(Baonghean.vn) - After the Nghe An Oncology Hospital Construction Project Phase 2 comes into operation, it will complete a closed cycle from diagnosis to cancer treatment, creating convenience in examining and treating oncological diseases for people in Nghe An province and neighboring areas.

With the goal of becoming the final hospital specializing in oncology in the North Central region, a "smart hospital", a "hotel hospital", becoming one of the key and typical medical infrastructure projects of the regional and national health sector, meeting the needs and satisfaction of patients - Nghe An Oncology Hospital has had many solutions to promote the disbursement of public investment capital; considering this an important task in the work of medical examination and treatment for the people.

IMPORTANT TASKS

In investing in infrastructure development and construction of Nghe An Oncology Hospital phase 2, public investment resources from the State budget are an important resource for the Hospital.

bna-chu-tich-ubnd-tinh-nguyen-duc-trung-kiem-tra-tien-do-thuc-hien-du-an-benh-vien-ung-buou-nghe-an-giai-doan-2-anh-cscc-7605.jpg
Chairman of the Provincial People's Committee Nguyen Duc Trung inspected the progress of the Nghe An Oncology Hospital Project Phase 2. Photo: CSCC

The Nghe An Oncology Hospital Construction Project Phase 2 was started on January 31, 2023 with many items and projects being built. Among them, many important items have been and are being deployed and put into use, creating conditions not only for people with cancer to enjoy the best medical services right in the province but also creating connections between regions and areas in the North Central region. The project is of great significance, contributing to the overall development of the Nghe An province's health sector in the spirit of Resolution 26 of the Politburo.

The Nghe An Oncology Hospital Construction Project Phase 2 was approved by the Nghe An Provincial People's Committee in Decision No. 4035/QD-UBND dated October 29, 2021. It is a Group A project, a civil construction project, a level 1 main project, with a scale of 1,000 hospital beds, with a total investment of VND 1,259 billion. Of which, the central budget is VND 1,000 billion, the local budget is VND 259 billion.

According to Associate Professor, Dr. Nguyen Quang Trung - Director of Nghe An Oncology Hospital, the investment in building the second phase of the hospital is extremely urgent in the face of the increasing rate of cancer. According to statistics from GLOBOCAN - the Global Cancer Research Organization, as of 2020, in Vietnam, there were 182,563 new cancer cases and 122,690 deaths from this disease.

bna-mo-hinh-bv-ub-nghe-an-gd-2-khi-hoan-thien-tro-thanh-1-trong-nhung-co-so-dieu-tri-ut-trong-diemcua-nganh-y-te-nghe-an-va-khu-vuc-bac-trung-bo-anh-cscc-7163.jpg
The Nghe An Oncology Hospital model phase 2, when completed, will become one of the key cancer treatment facilities of the Nghe An health sector and the North Central region. Photo: CSCC

Cancer treatment is a multimodal treatment, including surgery, chemotherapy, radiotherapy, etc. Therefore, after the Nghe An Oncology Hospital Construction Project Phase 2 comes into operation, it will complete a closed cycle from diagnosis to cancer treatment, creating convenience in examining and treating cancer diseases for the people of Nghe An province and neighboring areas. People will benefit from treatment methods of modern medicine right in their hometown; helping to shorten the distance and reduce treatment costs, reducing overload for specialized cancer hospitals at the central level.

Speeding up the disbursement of public investment capital

In 2023, Nghe An Oncology Hospital disbursed public investment capital for the construction of the second phase of the hospital ahead of schedule, reaching 100%. The main building has completed 100% of the reinforced concrete frame; the masonry and plastering work has reached 80% of the work; the electricity and water works have reached 60% of the work.

Speeding up the construction progress according to the set goals, Nghe An Oncology Hospital strives to complete the disbursement of public investment capital according to the signed commitments, seriously and drastically implementing tasks and solutions, proactively overcoming difficulties and obstacles to focus on directing the acceleration of project implementation progress, striving to achieve the disbursement target for 2023 - 2025 from 95 - 100% according to the direction of the Government.

Along with the items that have been invested in construction in phase 1 such as: 5-storey Radiotherapy and Nuclear Medicine Center, with a scale of 250 beds; Security and Entertainment Area; Technical Infrastructure, Wastewater Treatment Station, when phase 2 of the project is completed, the technical infrastructure items will be synchronized, increasing the capacity of the wastewater treatment station to 600m3/day and night. In particular, the main 8-storey building with 1,000 beds will be put into use, as well as dormitories for staff and workers, guest houses, funeral homes, green parks, gyms, sports areas, etc.

du-an-benh-vien-ung-buou-nghe-an-giai-doan-2-thuc-hien-thi-cong-tai-dia-chi-k456-xa-nghi-lien-tp-vinh-tinh-nghe-an-anh-csccjpg-3118.jpg
Nghe An Oncology Hospital Phase 2 project is under construction at Km456, National Highway 1A, Nghi Lien Commune (Vinh City). Photo: CSCC

Following the motto of taking the patient as the center, taking treatment effectiveness and patient satisfaction as the measure of value and the goal to strive for, Nghe An Oncology Hospital always cultivates medical ethics; attracts high-quality human resources, improves the professional quality of the medical team and doctors; successfully deploys advanced surgical and treatment methods in cancer treatment.

Focus on expanding scientific research, training, and guidance movements; especially technology transfer to lower-level hospitals; expand international cooperation, seek support, and learn from experiences of advanced countries.

Ensure benefits for health insurance card holders, policy beneficiaries, and poor households; fulfill social responsibilities, mobilize resources to support cancer patients, children in difficult circumstances, remote areas, and ethnic minorities to access quality specialized medical services at reasonable costs.

The results of implementing items in the public investment project and disbursing public investment in 2023 have contributed to further completing the infrastructure of the new Nghe An Oncology Hospital, creating motivation for cancer patients being treated at the hospital; creating a premise for Nghe An Oncology Hospital to develop even more strongly in the coming time.

In the future, with a spacious infrastructure, modern advanced medical equipment, in-depth expertise and tireless efforts for patients by the staff, Nghe An Oncology Hospital strives to become a model, modern hospital on par with advanced hospitals in the region and the whole country.

The hospital will also strive to become the “leading bird” of the Nghe An province health sector, a bright spot in the work of protecting, caring for and improving the health of people in President Ho Chi Minh’s homeland; worthy of the trust of the Party, the State and the trust and affection of the people.