225 days on the construction site of the 500kV circuit 3 power line.

Reporters Team August 28, 2024 17:07

After 225 days of construction, the 500kV circuit 3 transmission line project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) has been energized and is fully operational along the entire route.

dji_0365(1).jpg
The Quang Trach - Quynh Luu 500kV transmission line project is the final component of the 500kV circuit 3 transmission line project from Quang Trach to Pho Noi. The Quang Trach - Quynh Luu project spans 226 km, passing through the provinces of Quang Binh, Ha Tinh, and Nghe An. The project includes 463 tower foundation locations, of which 237 are located through mountainous terrain and complex landscapes. Of the 197 spans along the transmission line corridor, 7 spans cross large rivers and lakes, and 15 spans cross national highways. (Photo: Cuong Dao)
bna_6973.jpg
The project commenced construction on January 18, 2024, and was approved for commissioning by the investor's acceptance council on August 24, 2024. Photo: Cuong Dao
bna_7027.jpg
In Nghe An province, the project, approximately 100km long, includes 202 tower foundation locations and 85 corridor anchor points, passing through 6 districts and towns: Hoang Mai, Quynh Luu, Yen Thanh, Dien Chau, Nghi Loc, and Nam Dan. Photo: Cuong Dao
Trong quá trình triển khai, dự án luôn nhận được sự quan tâm chỉ đạo của Thủ tướng Chính phủ, các bộ, ngành, lãnh đạo Tập đoàn Điện lực Việt Nam. Cùng với đó là sự ủng hộ của các cấp chính quyền nơi có dự án đi qua, sự đồng lòng, chung sức của người dân đã nhường đất cho dự án, đã tham gia hỗ trợ thi công giai đoạn đào đúc móng. Ảnh: Thành Duy
Throughout its implementation, the project consistently received attention and guidance from the Prime Minister, ministries, and leaders of the Vietnam Electricity Group. This was coupled with the support of local authorities in the project areas, and the cooperation of the people who ceded land for the project and participated in supporting the excavation and foundation construction phase. Photo: Thanh Duy
_nda8653(1).jpg
To meet the required deadline, many work items were implemented simultaneously within a short period, such as construction, pole erection, wire pulling, frame installation, and technical adjustments. Photo: Cuong Dao
_nda9556(1).jpg
Besides the main workforce of the construction contractors, a large number of skilled and experienced personnel from EVNNPT and 5 Power Corporations were mobilized to support the construction. Photo: Cuong Dao
_nda1454(1).jpg
Besides favorable factors, the project faced many difficulties and challenges during implementation, including mobilizing machinery and equipment for simultaneous construction along the entire route; difficulties related to the terrain, with many locations on high hills and mountains; and challenging access to the foundation sites, especially during rainy weather when the roads are steep, slippery, and the construction surface is unfavorable. (Photo: Cuong Dao)
_nda1317(1).jpg
Adverse weather conditions, including many rainy days, storms, thunderstorms, extreme heat, and days with strong winds lasting 3 to 7 hours, as well as lightning strikes, have forced construction to halt at numerous times to ensure the safety of workers and equipment. (Photo: Cuong Dao)
_nda1965(1).jpg
The project also faced difficulties in mobilizing construction workers to erect poles and lay wires due to the tight construction schedule, short implementation time, and the simultaneous construction volume of poles and wires for other large projects. Photo: Cuong Dao
_nda0951(1).jpg
Furthermore, given the enormous volume of steel poles required and the tight deadline for delivery, EVNNPT, CPMB, and the contractors have made concerted efforts to focus on production and implement specific solutions to accelerate the manufacturing process. Photo: Cuong Dao
Ảnh: TC
Photo: TC
_nda0917(1).jpg
Photo: Cuong Dao
_nda1004(1).jpg
Photo: Cuong Dao
dji_0897-2(1).jpg
Photo: Cuong Dao
bna_anh-thanh-chung-3-526f8cc48dddc288e0430cec8943e0c2.jpg
Given the importance of the project, Vietnam Electricity also received manpower support from the Army, the Youth Union, and local authorities... who participated in erecting poles and laying wires for the projects. Photo: Thanh Chung
1000056869(1).jpg
The Quang Trach - Quynh Luu 500kV transmission line project is the final component project of the 500kV circuit 3 transmission line project from Quang Trach to Pho Noi. Prior to this, EVNNPT completed the energization of the Thanh Hoa 500kV substation on June 28, 2024, the Nam Dinh 1 Thermal Power Plant - Thanh Hoa 500kV transmission line project on June 30, 2024, and the Quynh Luu - Thanh Hoa 500kV transmission line and Nam Dinh 1 Thermal Power Plant - Pho Noi energized transmission line projects on August 19, 2024. Photo: Cuong Dao
Kỳ tích 500kV - 8
Photo: TC
1000057751.jpg
Upon completion, the project will help reduce the load and prevent overloading of existing 500kV transmission lines, ensuring the N-1 criterion, especially when transmission capacity is high along the Central-Northern interface at times when hydropower plants in the North are operating at low levels. Photo: Cuong Dao
Ảnh: T
Leaders of Nghe An province and Vietnam Electricity Group cut the ribbon to inaugurate the 500kV circuit 3 transmission line projects passing through Nghe An. Photo: TC