Vice Chairman of the Provincial People's Committee: 'Hung Nguyen must direct more drastically in site clearance'

DNUM_CFZBAZCABH 11:42

(Baonghean.vn) - On the morning of October 25, comrade Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee, after inspecting the progress of the WB project, requested Hung Nguyen district to direct more drastic measures in site clearance so that the project can be completed on schedule.

The Vice Chairman of the Provincial People's Committee requested Hung Nguyen to take stronger action, fulfill its commitments to the province and the people, and create high consensus to complete the construction of the 72m road from Vinh to Hung Tay.

Đồng chí Huỳnh Thanh Điền đi kiểm tra đường 35m đoạn đi qua Nghi Đức, thành phố Vinh
Comrade Huynh Thanh Dien inspected the 35m road section passing through Nghi Duc, Vinh city. Photo: Tran Chau

In Vinh city, the delegation inspected the progress of the 35m road project connecting Hung Hoa with National Highway 46, which has basically completed site clearance, inspected the construction progress of the regulating lake in Hung Hoa commune, Quan Bau intersection, the 72m road to Hung Nguyen, the overpasses on the route, Nguyen Van Be street and especially the congested area in Hung Nguyen.

The project of regulating lake will complete the site clearance in November 2017. Regarding the construction progress, according to the city's report, it is estimated to be 75%, while the implementation time is about 82% including the time for construction preparation. The construction progress is slow due to the recent rainy and flood weather.

The project to upgrade and renovate the canal around Vinh Citadel (the contractor is the Joint Venture of Hoa Hiep Company Limited and Thinh Hung Company) is scheduled to be completed on April 30, 2017. However, in Cua Nam ward, there are still 5 households that have not been cleared. At the site after the flood, there are 95 officers and workers participating in the construction with 15 excavators divided into many construction teams. The project is expected to complete site clearance in November 2017. The construction volume is estimated to reach 60%, while the implementation time is about 80% including the time for construction preparation.

Currently dredging 161,000/288,760 m of trenches3(55%); Construction of rubble wall reached 70%; Sluice gate: 02/03 sets; Construction of B400 ditch on sidewalk and sub-items, construction of surrounding culvert.

Đường 72m Vinh Hưng Tây đoạn đi qua Hưng Nguyên đang vướng mắc giải phóng mặt bằng. Ảnh: Trân Châu
The 72m Vinh - Hung Tay road section passing through Hung Nguyen is facing problems with site clearance. Photo: Tran Chau

Vinh - Hung Tay road in Vac hamlet has 4 households that have been cleared but are still obstructing construction. In Nam Phuc Long hamlet, 21/63 households have not received compensation; the reason is that they require the completion of Nguyen Van Be road before receiving compensation.

The overpass section on the 72m road, constructed by the Joint Venture of Thuan An Construction and Trade Development Joint Stock Company and Truong Son Construction Investment Joint Stock Company, has drilled bored piles: 2,389/3,198 m (75%); concrete bridge pier 477m3, progress is slow due to floods.

At the scene, during the inspection, comrade Huynh Thanh Dien praised Vinh city and contractors for actively constructing and ensuring progress after the flood, but reminded Hung Nguyen district to slow down the construction of Nguyen Van Be street and the area requiring site clearance in the district, affecting the overall progress.

Phó Chủ tịch Huỳnh Thanh Điền yêu cầu huyện Hưng Nguyên
Vice Chairman Huynh Thanh Dien asked Hung Nguyen district to be more active in site clearance. Photo: CL

Comrade Huynh Thanh Dien affirmed that the Vinh Sub-urban project is not only a particularly important project of the province and Nghe An, but also opens up the prospect of attracting other projects if the province and the city manage well. He requested Vinh city, especially Hung Nguyen district, to resolutely direct the completion of Nguyen Van Be road and resolve all obstacles in the area, creating conditions for the project to be completed in many items by the Lunar New Year 2018.

Up to now, the total disbursed ODA capital of the Vinh City Sub-project is 56.75 million USD, reaching 67% of the total existing project capital (84.66 million USD); the project implementation time is 86%.

Kiểm tra tại hiện trường dự án
Checking the site of the ancient citadel moat project. Photo: Tran Chau

» Nghe An: Extending 12 slow-moving projects