Vinh Urban Sub-Project - journey to destination

DNUM_ABZABZCABI 08:32

(Baonghean) - With great efforts, Nghe An province has issued Decision No. 4522/QD.UBND-CN on approving the Project on developing medium-sized cities in Vietnam - Vinh City Sub-Project, implemented from loans from the World Bank - WB and counterpart capital.

The project opens up great prospects in upgrading and renovating Vinh urban infrastructure, contributing to gradually building the city into an economic and cultural center of the North Central region.

The Vinh Urban Sub-Project includes 4 components: Component 1: Improving services and upgrading basic infrastructure; Component 2: Improving environmental sanitation, including: Upgrading and renovating the North Canal, building a regulating lake; upgrading and renovating the moat around Vinh Citadel, upgrading and renovating Cua Nam Lake; Component 3: Urban roads and bridges and Component 4: Capacity building and technical support.

By the end of 2017, many packages were completed such as: Construction of resettlement area in hamlet 5, Nghi Phu commune; School sanitation renovation; Upgrading and renovating Bac Canal section 1; Upgrading and renovating Bac Canal section 2, Bac Canal section 3; Upgrading and renovating ditch number 3; Upgrading the main pumping station and the new pumping station with a capacity of 10,500 m3/day and the self-flowing ditch to the main pumping station... Some remaining packages are actively under construction to complete early as committed.

Nghe An Newspaper introduces the following images reflecting the construction work of the components demonstrating the efforts of both the province and the city in implementing the Vinh Urban Sub-Project.

Chủ tịch UBND tỉnh Nguyễn Xuân Đường kiểm tra, chỉ đạo tiến độ dự án Tiểu đô thị Vinh. Ảnh: Xuân Hoàng
Chairman of the Provincial People's Committee Nguyen Xuan Duong inspects and directs the progress of the Vinh Sub-urban project. Photo: Xuan Hoang
Kênh Bắc đoạn 1 trở thành một công viên xanh với lối đi 2 bên. Ảnh: T.C
North Canal Section 1 becomes a green park with walkways on both sides. Photo: Tran Chau
Kênh Bắc đoạn 3 mới thi công xong. Ảnh: T.C
The newly completed North Canal section 3. Photo: Tran Chau
Khu tái định cư đường 35m ở xã Hưng Hòa đã hoàn thành. Ảnh: T.C
The resettlement area for 35m road in Hung Hoa commune has been completed. Photo: TC
Thi công cầu vượt đường sắt trên tuyến Vinh - Hưng Tây. Ảnh: T.C
Construction of a railway overpass on the Vinh - Hung Tay route. Photo: TC
Hồ Cửa Nam đã hoàn thành. Ảnh: T.C
Cua Nam Lake has been completed. Photo: TC