Vice Chairman of the Provincial People's Committee Hoang Phu Hien inspects the progress of social housing and worker accommodation projects.

Thanh Duy May 27, 2026 13:34

On the morning of May 27th, Mr. Hoang Phu Hien, Member of the Provincial Party Committee and Vice Chairman of the Nghe An Provincial People's Committee, conducted a field inspection and held a working session with local authorities and businesses regarding the implementation of several social housing and worker accommodation projects in the province, aiming to resolve difficulties and accelerate project progress.

bna_img_3265.jpg
The project is a housing complex for low-income earners and civil servants/workers in Vinh Loc ward. Photo: Thanh Duy

In Truong Vinh ward, Vice Chairman of the Provincial People's Committee Hoang Phu Hien inspected the Dong Dau Urban Area Project combined with low-income housing, comprising 308 apartments; the Vinh Tan Ward Housing Project, comprising 44 apartments; and the Vinh Tan Ward Urban and Commercial Service Area Project with 697 apartments.

In Vinh Loc ward, the Vice Chairman of the Provincial People's Committee inspected the Low-Income Housing Project for officials and employees with 89 apartments; the Urban Area Project in Hung Loc commune, which includes a social housing apartment building with 612 apartments; and the My Thuong Housing Project with 204 apartments.

bna_img_3361.jpg
Vice Chairman of the Provincial People's Committee Hoang Phu Hien inspects the progress of the housing project for low-income earners and officials/employees in Vinh Loc ward. Photo: Thanh Duy.

Meanwhile, in Vinh Hung ward, the working group inspected the North Nghi Kim Urban Area Project and the Nghi Kim Central Housing Area, which comprises 540 apartments.

During a site inspection of social housing projects in the province, Mr. Hoang Phu Hien, Vice Chairman of the People's Committee of Nghe An province, emphasized that developing social housing is an important political task, a specific target assigned by the Central Government to each locality, and has been included in the annual socio-economic development targets. According to the plan, Nghe An must complete approximately 2,129 social housing units in 2026.

bna_img_3491.jpg
Vice Chairman of the Provincial People's Committee Hoang Phu Hien listens to a report on the progress of the construction of a 20-story social housing apartment building with 612 units at the Hung Loc Commune Urban Area Project (now Vinh Loc Ward). Photo: Thanh Duy

Based on that, the Vice Chairman of the Provincial People's Committee requested investors to focus intensely and mobilize maximum resources to accelerate construction progress, ensuring the completion of projects as committed to the province in 2026.

The comrade affirmed that the tasks under the responsibility of the province, departments, and localities have basically been addressed and resolved promptly to create favorable conditions for businesses to implement projects.

bna_img_3518.jpg
Construction of social housing apartments at the Hung Loc Commune Urban Area Project, now Vinh Loc Ward. Photo: Thanh Duy

However, upon inspection, it was found that some projects are still behind schedule, or have not even started construction, such as the Dong Dau Urban Area Project combined with low-income housing in Truong Vinh ward; the Urban and Commercial Service Area Project in Vinh Tan ward (now Truong Vinh ward)...

In response to this situation, Comrade Hoang Phu Hien instructed the Department of Construction to take the lead in organizing meetings with each investor, reviewing and revising detailed monthly schedules to serve as a basis for monitoring, inspection, and implementation guidance.

For projects that are behind schedule or fail to fulfill their commitments to the province, if they still do not proceed after penalties have been imposed, the province will resolutely revoke their licenses to avoid wasting time and land resources.

bna_img_3212.jpg
The Dong Dau Urban Area project, which includes 308 social housing units for low-income earners, was committed to completion this year but construction has not yet begun. Photo: Thanh Duy

The Vice Chairman of the Provincial People's Committee also affirmed that the province will continue to support and create the best possible conditions for businesses within its scope of responsibility; difficulties and obstacles related to the locality or departments will be addressed. However, businesses must also proactively participate and closely coordinate with the government in land clearance, completing procedures, and organizing project construction.

During the on-site inspection, Comrade Hoang Phu Hien also specifically emphasized that the quality of social housing projects must be prioritized. Projects need to ensure wide, well-ventilated corridors; focus on waterproofing and odor control solutions; and fully meet essential living conditions to effectively serve the real housing needs of residents and workers.

bna_img_3555.jpg
Vice Chairman of the Provincial People's Committee Hoang Phu Hien inspects the North Nghi Kim Urban Area Project and the Nghi Kim Central Housing Area. Photo: Thanh Duy.

Comrade Hoang Phu Hien emphasized that the current demand for social housing is very high, and the market still has much room for development. Therefore, businesses need to be determined to overcome difficulties in capital, materials, and labor to focus on accelerating progress, completing projects early, and bringing products to the market, thereby meeting the housing needs of the people while improving the investment, production, and business efficiency of the enterprises.

bna_img_3657.jpg
Vice Chairman of the Provincial People's Committee Hoang Phu Hien inspects worker accommodation projects at VSIP Industrial Park in Hung Nguyen commune. Photo: Thanh Duy

Also on the morning of May 27th, at the VSIP Industrial Park in Hung Nguyen commune, Vice Chairman of the Provincial People's Committee Hoang Phu Hien inspected the progress of worker housing projects including: the Luxshare - ICT Nghe An worker housing project with 253 units; the Luxshare - ICT Nghe An 2 worker housing project with 1,582 units; and the Everwin Precision (Vietnam) worker housing project with 989 units.

bna_img_3588.jpg
Vice Chairman of the Provincial People's Committee Hoang Phu Hien inspects the progress of the construction of workers' accommodation at Luxshare - ICT Company. Photo: Thanh Duy.

During the on-site inspection, the Vice Chairman of the Provincial People's Committee acknowledged that the investors and contractors had focused on implementing the project and adhering to the set schedule; he also requested them to continue accelerating construction while ensuring absolute labor safety and construction safety throughout the entire process.

bna_img_3629.jpg
The construction project of worker accommodation by Everwin Precision (Vietnam) Company at VSIP Industrial Park, Hung Nguyen commune. Photo: Thanh Duy

Comrade Hoang Phu Hien also noted that workers' accommodation areas need to be invested in comprehensively, ensuring essential living conditions, spaciousness, and a good living environment for workers; in particular, attention should be paid to arranging community areas, sports facilities, and recreational areas so that workers can rest and regenerate their energy after work.