The Vinh urban sub-project has disbursed over $28 million.

March 8, 2016 08:25

(Baonghean.vn) - By the end of February 2016, the project had completed 67% of the time stipulated in the agreement, and the disbursed capital reached US$28,113 million, or 33.87% of the total capital.

Kênh Bắc đoạn 2 đã thi công xong
Section 3 of the North Canal has been completed.

According to information from the City People's Committee, the counterpart funding allocated is 675 billion VND, including: Central Government budget: 290 billion VND; Local budget (province and city): 385 billion VND, equivalent to 89.77%.

The project has completed the contractor selection and contract signing for all eight main consulting packages; currently, the progress of these packages is in line with the project schedule.

The city is undertaking projects such as: renovating and upgrading Cua Nam Lake, constructing a regulating lake and a 35m road, upgrading and renovating the canals surrounding Vinh ancient citadel...

Chau Lan