Why does the Khe Lai - Vuc Mau Lake Project have to extend the water blockage?

Van Truong - April 3, 2024 11:07
(Baonghean.vn) - According to the plan, the Khe Lai - Vuc Mau Lake Project (Hoang Mai town) will be closed and blocked from March 30, 2024. However, due to problems with site clearance, this project is allowed to extend the blocking from April 10, 2024.
Clip: Van Truong

Slow plan to block the line

Khe Lai Lake - Vuc Mau Projectin Tan Thang commune, Quynh Luu district, phase 1, invested by the Department of Agriculture and Rural Development. The purpose is to provide irrigation water for 1,524 hectares of cultivated land, including rice and industrial crops; at the same time, create a source of domestic water for 11,700 people in the surrounding area, supplementing the water source for Vuc Mau lake with a reserve of 13.4 million m3/year and participate in flood reduction on Hoang Mai River.

This project was approved in June 2009, started in 2010, with a total investment of more than 227.8 billion VND. However, due to many reasons, the project was behind schedule and had to be temporarily suspended in 2017.

bna_van truong mmnf.JPG
People still use Khe Lai lake area to grow short-term industrial crops. Photo: Van Truong

To continue building this project, on October 29, 2021, the Ministry of Agriculture and Rural Development issued Decision No. 4228 approving the adjustment of the Khe Lai - Vuc Mau Lake Project Phase 1. The total investment of the project is 627 billion VND, of which the cost of site clearance is more than 373 billion VND. According to the plan, the project will be put into use in 2024.

Quynh Luu District People's Committee is assigned to be responsible for compensation and site clearance. Since the beginning of 2022, Quynh Luu District has established a Compensation and Site Clearance Council; Focusing on clearing over 200 hectares of land in the Khe Lai reservoir area, mainly in Tan Thang commune, including forest land, agricultural land, and residential land.

bna_van truong 1.JPG
The mechanical part of the spillway of Khe Lai lake has been completed. Photo: Van Truong

From December 15, 2022 to this point, the site clearance work has completed the measurement and approval of land prices for project site clearance. Completed the inventory and field counting of 829/829 affected land plots, reaching a rate of 100%, and applied prices to 758/829 land plots, reaching a rate of 91.44%.

19 land recovery decisions have been issued with an area of ​​149.23 hectares, including: 2.48 hectares of residential land and garden land, 128.75 hectares of agricultural land, 18 hectares of production forest land. 20 decisions have been issued approving compensation, support and resettlement plans with an amount of 188.353 billion VND. Currently, 172.211 billion VND has been paid.

Currently, Quynh Luu district is completing documents to publicly announce compensation for site clearance with an area of ​​23.24 hectares/58 plots of land/16 households, with an amount of 21,982 billion VND.

On the construction side, the main dam is currently being built up to elevation 45 and reinforced soil is being filled to complete the upper and lower slopes. The mechanical part of the spillway has been completed, with an earth fill volume of over 300,000 m3.3, reaching over 60% of the volume.

According to the plan, Khe Lai - Vuc Mau Lake Project (Hoang Mai town) will be closed and blocked from the date ofMarch 30, 2024, however, due to land clearance problems, there are not enough conditions to close the canal and block the stream, so the Department of Agriculture and Rural Development must continue to extend the blocking until April 10, 2024.

bna_van truong 2.JPG
The Khe Lai - Vuc Mau Lake project in Tan Thang commune is still stuck in land clearance for forest land. Photo: Van Truong

Focus on removing difficulties and determining land origin

A representative of the Department of Natural Resources and Environment of Quynh Luu district said: Immediately after receiving the task of compensation and site clearance, the People's Committee of Quynh Luu district actively took part, however, the compensation and site clearance work of the Khe Lai - Vuc Mau Lake Project is still facing many difficulties.

The project currently has 215.82 ha/137 households and 74.8 ha of forest land that have not been recovered, of which 32.11 ha is natural forest, so the procedure for changing the forest purpose must be submitted to the Prime Minister for decision. Nghe An Provincial People's Committee has sent the Ministry of Agriculture and Rural Development an explanatory document. In which, it is recommended that the Prime Minister approve the policy of changing the forest use purpose to another purpose.

bna_van truong 5.JPG
The main dam is under construction at elevation 45 and the reinforced soil has been completed on the upper and lower slopes. Photo: Van Truong

There are still 7 households in the reservoir area complaining about compensation from agricultural land to residential land. The district has established a team to verify the content of the complaints about the project's compensation and site clearance for the 7 households complaining above.

In the project implementation area, in 2003, the Provincial People's Committee issued Decision 1805 allowing the conversion of forest land to agricultural land, but currently the conversion map has been lost, making it difficult to determine the land type and land use process.

bna_van truong 45.jpeg
Officials from the Compensation and Site Clearance Council of Quynh Luu district visited a household in the Khe Lai reservoir area to mobilize and promote relocation. Photo: Van Truong

The work of determining the origin of land by the People's Committee of Tan Thang commune is still slow, in some cases the origin is not determined accurately (there are 180 plots of land without origin); determining resettlement conditions is still incorrect and needs to be adjusted.

The reason for the slow site clearance of the Khe Lai Lake - Vuc Mau Project is due to the difficulty in determining the land owner and the origin of the land. For example, in the lake area, many plots of land do not have records or land allocation papers. Some plots of land have differences in land types on different maps, leading to difficulties in determining the land type for compensation and support, not to mention that previously, land was bought and sold without going through the government.

bna_van truong 3.JPG
The location will close and block the water flow of Khe Lai reservoir. Photo: Van Truong

The early blocking and closing of the Khe Lai - Vuc Mau Lake Project plays a very important role. In addition to storing water for production and daily life, the project also proactively responds to extreme weather...

In order to complete the project of blocking the flow on schedule from April 10, 2024, the People's Committee of Quynh Luu district is focusing on the remaining tasks such as: Extracting and supplementing incorrect land plots, completing the review of forest conversion. Directing the People's Committee of Quynh Thang commune to complete the work of determining the origin of land plots for site clearance. Pricing and approving plans, land recovery of the remaining land plots...