Strive to complete route N5 before June 30, 2017
(Baonghean.vn) - That was the direction of comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee during the inspection of the actual progress of the N5 route and working with Song Lam Cement Joint Stock Company on some problems related to site clearance for affected households on the morning of April 5.
Also attending the meeting were representatives of the Provincial People's Committee Office, relevant departments and branches: Transport, Finance, Planning and Investment, Natural Resources & Environment; leaders of localities: Nghi Loc, Do Luong and Song Lam Cement Joint Stock Company. |
Route N5 connecting the Southeast Economic Zone to Hoa Son, Do Luong district, is 29.1km long and has been approved as two specific projects with a total capital of more than VND1,265 billion.
Currently, the total allocated capital is more than 736 billion VND, reaching 58%; the remaining capital shortage is 528.5 billion VND.
![]() |
Comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee and the working delegation inspected route N5. Photo: Thu Huyen |
Up to now, after nearly 1 year of construction, the main route passing through 2 districts, Nghi Loc and Do Luong, the site has been handed over to the construction unit. However, there is still a household in Dai Son commune, Do Luong district who is deliberately obstructing and not allowing the contractor to construct the cement reinforcement layer with the reason that the roller will crack the house.
As for the crossroads and sewer yards that intersect with residential roads, serving transportation and production for Song Lam Cement Factory, there are still 7 communes: Nghi Phuong, Nghi My, Nghi Lam, Nghi Kieu, Nghi Loc district and Tan Son, Thinh Son, Hoa Son communes that have not yet handed over the site to the contractor, so the construction progress of the project is behind schedule.
![]() |
Workers are paving the road with asphalt concrete. Photo: Thu Huyen |
![]() |
Crushed stone mix for cement reinforcement on N5 route. Photo: Thu Huyen |
Regarding construction volume, by the end of March 2017, roadbed, bridge, culvert, crushed stone foundation has reached 100%, cement reinforcement has reached 93%, and asphalt layer 1 has reached nearly 40% of the total project length.
![]() |
Comrade Huynh Thanh Dien chaired the working session with departments, branches, Do Luong district and Song Lam Cement Joint Stock Company. Photo: Thu Huyen |
Through on-site inspection, Mr. Huynh Thanh Dien, Vice Chairman of the Provincial People's Committee, requested: The Department of Transport to direct contractors to arrange 7 construction teams on the route, striving to complete the first layer of asphalt before April 30, and complete the entire N5 project before June 30, 2017.
For Nghi Loc and Do Luong districts, focus on completing compensation records for level crossings and sewer yards to hand over the site to the construction unit before April 10, 2017; At the same time, prepare a plan to protect the construction of the section passing through households in Dai Son commune, Do Luong district in a thorough and strict manner, ensuring the proposed progress.
Thu Huyen