Power outage schedule in Hanoi on December 28, 2024
According to Hanoi Electricity, there is a scheduled power outage in districts in Hanoi on December 28, 2024.
The latest information on power outage schedule in Hanoi areas on Wednesday, December 28, 2024 is updated from the Hanoi Electricity portal.
There can be many reasons for power outages in Hanoi. Factors that can cause power outages include natural disasters, floods, storms, or the management unit carrying out repairs and maintenance of power grid lines.

This is the power outage schedule planned by the power companies. Depending on the weather, the power unit's plans... the power outage schedule can be adjusted and postponed in some places.
Hanoi power outage schedule on December 28, 2024
Electricity | Time | Area | Reason | Status |
Soc Son Power | From 06:30 to 14:30 | Part of Tan Minh commune | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 07:30 to 15:30 | Part of Phu Linh commune | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 06:30 to 14:30 | Part of Tan Minh commune | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 07:30 to 15:30 | Part of Phu Linh commune | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Electricity | From 08:00 to 11:00 | Duc Giang General Hospital customers. | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Electricity | From 09:00 to 10:00 | Part of Vimcom Riverside Customers | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Electricity | From 16:00 to 17:00 | Part of Vimcom Riverside Customers | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Electricity | From 08:00 to 12:00 | Regiment 918 | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Electricity | From 09:00 to 10:00 | Part of Vimcom Riverside Customers | Serving the renovation and upgrading of the power grid | Approved |
Long Bien Electricity | From 16:00 to 17:00 | Part of Vimcom Riverside Customers | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 00:00 to 11:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Postpone |
Ba Dinh Electricity | From 07:00 to 09:00 | Alley 12 Nghia Dung, lane 12/36 Nghia Dung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 09:00 | Lane 15/127 Phuc Xa lane, 141/127 Phuc Xa, group 7, cluster 2 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 09:00 | Lane 15/127 Phuc Xa lane, 141/127 Phuc Xa, group 7, cluster 2 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 09:00 | Alley 12 Nghia Dung, lane 12/36 Nghia Dung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 32 - 64 Phuc Xa, from 45 - 101 Phuc Xa, lane 32 - 34 - 38 - 44 - 52 Phuc Xa, house number 14,16 lane 65 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 32 - 64 Phuc Xa, from 45 - 101 Phuc Xa, lane 32 - 34 - 38 - 44 - 52 Phuc Xa, house number 14,16 lane 65 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 127 - 155 An Xa, from 84 - 100 An Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | Phuc Xa Street Head, Lane 2 An Xa, from 2 - 62 An Xa, Lane 59 - 117 An Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | Lane 77 Nghia Dung, Lane 82 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | The entire lane 133 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | Alley 33 Tap Ap, 17 Hong Ha Street | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | Alley 33, 53 Tan Ap, 52 - 58 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 32 - 64 Phuc Xa, from 45 - 101 Phuc Xa, lane 32 - 34 - 38 - 44 - 52 Phuc Xa, house number 14,16 lane 65 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | No. 23 - 47 Phan Dinh Phung, Alley 25, 45 Phan Dinh Phung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 00:00 to 11:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Postpone |
Ba Dinh Electricity | From 07:00 to 09:00 | Alley 12 Nghia Dung, lane 12/36 Nghia Dung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 09:00 | Alley 12 Nghia Dung, lane 12/36 Nghia Dung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 08:30 to 10:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 127 - 155 An Xa, from 84 - 100 An Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 32 - 64 Phuc Xa, from 45 - 101 Phuc Xa, lane 32 - 34 - 38 - 44 - 52 Phuc Xa, house number 14,16 lane 65 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | Phuc Xa Street Head, Lane 2 An Xa, from 2 - 62 An Xa, Lane 59 - 117 An Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 10:00 to 11:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | The entire lane 133 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 14:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | Lane 77 Nghia Dung, Lane 82 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | No. 23 - 47 Phan Dinh Phung, Alley 25, 45 Phan Dinh Phung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:30 to 15:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | Alley 33, 53 Tan Ap, 52 - 58 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | Alley 33 Tap Ap, 17 Hong Ha Street | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 16:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | Phuc Xa Street Head, Lane 2 An Xa, from 2 - 62 An Xa, Lane 59 - 117 An Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | No. 23 - 47 Phan Dinh Phung, Alley 25, 45 Phan Dinh Phung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 14:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | No. 23 - 47 Phan Dinh Phung, Alley 25, 45 Phan Dinh Phung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 00:00 to 11:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Postpone |
Ba Dinh Electricity | From 07:00 to 09:00 | Lane 15/127 Phuc Xa lane, 141/127 Phuc Xa, group 7, cluster 2 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 09:00 | Lane 15/127 Phuc Xa lane, 141/127 Phuc Xa, group 7, cluster 2 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 08:30 to 10:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | Phuc Xa Street Head, Lane 2 An Xa, from 2 - 62 An Xa, Lane 59 - 117 An Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | Lane 77 Nghia Dung, Lane 82 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | The entire lane 133 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | No. 23 - 47 Phan Dinh Phung, Alley 25, 45 Phan Dinh Phung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 14:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | Alley 33, 53 Tan Ap, 52 - 58 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | Lane 77 Nghia Dung, Lane 82 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 15:00 | No. 23 - 47 Phan Dinh Phung, Alley 25, 45 Phan Dinh Phung | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 08:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 12:00 | No (customer transfers MF to supply low voltage load) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 12:00 to 18:00 | No (customer transfers MF to supply low voltage load) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 00:00 to 11:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Postpone |
Ba Dinh Electricity | From 07:00 to 08:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 10:00 to 11:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:00 to 14:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 00:00 to 11:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Postpone |
Ba Dinh Electricity | From 10:00 to 11:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 13:30 to 15:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 16:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 00:00 to 11:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Postpone |
Ba Dinh Electricity | From 07:00 to 08:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 08:30 to 10:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 127 - 155 An Xa, from 84 - 100 An Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | Alley 33, 53 Tan Ap, 52 - 58 Tan Ap | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 16:00 to 17:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 00:00 to 11:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Postpone |
Ba Dinh Electricity | From 07:00 to 08:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 07:00 to 09:00 | Lane 15/127 Phuc Xa lane, 141/127 Phuc Xa, group 7, cluster 2 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 08:00 to 17:00 | No (customer transfers MF to supply low voltage load) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 08:30 to 10:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 09:00 to 11:00 | From 32 - 64 Phuc Xa, from 45 - 101 Phuc Xa, lane 32 - 34 - 38 - 44 - 52 Phuc Xa, house number 14,16 lane 65 Phuc Xa | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 10:00 to 11:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 17:00 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Ba Dinh Electricity | From 15:00 to 16:30 | No (low voltage transmission) | Serving the renovation and upgrading of the power grid | Approved |
Hai Ba Trung Electricity | From 08:00 to 12:00 | No - customer using generator | Serving the renovation and upgrading of the power grid | Approved |
Dong Da Electricity | From 00:00 to 07:00 | VIETTEL Network Corporation - Branch of Military Industry and Telecommunications Group No. 16, Phao Dai Lang, Lang Thuong Ward, Dong Da District, Hanoi City | Serving the renovation and upgrading of the power grid | Approved |
Dong Da Electricity | From 07:00 to 11:00 | VIETTEL Network Corporation - Branch of Military Industry and Telecommunications Group No. 16, Phao Dai Lang, Lang Thuong Ward, Dong Da District, Hanoi City | Serving the renovation and upgrading of the power grid | Approved |
Dong Da Electricity | From 08:30 to 11:00 | VINAMOTOR Investment Joint Stock Company - 104 Thai Thinh (According to customer CV). | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 05:00 to 10:00 | - From house number 2 to 26, lane 274, Le Trong Tan street - The entire lane 280, lane 312, Le Trong Tan street. - house number 3, lane 316, Le Trong Tan street - From house number 274 to house number 316, Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 11:00 to 16:00 | - The entire alley 164 Le Trong Tan street - From house number 162 to number 174 Le Trong Tan street - The entire alley 198/3 Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 11:00 to 16:00 | - The entire alley 164 Le Trong Tan street - From house number 162 to number 174 Le Trong Tan street - The entire alley 198/3 Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 05:00 to 10:00 | - From house number 2 to 26, lane 274, Le Trong Tan street - The entire lane 280, lane 312, Le Trong Tan street. - house number 3, lane 316, Le Trong Tan street - From house number 274 to house number 316, Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 11:00 to 16:00 | - The entire alley 164 Le Trong Tan street - From house number 162 to number 174 Le Trong Tan street - The entire alley 198/3 Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 05:00 to 10:00 | - From house number 2 to 26, lane 274, Le Trong Tan street - The entire lane 280, lane 312, Le Trong Tan street. - house number 3, lane 316, Le Trong Tan street - From house number 274 to house number 316, Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 08:00 to 11:00 | All T1 Station Airport 2 | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 11:00 to 16:00 | - The entire alley 164 Le Trong Tan street - From house number 162 to number 174 Le Trong Tan street - The entire alley 198/3 Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 05:00 to 10:00 | - From house number 2 to 26, lane 274, Le Trong Tan street - The entire lane 280, lane 312, Le Trong Tan street. - house number 3, lane 316, Le Trong Tan street - From house number 274 to house number 316, Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 08:00 to 10:30 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 10:00 to 12:30 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 11:00 to 16:00 | - The entire alley 164 Le Trong Tan street - From house number 162 to number 174 Le Trong Tan street - The entire alley 198/3 Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 05:00 to 10:00 | - From house number 2 to 26, lane 274, Le Trong Tan street - The entire lane 280, lane 312, Le Trong Tan street. - house number 3, lane 316, Le Trong Tan street - From house number 274 to house number 316, Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 13:30 to 16:30 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 06:30 to 14:30 | Part of Tan Minh commune | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 06:30 to 14:30 | Part of Tan Minh commune | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 08:30 to 16:00 | NCI Clients | Serving the renovation and upgrading of the power grid | Approved |
Thanh Xuan Electricity | From 05:00 to 10:00 | From house number 2 to 26, lane 274, Le Trong Tan street - The entire lane 280, lane 312, Le Trong Tan street. - house number 3, lane 316, Le Trong Tan street - From house number 274 to house number 316, Le Trong Tan street | Serving the renovation and upgrading of the power grid | Approved |
Hoang Mai Electricity | From 08:00 to 15:00 | Ngoc Linh Wood MBA | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 06:30 to 14:30 | Part of Tan Minh commune | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 06:30 to 14:30 | Part of Tan Minh commune | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 08:00 to 10:00 | Customer H26 | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 08:30 to 16:00 | NCI Clients | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 08:30 to 16:00 | NCI Clients | Serving the renovation and upgrading of the power grid | Approved |
Soc Son Power | From 08:30 to 16:00 | NCI Clients | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 14:00 | TT3,5A,6,7,8,10,12, BT8 Van Phu New Urban Area | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 2 - Van Quan Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 12 - Phuc La Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Da Sy Police Station; DP Group 1, Kien Hung Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 10:00 | Part of TDP 7 Quang Trung, 5-storey commercial area, Ngo Thi Nham Street, Quang Trung Ward, Ha Dong Clean Water Pump | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | PCC1 Ha Dong Apartment | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 2 - Van Quan Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Independent Residential Area, Lane 35 Ngo Thi Sy | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 2 - Van Quan Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Da Sy Police Station; DP Group 1, Kien Hung Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 12 - Phuc La Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | PCC1 Ha Dong Apartment | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 14:00 | TT3,5A,6,7,8,10,12, BT8 Van Phu New Urban Area | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 10:00 | Part of TDP 7 Quang Trung, 5-storey commercial area, Ngo Thi Nham Street, Quang Trung Ward, Ha Dong Clean Water Pump | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 10:00 | Apartment 210 Quang Trung | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 13:00 | Service Area 1 Van La | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 14:00 | TT3,5A,6,7,8,10,12, BT8 Van Phu New Urban Area | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 10:00 | Part of TDP 7 Quang Trung, 5-storey commercial area, Ngo Thi Nham Street, Quang Trung Ward, Ha Dong Clean Water Pump | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Independent Residential Area, Lane 35 Ngo Thi Sy | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Lane 93 to 113 Ngo Thi Sy | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 14:00 | TT3,5A,6,7,8,10,12, BT8 Van Phu New Urban Area | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 10:00 | Part of TDP 7 Quang Trung, 5-storey commercial area, Ngo Thi Nham Street, Quang Trung Ward, Ha Dong Clean Water Pump | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | PCC1 Ha Dong Apartment | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 14:00 | TT3,5A,6,7,8,10,12, BT8 Van Phu New Urban Area | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | PCC1 Ha Dong Apartment | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Da Sy Police Station; DP Group 1, Kien Hung Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 12 - Phuc La Ward | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power | From 06:30 to 09:30 | Phu Sa residential group – Vien Son ward. Part of Le Loi street (Son Tay Hospital area), Son Tay Hospital collective – Le Loi ward. Bai Lo Hong Hau area – Phu Thinh ward. | Serving the renovation and upgrading of the power grid | Postpone |
Son Tay Power | From 09:30 to 12:30 | Alley 1, 3 Tran Hung Dao Street, Alley 2 Phan Chu Trinh Street, Chua Moi Collective - Ngo Quyen Ward. | Serving the renovation and upgrading of the power grid | Postpone |
Son Tay Power | From 06:30 to 09:30 | Phu Sa residential group – Vien Son ward. Part of Le Loi street (Son Tay Hospital area), Son Tay Hospital collective – Le Loi ward. Bai Lo Hong Hau area – Phu Thinh ward. | Serving the renovation and upgrading of the power grid | Postpone |
Son Tay Power | From 09:30 to 12:30 | Alley 1, 3 Tran Hung Dao Street, Alley 2 Phan Chu Trinh Street, Chua Moi Collective - Ngo Quyen Ward. | Serving the renovation and upgrading of the power grid | Postpone |
Son Tay Power | From 09:30 to 12:30 | Alley 1, 3 Tran Hung Dao Street, Alley 2 Phan Chu Trinh Street, Chua Moi Collective - Ngo Quyen Ward. | Serving the renovation and upgrading of the power grid | Postpone |
Ha Dong Electricity | From 08:00 to 10:00 | Part of TDP 7 Quang Trung, 5-storey commercial area, Ngo Thi Nham Street, Quang Trung Ward, Ha Dong Clean Water Pump | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power | From 06:30 to 09:30 | Phu Sa residential group – Vien Son ward. Part of Le Loi street (Son Tay Hospital area), Son Tay Hospital collective – Le Loi ward. Bai Lo Hong Hau area – Phu Thinh ward. | Serving the renovation and upgrading of the power grid | Postpone |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:15 to 14:30 | Part of customers in Dong Thai commune (Minh Nghia) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:15 to 14:30 | Part of customers in Dong Thai commune (Minh Nghia) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:15 to 14:30 | Part of customers in Dong Thai commune (Minh Nghia) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 12:00 | Customers in Tan Linh commune (National Park Sub-area BV 3) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 13:00 | Part of customers in Dong Quang and Chu Minh communes, Tay Dang town (Vu Lam substation, Xom Cho, Tay Dang 5, ST Water Supply) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 12:00 | Customers in Tan Linh commune (National Park Sub-area BV 3) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 12:00 | Customers in Van Hoa commune (Muoi 2 substation) | Serving the renovation and upgrading of the power grid | Approved |
Ba Vi Electricity | From 07:00 to 12:00 | Customers in Tan Linh commune (National Park Sub-area BV 3) | Serving the renovation and upgrading of the power grid | Approved |
Thach That Electricity | From 07:00 to 15:00 | Cam Yen Commune, Dai Dong | Serving the renovation and upgrading of the power grid | Approved |
Thach That Electricity | From 07:30 to 10:00 | Binh Phu Commune | Serving the renovation and upgrading of the power grid | Approved |
Thach That Electricity | From 07:00 to 15:00 | Cam Yen Commune, Dai Dong | Serving the renovation and upgrading of the power grid | Approved |
Thach That Electricity | From 07:30 to 10:00 | Binh Phu Commune | Serving the renovation and upgrading of the power grid | Approved |
Thach That Electricity | From 07:30 to 10:00 | Binh Phu Commune | Serving the renovation and upgrading of the power grid | Approved |
Thach That Electricity | From 10:30 to 12:30 | An Khuong Imported Furniture Company Limited; Cuong Hien Limited Liability Company | Serving the renovation and upgrading of the power grid | Approved |
Quoc Oai Electricity | From 07:30 to 12:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Quoc Oai Electricity | From 13:30 to 17:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 07:00 to 15:00 | Thuy Huong Commune | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 08:00 to 11:00 | Hung Nguyen Agricultural Products Company Limited | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 16:00 to 18:00 | Mr. Nguyen Van Hai | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 07:00 to 15:00 | Thuy Huong Commune | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 08:00 to 11:00 | Special Forces | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 14:00 to 16:00 | Infor Paint Joint Stock Company | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 07:00 to 15:00 | Thuy Huong Commune | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 07:00 to 15:00 | Thuy Huong Commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 12:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 11:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 11:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 11:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Phu Xuyen Electricity | From 08:00 to 16:00 | From after the main ATM to the end of the 0.4kV line at Lat Duong 3 substation | Serving the renovation and upgrading of the power grid | Approved |
Phu Xuyen Electricity | From 08:00 to 16:00 | From after the main ATM to the end of the 0.4kV line at Lat Duong 3 substation | Serving the renovation and upgrading of the power grid | Approved |
Phu Xuyen Electricity | From 08:00 to 16:00 | From after the main ATM to the end of the 0.4kV line at Lat Duong 3 substation | Serving the renovation and upgrading of the power grid | Approved |
Son Tay Power | From 06:30 to 09:30 | Phu Sa residential group – Vien Son ward. Part of Le Loi street (Son Tay Hospital area), Son Tay Hospital collective – Le Loi ward. Bai Lo Hong Hau area – Phu Thinh ward. | Serving the renovation and upgrading of the power grid | Postpone |
Hoai Duc Electricity | From 07:00 to 15:00 | Part of Son Dong commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 07:00 to 09:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 09:00 to 11:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 11:00 to 15:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 07:00 to 09:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 07:00 to 09:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 09:00 to 11:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 11:00 to 15:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 07:00 to 09:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 07:00 to 15:00 | Part of Son Dong commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 11:00 to 15:00 | Part of Di Trach commune | Serving the renovation and upgrading of the power grid | Approved |
Hoai Duc Electricity | From 15:00 to 17:00 | No information yet | Serving the renovation and upgrading of the power grid | Approved |
Chuong My Electricity | From 07:00 to 15:00 | Thuy Huong Commune | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:30 to 15:30 | Tu Chau Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Tu Chau Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:30 to 15:30 | Tu Chau Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 05:30 to 07:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Quang Minh Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:30 to 15:30 | Tu Chau Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:00 to 15:00 | Tu Chau Village | Serving the renovation and upgrading of the power grid | Approved |
Thanh Oai Electricity | From 07:30 to 15:30 | Tu Chau Village | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Electricity | From 06:00 to 07:30 | Nghiem Xuyen Commune, Dung Tien | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Electricity | From 07:30 to 15:30 | Nghiem Xuyen Commune, Dung Tien | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Electricity | From 06:00 to 07:30 | Nghiem Xuyen Commune, Dung Tien | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Electricity | From 07:30 to 15:30 | Nghiem Xuyen Commune, Dung Tien | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Electricity | From 06:00 to 07:30 | Nghiem Xuyen Commune, Dung Tien | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Electricity | From 06:00 to 07:30 | Nghiem Xuyen Commune, Dung Tien | Serving the renovation and upgrading of the power grid | Approved |
Thuong Tin Electricity | From 07:30 to 15:30 | Nghiem Xuyen Commune, Dung Tien | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 10:30 | Part of Binh Lang village and Thanh Loi village, Hong Son commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 10:30 | Part of Binh Lang village and Thanh Loi village, Hong Son commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 12:00 | Part of Dong My village, An Tien commune | Serving the renovation and upgrading of the power grid | Approved |
My Duc Electricity | From 07:00 to 15:00 | Part of Doc Tin commune (Doc Tin 1, Doc Tin 2, Doc Tin 5, Doc Tin 6, Doc Tin 7, Doc Tin Pump), Bach Tuyet Pump, Doc Tin Pump and part of Huong Son commune (Huong Son 21 Substation) | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 12:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 11:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 12:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 11:00 | Part of Van Dinh town | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Ung Hoa Power | From 08:00 to 16:00 | Part of Hoa Lam commune | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:00 to 16:00 | Part of Thanh Lam commune, Kim Hoa | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:00 to 16:00 | Part of Thanh Lam commune, Kim Hoa | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:00 to 16:00 | Part of Thanh Lam commune, Kim Hoa | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:00 to 16:00 | Part of Thanh Lam commune, Kim Hoa | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:00 to 16:00 | Part of Thanh Lam commune, Kim Hoa | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 06:30 to 16:30 | Part of Thach Da commune, Tam Dong | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:00 to 16:00 | Part of Thanh Lam commune, Kim Hoa | Serving the renovation and upgrading of the power grid | Approved |
Me Linh Power | From 07:30 to 15:30 | Part of Me Linh, Van Khe and Trang Viet communes | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | PCC1 Ha Dong Apartment | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | PCC1 Ha Dong Apartment | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 10:00 | Part of TDP 7 Quang Trung, 5-storey commercial area, Ngo Thi Nham Street, Quang Trung Ward, Ha Dong Clean Water Pump | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | PCC1 Ha Dong Apartment | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 14:00 | TT3,5A,6,7,8,10,12, BT8 Van Phu New Urban Area | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 2 - Van Quan Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | TSQ CC Building | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | People's Committee of Mo Lao Ward, Mo Lao Secondary School, Area 16B4 Mo Lao | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 12 - Phuc La Ward | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 13:00 | Service Area 1 Van La | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 06:00 to 14:00 | TT3,5A,6,7,8,10,12, BT8 Van Phu New Urban Area | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Lane 93 to 113 Ngo Thi Sy | Serving the renovation and upgrading of the power grid | Approved |
Ha Dong Electricity | From 08:00 to 12:00 | Part of Residential Group 2 - Van Quan Ward | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 05:00 to 10:00 | Lighting Le Duc Tho Street - My Dinh 1 Ward - Nam Tu Liem District - HN | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 07:00 to 12:00 | Click to download CT1 Building, TDP 12 Trung Van, Trung Van Ward, Nam Tu Liem District, Hanoi City | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 07:00 to 17:00 | Ministry of Foreign Affairs - Me Tri Ward - Nam Tu Liem District - Hanoi | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 07:00 to 12:00 | Click to download CT1 Building, TDP 12 Trung Van, Trung Van Ward, Nam Tu Liem District, Hanoi City | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 10:30 to 13:30 | Lighting Le Van Luong Street - Trung Van Ward - Nam Tu Liem District - Hanoi | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 13:00 to 17:00 | Part of Phuong Residential Area, Tay Mo Ward, Nam Tu Liem District, Hanoi City | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 14:00 to 17:00 | Part of Pho To residential group - Tay Mo Ward - Nam Tu Liem District - Hanoi | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 07:00 to 17:00 | Ministry of Foreign Affairs - Me Tri Ward - Nam Tu Liem District - Hanoi | Serving the renovation and upgrading of the power grid | Approved |
Nam Tu Liem Electricity | From 05:00 to 10:00 | Lighting Le Duc Tho Street - My Dinh 1 Ward - Nam Tu Liem District - HN | Serving the renovation and upgrading of the power grid | Approved |
Above is the power outage schedule for areas in Hanoi on December 28, 2024. Currently, there is no information about power outages in some other locations. Nghe An Newspaper will regularly update the latest and most accurate information about the power outage schedule in Hanoi for readers to follow.
Instructions for looking up power outage schedule in Hanoi
There are many ways to look up power outage schedules, including the following:
Follow Hanoi power outage schedule at Nghe An newspaper
Nghe An Newspaper will regularly update the latest and accurate information about power outage schedule in Hanoi for readers' convenience.
Look up power outage schedule on EVN Hanoi website
To look up the power outage schedule in Hanoi today and the coming days, everyone can access the EVN Hanoi website at the linkhttps://evnhanoi.vn/search/power-cut. Select itemDistrict -> Ward -> From date, To dateto capture information

Search on EVN Customer Service application
Everyone downloads the EVN Customer Service application to their phone and registers for an account. Next, select the “Power outage schedule” section to see the exact Hanoi power outage schedule right on your phone.