Promptly resolve obstacles for the Vinh urban sub-project.

• April 4, 2017 17:54

(Baonghean.vn) - "The Vinh urban sub-project is still progressing very slowly and needs more decisive action because time is very limited" - that is the directive fromVice Chairman of the Provincial People's CommitteeHuynh Thanh Dien at the project progress inspection on the afternoon of April 4th.

Đồng chí Huỳnh Thanh Điền, Phó Chủ tịch UBND tỉnh
Comrade Huynh Thanh Dien, Vice Chairman of the Provincial People's Committee, inspects the regulating reservoir project in Hung Loc commune. Photo by Tran Chau.

Comrade Huynh Thanh Dien and the delegation inspected the progress of projects including: the road connecting National Highway 46 with the Lam River embankment road, the regulating lake, the 72m Vinh - Hung Nguyen road, the moat of the ancient citadel, etc.

Many projects still face numerous obstacles in land clearance that are difficult to resolve.

The National Highway 46 project, connecting to the Lam River embankment road, was contracted on January 28, 2016, and was scheduled for completion by June 11, 2017. However, only an average of 45% of the construction work has been completed, while 65% of the construction time has already passed. Progress is severely delayed due to the inability to secure the necessary land for construction.

The section passing through Nghi Duc and Nghi An communes is approximately 1.2 km long, affecting 106 households (74 in Nghi Duc and 32 in Nghi An) and one military unit. Most households (102 households: 72 in Nghi Duc and 30 in Nghi An) have had their compensation and resettlement plans approved, but only 27 out of 74 households in Nghi Duc and 7 out of 27 households in Nghi An have accepted the compensation money, while the remaining 67 households have not yet accepted the compensation plan. The resettlement areas are not yet completed.

The reservoir project still has some households that have not yet been relocated.

The Hung Tay-Vinh connecting road project, contracted on January 28, 2016, was supposed to be completed by June 11, 2017. Construction volume has only reached an average of 43%, while 65% of the construction time has already passed. Progress is seriously delayed due to the inability to hand over the land, and access roads to the construction site are still missing in some sections. Two attempts have been made to construct only 1.5 km of access road through Hung Tay and Hung Nguyen leading to the construction site.

This project currently has 5 businesses, including Auto No. 5, Phu Nguyen Hai Company, Kim Lien Company Limited, Savings Fund No. 6 of the Industrial and Commercial Bank, and Hung Son Company (Hoa Ly guesthouse), that have not yet dismantled their premises.

a
The inspection team checks the progress of the 72-meter road project section through Hung Dong. Photo: Tran Chau

The section passing through Hung Tay (Hung Nguyen) goes through two hamlets (Vac and Nam Phuc Long), requiring land acquisition from nearly 120 households. This section is over 600m long; however, only 8 out of 76 households have accepted compensation, while the others have not yet agreed. The on-site resettlement areas are not yet completed. The People's Committee of Hung Nguyen district had planned to complete all compensation and land clearance work by March 2017, but it remains unfinished to date.

The ancient moat project, contracted on January 27, 2016, was supposed to be completed by August 10, 2017; however, only 30% of the work has been completed while 55% of the construction time has already passed.

During the meeting, the Vinh Urban Sub-project Management Board reported that the remaining time for the Vinh Sub-project is very limited. To ensure commitments to the Government and the World Bank, the remaining time in 2017 requires tremendous effort from the entire political system of the city.

a
WB supervisors were also present at the site to conduct the inspection.

At the construction sites, Comrade Huynh Thanh Dien met with the investors, Project Management Board, and contractors to directly resolve any obstacles. He instructed Vinh City and the project investors to be more decisive and take advantage of favorable weather conditions to complete the work volume and ensure the project's progress. He also requested Vinh City and Hung Nguyen District to mobilize all available resources to stay on-site, supervise, and direct the project, setting a deadline of April 10th for resolving several outstanding issues.

a
Construction work is underway on the moat of Vinh Ancient Citadel, specifically the section passing through Doi Cung ward. Photo: Tran Chau