The Song Lam Cement Plant project is 80% complete.

January 18, 2016 12:11

(Baonghean.vn) - These days, the construction site of the Song Lam Cement Plant (Do Luong district) is bustling with activity as workers accelerate the progress of all items to bring it into operation soon. The plant is expected to start operating in September 2016. Approximately 1,300 workers, divided into various construction teams, are always present on the site.

Thap
The nine-story heat exchange tower is the most important component of the cement plant, and machinery is currently being mobilized for assembly and construction. The tower is used for heating and drying raw materials and producing clinker. Currently, the plant has completed the construction of the fourth floor.
2
This is an electrostatic dust filter system, filtering out up to 99% of dust to prevent environmental impact during production. According to the factory's General Director, Mr. Bui Quoc Quyen, 80% of the work is currently complete.
3
The Clinker Silo section comprises large storage facilities. Each silo holds up to 60,000 tons of clinker. The clinker is stored for 10 consecutive days before being transported to Nghi Thiet port for cement production.
r
Every day, up to 1,300 workers from various foreign contractors are divided into teams working both above ground and underground. In the photo: Construction of a compressed air station and limestone storage facility.
Khu chế tác cơ khí
The factory construction site is divided into four areas with different main activities, such as the manufacturing area, the mechanical area, and the main assembly and construction area. The image shows...Mechanical manufacturing area.
Khu tái định cư phục vụ cho giải phóng mặt bằng đường N5, D4 để vận chuyển xi măng xuống Nghi Thiết cũng  đã được thi công
The resettlement area serving the land clearance for the N5 and D4 roads to transport cement to Nghi Thiet is also being constructed at an accelerated pace. The Song Lam Cement Plant project is being built with a capacity of 18,000 tons/day in Bai Son commune, Do Luong district. Phase 1 (2015-2017) involved the investment in two production lines with a total capacity of 12,000 tons of clinker/day (equivalent to 4 million tons of cement/year), creating jobs for 2,000 workers. Phase 2 (2017-2020) involved the third production line with a capacity of 6,000 tons of clinker/day.

Chau Lan