Many key projects in Vinh City are delayed due to land clearance issues.
(Baonghean.vn) - Key projects in Vinh City are behind schedule because the land has not yet been handed over to the construction units. This was the topic discussed at a meeting of the Vinh City Party Committee on the morning of November 22nd. Comrade Vo Viet Thanh - Member of the Standing Committee of the Provincial Party Committee, Secretary of the Vinh City Party Committee - chaired the meeting.
Despite numerous efforts, six key projects in Vinh City are currently behind schedule due to obstacles in land clearance.
Approval of 72 billion VND for land clearance for Vinh Ancient Citadel moat.
![]() |
| The project to renovate the moat of Vinh Ancient Citadel is still facing obstacles in land clearance. (Photo: Archival image) |
Regarding the project to build a road connecting National Highway 46 with the Lam River embankment road, only 36% of the construction has been completed. Currently, the project is facing land acquisition issues in Hung Hoa, Nghi An, and Nghi Duc communes, with a total length of 1,400m.
At the reservoir construction project, the construction volume has reached 38%, due to obstacles on over 0.85 hectares in Hung Loc and Hung Hoa communes.
The project to upgrade and renovate the moat surrounding Vinh ancient citadel has reached 20% completion, but is still facing obstacles in Cua Nam and Doi Cung wards, where 249 households have not yet demolished their properties and handed them over to the construction unit.
The Hung Tay – Vinh road construction project has reached 30% completion, but is still facing obstacles in the communes and wards of Quan Bau, Hung Dong, and Hung Tay (Hung Nguyen district), with a total length of nearly 2000m… In these projects, some households have not accepted the compensation rates for land clearance, have not agreed to the resettlement plan, some plots have not had their land use origins confirmed, and many households have questions about compensation for assets on the land, land prices at the new location, etc.
![]() |
| A panoramic view of the meeting. |
At the meeting, the Party Secretary of the City Committee requested that the units implement stronger and more decisive solutions. Simultaneously, a mobilization team should be established to regularly monitor the situation at the grassroots level, assigning specific responsibilities to the supporting staff to focus on resolving issues related to documentation and procedures. The deadline for completing land clearance for all contract packages is December 30, 2016, to hand over clean land to the construction units.
Vo Huyen