil and rocks from falling down from the mountain.

The road project connecting National Highway 7C (Do Luong) to Ho Chi Minh Highway (Tan Ky) has a total investment of over 739 billion VND. The approximately 23 km long road connects Do Luong and Tan Ky districts and, once completed, will be a crucial project contributing to economic development between the two districts.