'No way back' for Vinh Sub-Urban Project!

DNUM_CFZAEZCABH 12:20

(Baonghean.vn) - "The important issue is that if the progress is delayed, the World Bank will stop providing capital and the damage will not only be done to a few households but will also affect the socio-economic development of Vinh City, Hung Nguyen District and Nghe An Province. Therefore, we have no way to turn back time, all levels and sectors must make efforts for the common goal" - Comrade Huynh Thanh Dien emphasized when inspecting the actual components of the Vinh Urban Development Project.

177 hộ dân ở xã Hưng Đông (TP Vinh) đã tháo dỡ công trình, bàn giao mặt bằng cho thi công dự án đường 72m. Ảnh Nguyên Nguyên
177 households in Hung Dong commune (Vinh city) have dismantled the construction and handed over the site for the construction of the 72m road project. Photo: Nguyen Nguyen
On the morning of April 25, Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee inspected the construction of some components of the Vinh Urban Development Project (also known as the Vinh Sub-Urban Project). Accompanying him were leaders of Vinh City, Hung Nguyen District and some Departments and branches.

The project includes 4 components: Component 1: Improving services and upgrading basic infrastructure. Component 2: Improving environmental sanitation, including upgrading and renovating the North Canal, building a regulating lake; upgrading and renovating the moat around Vinh Citadel, upgrading and renovating Cua Nam Lake. Component 3: Urban roads and bridges. Component 4: Capacity building and technical support. The project implementation cost is 121.5 million USD (World Bank loan), of which domestic counterpart capital is 26.5 million USD.

Up to now, the project to upgrade and renovate the canal and reservoir has basically been completed. Other components are still stuck in the work of compensation, site clearance, and resettlement support. At the end of 2016, when inspecting the site, the World Bank (WB) proposed to speed up the progress, otherwise the funding source would be cut off.

Dự án đường nối đường ven Sông Lam với Ql 46 còn 3 hộ chưa di dời, TP Vinh sẽ tổ chức bảo vệ thi công. Ảng Nguyên Nguyên
The project of connecting the road along Lam River with National Highway 46 still has 3 households that have not been relocated, Vinh City will organize construction protection. Photo: Nguyen Nguyen

On the morning of April 25, the provincial working delegation inspected the construction site of the Hung Tay - Vinh new road project, connecting with the Vinh city bypass at the beginning of the route, connecting with National Highway 1A at the end of the route, building a bridge over the Ke Gai river; clearing some sections of the 72m road project... Most of the inspected sections were still slow in the site clearance stage.

To speed up the construction of projects according to the commitment of the Provincial People's Committee to the World Bank (WB), comrade Huynh Thanh Dien directed Vinh City and Hung Nguyen District to actively participate in mobilizing people to cooperate in completing compensation and handing over the site to contractors.

Đồng chí Huỳnh Thanh Điền kiểm tra thực tế và đối chiếu với quy hoạch dự án đường nối đường ven Sông Lam với QL 46. Ảnh Nguyên Nguyên
Comrade Huynh Thanh Dien inspected the actual situation and compared it with the planning of the road connecting the Lam River road with National Highway 46. Photo: Nguyen Nguyen

Specifically, on the road connecting the Lam River road with National Highway 46, there are still 3 households that have not handed over the land, the Vice Chairman of the Provincial People's Committee requested Vinh City to organize construction protection. As for the sections of the 72m road project, the contractors are requested to clear the land and mobilize maximum means for construction.

Particularly at the Ke Gai River bridge project, in Nam Phuc Long hamlet of Hung Tay commune, Hung Nguyen district, there are still 42 households that do not agree with the compensation and site clearance plan, while Vinh city has completed the bridge abutment, the construction unit has prepared vehicles and bridge beams for construction but is stuck with site clearance.

Đồng chí Huỳnh Thanh Điền kiểm tra thực tế công tác giải tỏa mặt bằng cho dự án đường 72m. Ảnh Nguyên Nguyên
Comrade Huynh Thanh Dien inspects the site clearance work for the 72m road project. Photo: Nguyen Nguyen
Dự án cầu qua sông Kẻ Gai nối TP Vinh với huyện Hưng Nguyên nguy cơ chậm tiến độ khi công tác giải phóng mặt bằng còn vướng mắc phí xóm Nam Phúc Long, xã Hưng Tây, Hưng Nguyên. Ảnh Nguyên Nguyên
The bridge project across Ke Gai River connecting Vinh City with Hung Nguyen District is behind schedule because of problems with site clearance in Nam Phuc Long Hamlet, Hung Tay, Hung Nguyen. Photo: Nguyen Nguyen

Comrade Huynh Thanh Dien assigned the People's Committee of Hung Nguyen district to take more active action, mobilize people's consensus to clear the ground for construction, because when completed, the project will effectively serve the regional connection between Vinh city and Hung Nguyen district in economic development.

“Another important issue is that if the progress is delayed, the World Bank will stop providing capital and the damage will not only be done to a few households but will also affect the overall socio-economic development of Vinh City, Hung Nguyen District and Nghe An Province. Therefore, we have no way to go back in time, all levels and sectors must make efforts for the common goal” - Comrade Huynh Thanh Dien emphasized when assigning specific tasks to the leaders of Vinh City, Hung Nguyen District and departments and sectors.

» Vinh City will enforce land clearance for Vinh Sub-Urban project

Nguyen Nguyen