Hanoi power outage schedule for November 20, 2024
According to Hanoi Power Company, power outages are scheduled in districts and communes across Hanoi on November 20, 2024.
The latest information on power outage schedules for areas in Hanoi on Wednesday, November 20, 2024, is updated from the EVN Hanoi Power Information Portal.
Power outages in Hanoi can have many causes. These include natural disasters such as floods, storms, or maintenance and repair work being carried out by the power grid management unit.

This is the scheduled power outage as planned by the power companies. Depending on weather conditions, the plans of the power companies, etc., the power outage schedule may be adjusted or postponed in some areas.
Hanoi power outage schedule for November 20, 2024
| Unit | Time | Area | Reason | Status |
| Gia Lam Power Company | From 07:00 to 12:00 | Part of Kim Lan commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Gia Lam Power Company | From 09:00 to 11:00 | Long Bien Packaging Trading and Manufacturing Joint Stock Company | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ba Dinh Power Company | From 14:00 to 15:30 | No (low voltage transmission) | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ba Dinh Power Company | From 3:00 PM to 4:30 PM | No (low voltage transmission) | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ba Dinh Power Company | From 16:00 to 17:30 | No (low voltage transmission) | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoan Kiem Power Company | From 08:00 to 09:30 | From number 20 to number 22, from number 18 to number 20, number 18 Ngo Quyen Street, from number 31 to number 35, number 6 to number 32 Trang Tien Street, number 9 to number 27 Trang Tien Street, from number 1 to number 3, number 5 + number 2 Nguyen Khac Can Street, from number 1 to number 15 Trang Tien Alley, from number 2 to number 10 Trang Tien Alley, from number 10 to number 12 + number 8 Hai Ba Trung Street, From number 2 to number 6 Phan Chu Trinh Street. | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoan Kiem Power Company | From 11:00 to 12:30 | Alley 48 Ly Thuong Kiet, number 57, from number 59 to number 61 Ly Thuong Kiet Street; from number 76 to number 82, from number 71 to number 77 Tho Nhuom Street | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoan Kiem Power Company | From 2:30 PM to 3:30 PM | 87 Tran Hung Dao; 48, from number 15 to number 47 Lien Tri; 77+79, from number 78 to number 84 Tran Quoc Toan | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoan Kiem Power Company | From 3:30 PM to 4:30 PM | From number 38 to 60, from number 97 to 155 Hang Bong; from number 2 to 52 Quan Su; from number 1 to 27, from number 2 to 16 Tam Thuong. | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoan Kiem Power Company | From 05:00 to 06:30 | From house number 9 to house number 15 Tran Hung Dao, Apartment complex 16 Tran Hung Dao, from house number 8 to house number 10 Tran Hung Dao | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoan Kiem Power Company | From 06:30 to 08:00 | Apartment complex 15 to 21 Tran Khanh Du Street | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoan Kiem Power Company | From 09:30 to 11:00 | From number 50 to 58 Ly Thuong Kiet; from number 61 to 63, 64+68 Quan Su; 52 Tho Nhuom; Cuban Embassy | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hai Ba Trung Power Company | From 08:00 to 10:00 | Thanh Son Joint Stock Company | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Thanh Xuan Power Company | From 7:00 to 10:00 | Rubber Workers' Housing Complex, Alley 41 Khuong Dinh, Houses 1 to 41 Khuong Dinh, Houses 2 to 56 Khuong Dinh | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Thanh Xuan Power Company | From 10:00 to 14:00 | Alley 460 Khuong Dinh | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoang Mai Power Company | From 09:00 to 12:00 | MBA T1 housing CS CA district Hoang Ma | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ha Dong Power Company | From 06:00 to 13:00 | CT7 Apartment Building - Duong Noi Ward | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ha Dong Power Company | From 05:30 to 12:30 | Buildings CT6A1, CT6A2, CT6B, CT6C Kien Hung | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ba Vi Power Company | From 07:00 to 15:00 | Some customers are from Duong Lam commune (Duong Lam 2), Cam Thuong commune (Thinh Bai, Nam An, Cam Da, Quynh Lam). | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ba Vi Power Company | From 06:30 to 14:30 | Some customers are from Vat Lai commune (Xom Noi hamlet), Tay Dang town (Cao Nhang, Xom Moi, Cau Ba). | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ba Vi Power Company | From 7:30 to 11:30 | A portion of our customers are from Cam Thuong commune (Cam Cao, Nam Coc, Coc Thon). | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Ba Vi Power Company | From 07:15 to 15:15 | The customer is from Tong Bat commune. | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Thach That Power Company | From 00:00 to 05:00 | Viettel S4 CNC Station, Hoa Lac High-Tech Park | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Quoc Oai Power Company | From 07:00 to 15:00 | Part of Phu Cat Commune, Hoa Thach | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Quoc Oai Power Company | From 06:00 to 07:00 | Part of Phu Cat Commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Quoc Oai Power Company | From 3:00 PM to 4:00 PM | Part of Phu Cat Commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Chuong My Power Company | From 07:00 to 15:00 | Trung Hoa Cooperative | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Chuong My Power Company | From 08:00 to 10:00 | JK Vietnam Industrial Joint Stock Company | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Chuong My Power Company | From 11:00 to 12:00 | HDO Trading Joint Stock Company, VAN LANG PHARMACEUTICAL JOINT STOCK COMPANY | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Chuong My Power Company | From 10:00 to 11:00 | Thang Long Traditional Medicine Joint Stock Company | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoai Duc Power Company | From 7:30 to 10:30 | Part of An Khanh commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoai Duc Power Company | From 08:30 to 13:00 | Small-scale industrial worker La Phu | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoai Duc Power Company | From 10:30 to 13:30 | Part of An Khanh commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoai Duc Power Company | From 2:00 PM to 5:00 PM | Part of An Khanh commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Hoai Duc Power Company | From 10:00 to 11:30 | Thang Long T1 Telecommunications Joint Stock Company | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Me Linh Power Company | From 06:30 to 11:30 | Part of Lien Mac commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Me Linh Power Company | From 07:00 to 09:00 | Part of Van Yen commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Me Linh Power Company | From 09:20 to 11:20 | Part of Van Yen commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Me Linh Power Company | From 13:00 to 15:00 | Part of Van Yen commune | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Nam Tu Liem Power Company | From 09:00 to 13:00 | Click to download a portion of the Police Officers' Housing Area - Phuong Canh Ward - Nam Tu Liem District - Hanoi | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Nam Tu Liem Power Company | From 13:00 to 14:30 | Mai Linh Dong Do Joint Stock Company, Address: 499 Luong The Vinh Street, Me Tri Ward, Nam Tu Liem District | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Bac Tu Liem Power Company | From 08:30 to 09:00 | The Institute of Materials Science, Lane 238, Hoang Quoc Viet Street | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Bac Tu Liem Power Company | From 09:00 to 11:00 | Duc Dien Station 5 | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Bac Tu Liem Power Company | From 11:00 to 13:00 | Nguyen Xa 3 Station | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Bac Tu Liem Power Company | From 13:00 to 15:00 | The entire T2 station illuminates Road 32. | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Nam Tu Liem Power Company | From 2:30 PM to 4:30 PM | EMICO Investment and Construction Project Management Board, Address: Me Tri Broadcasting Station Project, Me Tri Ward, Nam Tu Liem District, Hanoi City | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Nam Tu Liem Power Company | From 17:30 to 18:30 | KH Project Management Board for Investment and Construction in the Social Insurance Sector, Address: Zone C, 74.3ha land area, Dai Mo Ward, Nam Tu Liem District, Hanoi City | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Nam Tu Liem Power Company | From 09:00 to 10:00 | Customer: Thien Son Investment and Tourism Joint Stock Company, Address: Lot CT4, Le Duc Tho Street, My Dinh 2 Ward, Nam Tu Liem District | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Nam Tu Liem Power Company | From 08:00 to 09:00 | Customer: Thien Son Investment and Tourism Joint Stock Company, Address: Lot CT4, Le Duc Tho Street, My Dinh 2 Ward, Nam Tu Liem District | Serving the purpose of renovating and upgrading the power grid. | Approved |
| Bac Tu Liem Power Company | From 10:00 to 11:30 | A45 | Serving the purpose of renovating and upgrading the power grid. | Approved |
Above is the power outage schedule for areas in Hanoi on November 20, 2024. Currently, there is no information on power cuts in some other locations. Nghe An Newspaper will regularly update the latest and most accurate information on the power outage schedule in Hanoi for readers to easily follow.