225 days on the construction site of 500kV line circuit 3

Reporter Group August 28, 2024 17:07

After 225 days of construction, the 500kV Transmission Line Project, Circuit 3, Quang Trach (Quang Binh) to Pho Noi (Hung Yen) has been energized and the entire line is fully operational.

dji_0365(1).jpg
The 500kV Quang Trach - Quynh Luu transmission line project is the final component project of the 500kV line project circuit 3 from Quang Trach to Pho Noi. The Quang Trach - Quynh Luu project is 226 km long, passing through the provinces of Quang Binh, Ha Tinh, and Nghe An. The project has 463 column foundation locations, of which 237 column locations cross mountains, passing through many complex terrains. Of the 197 corridor anchorages, 7 anchorages cross rivers and large lakes, and 15 anchorages cross national highways. Photo: Cuong Dao
bna_6973.jpg
The project was implemented from January 18, 2024, and the investor-level Acceptance Council met on August 24, 2024 and agreed to connect to the power grid. Photo: Cuong Dao
bna_7027.jpg
In Nghe An province, the project is about 100km long, including 202 column foundation positions and 85 corridor anchorages, passing through 6 districts and towns: Hoang Mai, Quynh Luu, Yen Thanh, Dien Chau, Nghi Loc, Nam Dan. Photo: Cuong Dao
Trong quá trình triển khai, dự án luôn nhận được sự quan tâm chỉ đạo của Thủ tướng Chính phủ, các bộ, ngành, lãnh đạo Tập đoàn Điện lực Việt Nam. Cùng với đó là sự ủng hộ của các cấp chính quyền nơi có dự án đi qua, sự đồng lòng, chung sức của người dân đã nhường đất cho dự án, đã tham gia hỗ trợ thi công giai đoạn đào đúc móng. Ảnh: Thành Duy
During the implementation process, the project has always received the attention and direction of the Prime Minister, ministries, branches, and leaders of Vietnam Electricity Group. Along with that is the support of authorities at all levels where the project passes through, the consensus and joint efforts of the people who have given up land for the project, and participated in supporting the construction of the foundation excavation phase. Photo: Thanh Duy
_nda8653(1).jpg
To meet the required progress, in a short period of time, many work items were deployed simultaneously such as construction and installation, pole erection, wire pulling, positioning frame installation, and technical calibration. Photo: Cuong Dao
_nda9556(1).jpg
In addition to the main force of construction contractors, forces from EVNNPT and 5 Power Corporations have been mobilized to participate in the construction support with a large number of qualified, experienced and skilled human resources. Photo: Cuong Dao
_nda1454(1).jpg
Besides the favorable factors, during the implementation process, the Project encountered many difficulties and challenges in mobilizing machinery and construction equipment simultaneously on the entire route; Difficult terrain of the route with many locations on high hills and mountains, difficult roads to the column foundation locations, especially difficult when it rains, the roads are steep, slippery, and the construction site is not favorable. Photo: Cuong Dao
_nda1317(1).jpg
Unfavorable weather conditions included many days of rain, storms, thunderstorms, extreme heat, many days of strong winds lasting from 3 to 7 hours, and thunderstorms, so construction had to be stopped at many times to ensure the safety of workers and construction equipment. Photo: Cuong Dao
_nda1965(1).jpg
The project also faced difficulties in mobilizing construction forces to erect poles and pull wires due to urgent construction progress, short implementation time, and the volume of construction work to erect poles and pull wires simultaneously for large projects. Photo: Cuong Dao
_nda0951(1).jpg
Along with that, the volume of steel columns is very large while the progress requires supplying columns in a short time, EVNNPT together with CPMB and contractors have made efforts to focus on production, implementing specific solutions to speed up production progress. Photo: Cuong Dao
Ảnh: TC
Photo: TC
_nda0917(1).jpg
Photo: Cuong Dao
_nda1004(1).jpg
Photo: Cuong Dao
dji_0897-2(1).jpg
Photo: Cuong Dao
bna_anh-thanh-chung-3-526f8cc48dddc288e0430cec8943e0c2.jpg
Given the importance of the project, Vietnam Electricity also received construction manpower support from the Army, Youth Union, local authorities, etc. to participate in supporting the erection of poles and pulling of wires for the projects. Photo: Thanh Chung
1000056869(1).jpg
The 500kV Quang Trach - Quynh Luu transmission line project is the last component project of the 500kV line circuit 3 project from Quang Trach to Pho Noi. Previously, EVNNPT completed energizing the Thanh Hoa 500kV transformer station on June 28, 2024, the Nam Dinh 1 - Thanh Hoa 500kV transmission line project was completed on June 30, 2024, the Quynh Luu - Thanh Hoa 500kV transmission line project and the Nam Dinh 1 - Pho Noi power plant were completed energizing on August 19, 2024. Photo: Cuong Dao
Kỳ tích 500kV - 8
Photo: TC
1000057751.jpg
Once completed, the project will help reduce the load and avoid overloading of existing 500kV lines, ensuring the N-1 criteria, especially when the transmission capacity is high along the Central - North interface at a time when hydropower plants in the North have low generation. Photo: Cuong Dao
Ảnh: T
Leaders of Nghe An province and Vietnam Electricity Group cut the ribbon to inaugurate the 500kV line projects, circuit 3, through Nghe An. Photo: TC