(Baonghean.vn)- In recent days, Dong Hoi (Quynh Lap) has had heavy rain, flooding the construction site of Hoa Sen factory of Hoa Sen Group. However, the investor and contractor are still sticking to the construction site, speeding up the project's progress.

Nước mưa ngập nhà xưởng số 1 đang xây dựng
Hoa Sen Nghe An Factory in Dong Hoi Industrial Park, Quynh Lap Commune, Hoang Mai Town is a new project invested and built by Hoa Sen Nghe An One Member Co., Ltd. on an area of ​​35 hectares. In recent days, heavy rain has causedConstruction area of ​​factory No. 1 was flooded.
Khu nhà xưởng số 2 đã thi công gần xong
Mr. Nguyen Cong Tri, Head of Construction Management Board of Hoa Sen Group said: The factory has 4 workshops. After 5 months of construction, currently, workshop No. 2 is nearly completed, workshop No. 1 is under installation. In addition, there is also a wastewater treatment area, boiler area, and power station area.In photo: Factory area No. 2 has been basically completed.
Nước ngập sau khu nhà xưởng số 2
Flooding at factory area number 2.
Nhà thầu đang huy động máy xúc san gạt để tiêu thoát nước
Hoa Sen Nghe An factory in Quynh Lap has invested in a cold rolling line with a designed capacity of 1 million tons/year; 1 color-coated steel production line with a designed capacity of 120,000 tons/year; 2 galvanized steel production lines with a total designed capacity of 500,000 tons/year; 1 acid recycling line with a designed capacity of 3,000 liters/hour; 1 rust removal line with a designed capacity of 700,000 tons/year; 1 edge cutting and re-rolling line with a designed capacity of 120,000 tons/year; 2 CNC steel roller grinding machines with a designed capacity of 24 rollers/day. In the photo:The contractor is mobilizing excavators to drain water at the construction site.
Nhà thầu lắp đặt vận chuyển thiết bị đẩy nhanh tiến độ thi công
The total investment of the project is 5,000 billion VND, expected to be operational by March 2016, producing products. In the photo: Contractors install equipment, speeding up the construction progress of the power station.
 Hệ thống mương phía trước nhà máy để dẫn nước từ trên núi đi ra biển
This is the second factory of Hoa Sen Group in Nghe An. During the project implementation, the Provincial Party Committee, Provincial People's Committee, Southeast Economic Zone Management Board, Hoang Mai town and related sectors have created the best conditions for the factory to come into operation. In the photo:The ditch system in front of the factory to lead water from the mountains to the sea.