Focus on bringing the Than Vu Tunnel project to completion and operational by June 2027.

Nguyen Toan July 14, 2026 16:33

The project to complete the Than Vu tunnel on the Dien Chau – Bai Vot section of the expressway is being implemented under the public investment model with a total investment of approximately 2,155 billion VND. According to the plan, the project will be basically completed in 2026 and put into operation from mid-2027.

Currently, on the construction site, the investor and contractors are focusing on overcoming difficulties to keep up with the project timeline.

Nguyễn Toàn
The Than Vu tunnel project is currently under intensive construction with the aim of putting it into operation in June 2027. Photo: Nguyen Toan

North of the Than Vu tunnel, two main projects, the Xuan Duong 1 Bridge and the left branch of the Xuan Duong 2 Bridge, are currently under intensive construction. The main contractor, Construction Corporation No. 8 (Cienco 8), is deploying personnel and equipment to construct the 21-span Xuan Duong 2 Bridge and the 6-span Xuan Duong 1 Bridge. The subcontractor, Truong Son Construction Investment Joint Stock Company, is constructing the 15 spans of the Xuan Duong 1 Bridge. Currently, the piling work is complete, and contractors are deploying forces to construct the piers, pier sections, and cap beams, aiming for the full girder launching in 2026.

Cầu Xuân Dương 2 nhánh trái với 21 nhịp đang được Cienco 8 thi công. Ảnh Nguyễn Toàn
The left branch of the Xuan Duong 2 bridge, with 21 spans, is currently under construction by Cienco 8. Photo: Nguyen Toan.

Mr. Truong Cong Trung, Deputy General Director of Cienco 8, stated that as of July 10, 2026, Cienco 8 had completed 110 billion VND out of over 300 billion VND worth of the contract, equivalent to approximately 36% of the total output: “We are currently deploying 9 construction teams; 6 teams are deployed for the nearly 1km-long Xuan Duong 2 bridge and 3 teams for the Xuan Duong 1 bridge. The total number of engineers and workers involved is 125. In the coming period, during peak construction periods, we will plan to supplement personnel promptly to meet the set deadlines.”

Mố cầu và xã mũ các trụ cầu Xuân Dương 2 phía tiếp giáp hầm Thần Vũ đang được Cienco 8 thi công. Ảnh Nguyễn Toàn
The bridge abutments and pier caps of the Xuan Duong 2 bridge on the side adjacent to the Than Vu tunnel are currently being constructed by Cienco 8. Photo: Nguyen Toan

The consulting and supervision firm for the Xuan Duong 1 and Xuan Duong 2 bridges and the completion of the Than Vu tunnel is the Bridge and Tunnel Design Consulting Joint Stock Company. Mr. Nguyen Trung Chinh, the chief consulting and supervision firm, assessed: Construction conditions on the northern side of the Than Vu tunnel are difficult, with hilly terrain making access challenging even from the initial site preparation phase. There are also limited solutions to shorten the construction time during the girder launching phase. Furthermore, the current labor supply on the market is very scarce, requiring contractors to make strenuous efforts to mobilize manpower, especially workers for constructing the main body and cap of the tall piers. Therefore, the consulting and supervision firm is deploying sufficient personnel to work alongside the contractors day and night to closely monitor progress, update the contractors, and report regularly to the investor.

Các nhà thầu gặp khó khăn về công nhân thi công trụ cao và xã mũ. Ảnh Nguyễn Toàn
Contractors are facing difficulties in finding workers to construct the tall pillars and cap beams. Photo: Nguyen Toan
Trụ T55, T56 cầu Thần Vũ đoạn qua xóm 5 Nghi Đồng, xã Thần Lĩnh đang bị cản trở thi công. Ảnh Nguyễn Toàn
Pillars T55 and T56 of the Than Vu bridge section passing through Hamlet 5, Nghi Dong, Than Linh commune. Photo: Nguyen Toan

South of the Than Vu tunnel, contractors Hoa Hiep Co., Ltd., Bridge Construction Corporation No. 75, and Bien Dong Consulting and Construction Joint Stock Company are focusing on constructing the Than Vu bridge with 50 spans. At the construction site of piers T55 and T56 of the Than Vu bridge, located in Hamlet 5, Nghi Dong, Than Linh commune, one household is continuously obstructing construction despite the land clearance work for the project being completed in phase 1.

Directing operations at the construction site, Mr. Nguyen Tien Suu - Deputy Director of Bien Dong Consulting and Construction Joint Stock Company - shared: “Bien Dong Consulting and Construction Joint Stock Company is constructing 16 spans of the Than Vu bridge, from pier T47 to abutment A1. Construction on piers T55 and T56 had to be halted in April and May. After the Than Linh commune authorities intervened, the family facilitated the construction of the pier base and body. However, the access road for transporting materials for girder installation is still being blocked. If this issue is not resolved in the near future, the company will be very vulnerable in ensuring the project's progress.”

Những phiến dầm đầu tiên ở phía nam cầu Thần Vũ. Ảnh Nguyễn Toàn
The first girders are laid on the southern side of Than Vu Bridge. Photo: Nguyen Toan

The Than Vu Tunnel project has a total length of 8.2 km, including 3 bridges: Xuan Duong 1, Xuan Duong 2, and Than Vu, with a length of over 4.1 km; completion of the tunnel's interior surface for nearly 1.1 km; the beginning and end roads for 2.88 km; and adjustments to the Nghi Phuong interchange to connect to the expressway in the final phase. To date, the contractors have achieved a cumulative output of over 381 billion VND, equivalent to 29.37% of the contract value.

Nhà thầu Cty TNHH đã lao dầm được 3 nhịp cầu Thần Vũ. Ảnh Nguyễn Toàn
The contractor, Hoa Hiep Co., Ltd., has launched girders for 3 out of 29 spans of the Than Vu bridge. Photo: Nguyen Toan

Mr. Ngo Trong Nghia - Director of the Than Vu Tunnel Completion Project, Railway Project Management Board, Ministry of Construction, assessed that, despite facing many difficulties from the beginning of the project regarding terrain, escalating fuel and material prices, labor shortages, and some locations where local residents obstructed construction, the five contractors, including Hoa Hiep Co., Ltd., Cienco 8, Bridge Construction Corporation No. 75, and Bien Dong Consulting and Construction Joint Stock Company, have successfully completed the project.,Truong Son Construction Investment Joint Stock Company has made efforts to mobilize machinery and equipment and implemented remedial measures, especially regarding human resources. As a result, the critical path progress is currently under control. According to the requirements of the Ministry of Construction, the project will be essentially completed before Tet (Lunar New Year) and put into operation in June 2027..

Nhánh trái cầu Thần Vũ bên nhánh phải đang khai thác. Ảnh Nguyễn Toàn
The left branch of the Than Vu Bridge is being completed. Photo: Nguyen Toan
Hầm Thần Vũ nhánh phải đã khai thác và nhánh trái đang được hoàn thiện. Ảnh Nguyễn Toàn
Than Vu Tunnel on the North-South Expressway. Photo: Nguyen Toan

Representatives from the Railway Project Management Board also requested the People's Committee of Nghe An province to continue taking measures to control construction material businesses; to prevent hoarding and price gouging; and to ensure the supply of construction materials for key projects in the area. They also requested Than Linh commune to disseminate information and encourage residents not to obstruct the construction of the pillars and access roads at the T55 and T56 pillars of the Than Vu bridge.

Hầm Thần Vũ nhánh trái và hệ thống cầu đường kết nối sẽ giải quyết dứt điểm tình trạng ách tắc . Ảnh Nguyễn Toàn
The left-hand branch of the Than Vu Tunnel and the connecting bridge and road system will definitively resolve traffic congestion on the Dien Chau - Bai Vot expressway during peak periods. Photo: Nguyen Toan

Upon completion, the 8.2 km section will operate as designed, with the Than Vu tunnel featuring two two-way tunnels, each with three lanes. This will effectively resolve traffic congestion at the Than Vu tunnel junction during peak hours.