Nghe An cuts more than 360 billion VND after final settlement appraisal
According to the Department of Finance, in 2024, the province appraised 1,832 projects. The total estimated value submitted for appraisal was VND 16,642 billion; after appraisal, it was reduced by VND 364.43 billion.
Specifically: The total estimated value submitted for appraisal is 16,642 billion VND. After appraisal, it was reduced by 364.4 billion VND (reaching 2.19%). The whole province implemented 1,261 bidding packages; the total approved bidding package value was 4,894.2 billion VND; the value reduced through bidding: 63.08 billion VND (reaching 1.29%).
The total number of completed projects (works) submitted for appraisal and final settlement approval is 2,424 projects. The total investment cost completed for final settlement proposal is 7,388.78 billion VND; the investment cost decreased after appraisal by 126.96 billion VND (reaching 1.72%).

Meanwhile, as of November 18, 2024, the State Treasury has controlled the expenditure of VND 43,947 billion. The Treasury has also refused to pay, requesting to supplement and complete 97,250 records with an amount of VND 16,249 billion (of which: investment expenditure is VND 8,926 billion of 9,039 records; regular expenditure is VND 7,368 billion of 88,211 records).
Also in the year, violations were discovered and recommendations were made to recover violations of norms, standards and regimes with the amount of 437 million VND.
Right from the beginning of the year, the Provincial People's Committee has publicly announced the decision to assign the State budget revenue and expenditure estimates to all administrative management units and public service units at the provincial level; the Department of Finance has developed and publicly announced the process of auditing the settlement of completed ISO: 9001-2008 projects, which is publicly posted on the Website: Sotaichinh.nghean.gov.vn.